Pikes Peak Regional Building Department

Pikes Peak permit action guide

Move From Project Idea to PPRBD Final Inspection Without Missing Zoning, Floodplain or Plan Review

PPRBD is a regional code and inspection agency—not the zoning or fire department. Your project may need approval from the city, town, county, fire authority, floodplain office and PPRBD in the correct order.

This guide shows the exact path for permit checks, electronic plans, homeowner permits, contractor verification, fee estimates, same-day inspection scheduling, mountain snow and wind design, corrections and final closeout.

Serving nine current regional jurisdictions
2023 PPRBC, 2nd Printing now effective
Permit, plan and inspection status decoded
Pikes Peak permit route from mountain-site plans to final inspection A mountain site plan, snow and wind design shield, electronic plan review and final inspection animate in sequence. MOUNTAIN SITE PLAN E-PLAN REVIEW APPROVED PLAN FILE SNOW + WIND FINAL INSPECTION FINAL
📘
Current code update Effective June 30, 2026, PPRBD uses the 2023 Pikes Peak Regional Building Code, 2nd Printing, with the 2021 IBC/IRC/IEBC/IMC/IFGC/IPC/IECC, 2023 NEC and 2021 pool code adopted by reference.
Start here

Choose the Exact PPRBD Task

PPRBD Next-Step Finder

Select the project or problem. The result gives the first official action.

Regional jurisdiction

PPRBD Handles Building Codes—Local Agencies Still Handle Land Use and Fire Review

Current PPRBD service jurisdictions

  • Colorado Springs
  • Unincorporated El Paso County
  • Fountain
  • Woodland Park
  • Manitou Springs
  • Monument
  • Green Mountain Falls
  • Palmer Lake
  • Calhan

PPRBD usually handles

  • Building permits
  • Residential and commercial plan review
  • Building inspections
  • Electrical inspections
  • Mechanical inspections
  • Plumbing inspections
  • Contractor licensing or registration
  • Regional floodplain review

Contact the local jurisdiction for

  • Zoning and land use
  • Setbacks and lot coverage
  • Planning or site approval
  • Fire-code plan review
  • Historic requirements
  • Public works and utilities
  • Local use tax
  • HOA restrictions
Do not treat PPRBD approval as zoning approval. The residential plan-review guide says site-specific plans also require the zoning authority in the jurisdiction where the property is located, and Fire Code requirements are reviewed by the applicable fire authority.
Official contacts

Pikes Peak Regional Building Department Phone Numbers and Offices

Main number 719-327-2880 General help and inspection scheduling
Permit counter 719-327-2883 7:30 AM–4:15 PM
Plan Review 719-327-2885 Appointment only
Contractor Licensing 719-327-2887 7:30 AM–4:15 PM
Floodplain 719-327-2898 Appointment only
Enumeration 719-327-2960 Addressing, by appointment
Inspector office hours 7:30–8:30 AM Building, electrical, mechanical, plumbing and elevator
Main office 2880 International Circle Colorado Springs, CO 80910
North office: 3939 Cordera Crest Avenue, Colorado Springs, CO 80924. Call first to confirm which services are available at the North Office.
Permit decision table

Which Projects Commonly Need a PPRBD Permit?

Project
Likely route
Check before filing
New home, addition or structural alteration
Building plan + permit
Zoning, address, floodplain, fire authority, soils, snow/wind design and energy
Basement finish or garage conversion
Residential plan review
Room use, egress, heating, plumbing, electrical and fee-calculator inputs
Deck, patio cover or enclosed patio
Residential permit/plan
Zoning setbacks, attachment, foundations, snow load and required inspections
Detached garage, shed or greenhouse over 200 sq. ft.
Accessory structure permit
Zoning approval, foundation, setbacks, utilities and floodplain
Roof replacement
Roofing permit
Roof system, solar interaction, sheathing and inspection requirements
Electrical, plumbing, mechanical, furnace or water heater
Trade permit
Who is allowed to obtain the permit and whether a building permit is related
Pool or hot tub
Pool/spa plan and permit
Zoning, barrier, electrical, mechanical and floodplain
Retaining wall over 4 feet
Building permit
Height measurement, surcharge, drainage, engineering and zoning
Commercial remodel or change of occupancy
Commercial plan review
Zoning, fire authority, accessibility, occupant load, energy and trade plans
Work inside a mapped floodplain
Floodplain review first
Floodplain Development Permit, elevations, fill and design documentation
Possible permit exemptions

Work That May Not Need a Building Permit Still May Need Zoning or Floodplain Approval

Official Start-a-Project examples

  • Painting
  • Flooring and carpeting
  • Cabinets and countertops
  • Window and door replacement
  • Minor cosmetic repairs
  • Fence not more than 7 feet
  • Detached accessory structure up to 200 sq. ft., directly on grade
  • Some minor plumbing or heating repairs

Local exceptions to remember

  • Colorado Springs zoning approval is identified for detached structures of 125 sq. ft. or more.
  • Colorado Springs zoning approval is identified for fences 6 feet or higher.
  • Floodplain review can apply even when the building code does not require a permit.
  • Electrical, plumbing or mechanical work may require a separate trade permit.
Safe rule: Use the official Start a Project tool and confirm zoning before treating work as exempt.
Electronic plan review

Submit an Electronic Plan Without Creating a Review Delay

Create the correct web-account type

Electronic plans may be submitted by eligible homeowners, licensed contractors or Colorado design professionals. Available plan types depend on the account, license, project and jurisdiction.

Choose Plans → Electronic Plans → New Plan

Select New or Remodel, then the exact plan type. Use the project-specific walkthrough that appears beside the selection.

Enter the site and contacts

Add the project address for site-specific plans. New-construction addresses are checked during Enumeration review.

Upload the required PDFs

Upload the requested application, plans and supporting files. PPRBD notes that locked PDFs often cannot be marked up or merged into the approved plan.

Before upload: Combine coordinated plan sheets, use clear names and confirm every PDF opens.

Submit the plan—not only save it

A new plan starts as Incomplete. Review does not begin until the green Submit Plan action changes it to Submitted/Triage.

Wait for the full review cycle

During review, new uploads are usually blocked. PPRBD generally waits for all required departments before returning a combined correction set, except certain Enumeration or Floodplain disapprovals may return earlier.

Correct original files and resubmit

Revise the original plan documents, not the marked-up review set. Replace every disapproved required document and add a clear resubmittal comment.

Download the final approved plan

Some permits can be issued online; many still require permit pickup. Keep a hard-copy approved plan set at the job site when required for inspections.

Plan status decoder

What the Electronic Plan Status Means

Incomplete Edit information and upload files. The plan has not entered review.
Submitted / Triage PPRBD is checking whether the initial package is complete enough to enter plan tracking.
Open The plan is in active review. Follow required departments and log entries online.
Disapproved / returned to Incomplete Download the combined Review Set, correct original documents and resubmit.
Approved The plan is released for a permit type that allows online issuance.
Closed The electronic review has ended after approval or cancellation; permit information carries forward separately.
Regional design criteria

Put Pikes Peak Snow and Wind Criteria on the Submittal Documents

Design condition
Current PPRBD basic criterion
Action
Grade plane below 7,000 feet
Ground snow load 43 psf; flat-roof snow load 30 psf
Show elevation and applicable balanced, unbalanced and drift design
Grade plane at or above 7,000 feet
Ground snow load 57 psf; flat-roof snow load 40 psf
Use the higher-elevation criterion and coordinate site-specific engineering
Risk Category I or II
130 mph ultimate basic wind speed
State risk category, wind speed and components/cladding design
Risk Category III
135 mph ultimate basic wind speed
Confirm classification with the design professional
Risk Category IV
140 mph ultimate basic wind speed
Use essential-facility design requirements
Wind exposure
Exposure C required in the current basic-design sheet
Do not substitute a lower exposure without approved code basis
Mountain-site warning: Elevation, drifting, topography, expansive soils, wildfire requirements and local fire-authority rules can materially change the design. Use the current PPRBD documents and a Colorado-licensed design professional when required.
Permit fees and use tax

Estimate PPRBD Fees, Then Add the Correct Jurisdiction’s Use-Tax Step

Selected Table A fee tiers

  • $1–$500 valuation: $50.
  • $501–$2,000: $50 for first $500 + $2 per additional $100 or fraction.
  • $2,001–$25,000: $80 for first $2,000 + $8 per additional $1,000 or fraction.
  • $25,001–$50,000: $264 for first $25,000 + $8 per additional $1,000 or fraction.
  • $50,001–$100,000: $464 for first $50,000 + $5 per additional $1,000 or fraction.

Use the official fee calculator

Why the calculator is still only an estimate

  • Final valuation is set by the Building Official.
  • Combined scopes can calculate differently from separate estimates.
  • Trade permits, plan review and outside-agency fees can apply.
  • Local use tax varies by jurisdiction.
  • Woodland Park can use a jurisdiction-specific fee schedule.
Jurisdiction
Use-tax action before or during permit issuance
El Paso County
Select the affidavit or job-material-valuation method; contact El Paso County Use Tax with questions
Fountain
May be paid during local review or collected when PPRBD issues the permit
Green Mountain Falls
Collected by PPRBD when the permit is issued
Manitou Springs
Pay through Manitou Springs before PPRBD permit issuance
Monument
Pay through Monument before PPRBD permit issuance
Palmer Lake
Pay through Palmer Lake before PPRBD permit issuance
Woodland Park
Collected when the permit is issued at Woodland Park or PPRBD
Inspection scheduling

Request the Inspection Before the 8:30 AM Same-Day Cutoff

Confirm the permit is Open

PPRBD defines Open as active and paid, meaning work can begin and inspections can be requested.

Use the account that purchased the permit

The party that purchased the permit can request the inspection online or by phone. A homeowner cannot schedule when the contractor obtained the permit.

Request online or call 719-327-2880

Online: sign in, open Permits, select the permit and choose Request Inspection. Have the permit number ready when calling.

Schedule by 8:30 AM for possible same-day service

Inspections can be booked in advance. Weekday same-day requests have an 8:30 AM cutoff.

Check estimated arrival after 9:00 AM

Routes are set geographically. The published time is an estimate and can change.

Use the call-ahead option

An automated call can arrive about 60 minutes before the estimated arrival. The published caller number is 719-301-4403.

Keep the approved plan and work visible

Provide safe access, required ladders and the approved hard-copy plans. Do not conceal work that must be inspected.

Find the correct inspection code first: Use PPRBD’s Required Inspections by Project tool instead of guessing at framing, rough, final or trade codes.
Homeowner permits

A Homeowner Permit Is Only for Work You Personally Perform on Your Primary Residence

You may qualify when

  • You own the residence
  • You currently live there
  • It is your primary residence
  • You personally perform the permitted work
  • You understand the applicable code
  • You accept inspection responsibility

You do not qualify when

  • The property is a rental
  • You do not reside in the home
  • A contractor will perform licensed work
  • You are pulling the permit for a contractor
  • The entity is operating a business
  • The project exceeds homeowner-permit authority
Do not “help” an unlicensed contractor by pulling the permit. PPRBD states that it is illegal for a homeowner to obtain a homeowner permit for a hired contractor. Unpermitted work can trigger a stop-work order and a recorded Certificate of Alleged Non-compliance.
Contractor verification

Check PPRBD License or Registration Status Before Signing the Contract

Search the exact business

Confirm the legal business name, license or registration type and current standing.

Search contractors

Match scope to license

A general, mechanical, electrical, plumbing, fire or specialty scope can require different PPRBD or Colorado credentials.

Close old permits

Outstanding administratively closed permits or fines can block contractor license or registration renewal.

Permit status decoder

What the PPRBD Permit Status Means

Open The permit is active and paid. Work can begin and inspections can be requested.
Pending An attachment or approval from another department is missing. Work cannot begin.
Final All requirements and inspections are complete; no further action is needed.
Void The permit is invalid, cancelled or no longer required.
Admin-Closed No inspections occurred for 180 days. The permit lacks a final inspection and must be reopened to continue.
Admin-Closed (Renewed) Reopening fees were paid, but an inspection result is still needed to fully reopen the permit.
Locked PPRBD suspended work or inspections because of a permit-related problem. Call 719-327-2880.
Open permit during property sale Verify the final inspection—not only that a permit was purchased or work appears complete.
Floodplain and addressing

Check Floodplain and Addressing Before the Plan Gets Stuck

Floodplain Management

Proposed alterations or construction in a mapped floodplain must be reviewed. Most projects require a Floodplain Development Permit, including buildings, additions, excavation, fill, extensive landscaping, fences, roads and bridges.

Phone: 719-327-2898
Open floodplain mapping

Enumeration and addresses

New buildings and many standalone structures or separately metered equipment need an assigned or verified address. Enumeration also handles suite and unit numbers.

Phone: 719-327-2960
Open public GIS

Troubleshooting

Fix Common PPRBD Permit, Plan and Inspection Problems

Problem
Likely cause
Best next action
Plan stays Incomplete
It was saved but not submitted, or required documents are missing
Open Electronic Plans, add required PDFs and click Submit Plan
Plan returned before other reviews
Enumeration or Floodplain disapproved a controlling item
Resolve the address or floodplain issue before resubmission
Cannot upload during review
The current review cycle is still open
Wait until the plan returns to Incomplete, then upload corrected originals
Permit is Pending
A local zoning, tax, fire or other attachment is missing
Open attachments and contact the outside department shown
Homeowner cannot request inspection
The contractor purchased the permit
Ask the permit purchaser to schedule it
Permit became Admin-Closed
No inspections occurred for 180 days
Reopen online within the first year or call a permit technician
Permit is Locked
PPRBD suspended further work or inspections
Call 719-327-2880 and resolve the stated problem before continuing
Old work appears unpermitted
No permit or final inspection is in the record
Search permit and plan records, then ask PPRBD for a compliance path
Ready-to-use scripts

What to Say When You Contact PPRBD or a Local Agency

Permit requirement
“I plan to [exact work] at [address and jurisdiction]. Can you confirm whether PPRBD requires a permit or plan review and which zoning, fire, floodplain or use-tax approval must come first?”
Plan correction
“Electronic plan [number] was returned. I revised the original files and addressed each department comment. Please confirm whether Enumeration, Floodplain or another controlling review remains unresolved.”
Inspection request
“I need inspection code [code] for permit [number]. The work is complete for that stage, exposed and accessible. The approved plans are on site, and the call-ahead number is [phone].”
Admin-closed permit
“Permit [number] is administratively closed. Which fee and inspection are required to reopen it and obtain the missing final approval?”
Final closeout

Do Not Consider the Project Complete Until These Items Are Confirmed

  • Correct PPRBD jurisdiction confirmed
  • Zoning and fire approvals confirmed
  • Floodplain review completed if triggered
  • Address assigned or verified
  • Correct permit and plan type selected
  • Snow, wind and energy criteria shown
  • Electronic plan formally submitted
  • All review comments resolved
  • Permit status changed to Open
  • Approved plans kept on site
  • Required building and trade inspections passed
  • Use tax completed for the jurisdiction
  • Certificate of Occupancy obtained when required
  • Permit status shows Final
Office map

PPRBD Main Office and North Office

Main office:
2880 International Circle
Colorado Springs, CO 80910
North office:
3939 Cordera Crest Avenue
Colorado Springs, CO 80924
Official resources

Open the Correct PPRBD Tool or Document

FAQs

Pikes Peak Regional Building Department Questions

Which jurisdictions are currently served by PPRBD?

PPRBD currently lists Colorado Springs, El Paso County, Fountain, Woodland Park, Manitou Springs, Monument, Green Mountain Falls, Palmer Lake and Calhan. Local zoning, planning, fire and tax requirements still vary by jurisdiction.

How do I find out whether my project needs a permit?

Use PPRBD’s official Start a Project tool. It asks whether the project is exempt, whether plans are required, the project details and whether the permit or plan can be submitted online.

Can a homeowner obtain a PPRBD permit?

Yes, when the homeowner owns and resides in the primary residence and personally performs the work. A homeowner permit cannot be used for a rental property or pulled for a hired contractor.

How do I submit plans electronically?

Create a web account, open Plans, choose Electronic Plans and New Plan, select the project type, upload the required PDF documents and click Submit Plan. Saving the plan without submitting leaves it Incomplete.

What is the same-day PPRBD inspection cutoff?

The weekday cutoff for same-day inspection scheduling is 8:30 AM. Inspections can also be scheduled in advance.

Who is allowed to schedule the inspection?

The party that purchased the permit can schedule online or by phone. A homeowner cannot schedule an inspection when a contractor purchased the permit.

What does Admin-Closed mean on a PPRBD permit?

A permit becomes administratively closed after 180 days without inspections. It did not receive a final inspection and must be reopened before inspections continue. Fees may apply.

What building codes does PPRBD currently use?

Effective June 30, 2026, the current regional code is the 2023 Pikes Peak Regional Building Code, 2nd Printing. It adopts the 2021 IBC, IRC, IEBC, IMC, IFGC, IPC and IECC, the 2023 NEC and the 2021 International Swimming Pool and Spa Code, among other standards.

What snow and wind values should appear on PPRBD plans?

The current basic-design sheet lists ground and flat-roof snow loads of 43 and 30 psf below 7,000 feet, and 57 and 40 psf at or above 7,000 feet. It lists ultimate wind speeds of 130, 135 or 140 mph by risk category and Exposure C.

Does a permit-exempt project still need zoning approval?

It can. PPRBD specifically notes local zoning thresholds for certain Colorado Springs fences and accessory structures, and floodplain review can apply even when a building permit is not required.

Source and accuracy note

Official Information Used for This Guide

Building-Department.org is an independent informational guide and is not Pikes Peak Regional Building Department.

This page was checked against PPRBD’s current homepage, Start a Project tool, Electronic Plan Review guide, fee schedule and calculator, homeowner guidance, permit-status definitions, inspection instructions, adopted-code page, design criteria, residential plan-review packet, hours, GIS and floodplain resources.

Last reviewed: July 23, 2026.

Codes, local approvals, use tax, fees, plan types and inspection procedures can change. Confirm time-sensitive requirements with PPRBD and the property’s city, town or county before filing or starting work.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.