Miami Beach Building Department: Permit Search & Permits

City of Miami permit action guide

Move From iBuild Application to Miami Inspection, Certificate and Final Permit Closure

This guide is for properties inside the City of Miami—not Miami-Dade County, Miami Beach, Coral Gables or another municipality.

Start with the exact task you need: use an Easy Permit, get a same-day residential review, submit plans through ProjectDox, search an old permit, schedule an inspection, request an extension or obtain a Certificate of Occupancy or Completion.

iBuild application, payment and permit tracking
ProjectDox plan naming and correction workflow
Inspections, NOC, open permits and CO/CC closeout
Miami permit moving from electronic plans to inspection and certificate An animated Miami skyline, electronic plan, permit document, ProjectDox review screen and final inspection approval show the City of Miami permit process. MIAMI PROJECTDOX PLAN APPROVED PERMIT FINAL INSPECTION PASSED MIAMI RIVERSIDE CENTER
City of Miami is not Miami-Dade County Confirm the property is inside City of Miami limits before applying. Miami-Dade County and nearby cities operate separate permit systems.
Public building functions close at 3:30 PM Listed department hours are 7:30 AM–4:30 PM, Monday through Friday, but public-facing building functions close earlier.
Same-day residential review is available Walk-Thru Express operates Monday–Friday, 7:30 AM–12:30 PM, for eligible small residential projects.
Start here

Choose the Miami Building Department Task You Need

Miami Permit Next-Step Finder

Official contact panel

City of Miami Building Department Phone, Address and Hours

General information 305-416-1100 Permits, plan review and inspections
Building email building@miamigov.com Include address and permit number
ePlan support eplansupport@miamigov.com ProjectDox and digital-plan help
Office location Miami Riverside Center 444 SW 2nd Avenue, 4th Floor, Miami, FL 33130
Department hours 7:30 AM–4:30 PM Monday through Friday
Public-service cutoff 3:30 PM Building functions close to the public at this time
Unsafe Structures 305-416-1177 Located on the first floor
Before calling: Have the exact address, permit or application number, project scope, contractor name and wording of the review comment ready.
First decision

Confirm the Property Is Inside the City of Miami

Use City of Miami iBuild when

  • The parcel is within City of Miami limits
  • The City’s GIS recognizes the property
  • Miami 21 zoning applies
  • City of Miami inspectors handle the work
  • The official permit history returns City records
  • The project address is not controlled by another city

Verify another authority when

  • The property is in Miami-Dade County
  • The address is in Miami Beach
  • The parcel is in Coral Gables
  • The property is in North Miami
  • The site is in a different municipality
  • The mailing address only says “Miami”
A Miami mailing address is not enough. Many properties use “Miami” in the postal address while following Miami-Dade County or another city’s permitting process.

Open City Property Information Tools

Permit decision table

Choose the Correct Miami Permit Route

Project
Best starting route
Important local check
Small project with no plan review
Easy Permit
Applicant must be a qualified contractor in good standing and the exact project must be eligible
Fence, driveway, windows, doors, roof, kitchen or bathroom remodel
Walk-Thru Express
Small residential project; bring a complete package during the morning service window
New home, addition or structural remodel
Full iBuild permit
ProjectDox plans, zoning, flood, energy, tree and trade reviews
Roof repair or replacement
Roofing permit
Roof application, product approvals, fastening, deck condition and related permit history
Electrical, plumbing, gas or mechanical work
Sub-permit
Correct master permit, qualified contractor and discipline-specific inspections
Pool, spa or exterior site work
Reviewed permit
Zoning, survey, flood, barrier, electrical and environmental approvals
Commercial tenant improvement or change of use
Commercial review
Zoning use, occupancy, accessibility, fire, DERM/CU and MEP requirements
Large or complex development
Concierge or joint review
Program eligibility, Special Area Plan, interdepartmental reviews and project schedule
Routine facility repairs across a qualifying property
Annual Facility Permit
Approved one-year scope and qualifying owner, utility or government facility
Tree removal, relocation or trimming with construction
Tree review
Environmental Resources and construction-related tree-permit requirements
Fast permit options

Use the Fast Route That Actually Fits the Project

Easy Permit

Designed for qualified contractors completing eligible small work that does not require plan review.

Result: A qualifying permit may be issued by email without the full plan-review path.

Check Easy Permit eligibility

Walk-Thru Express

Residential homeowners can request same-day review for eligible small projects.

Current hours: Monday–Friday, 7:30 AM–12:30 PM, at Miami Riverside Center.

Open Walk-Thru Express information

Homeowner’s Express Review

A separate expedited-review route may help qualifying owner-builder residential applications.

Do first: Confirm eligibility and required documents before scheduling.

Open Homeowner’s Express Review

Fast review does not remove code, zoning or document requirements. An incomplete package can still be rejected or moved to a full review.
iBuild and ProjectDox workflow

Apply for a Miami Building Permit in Seven Practical Steps

Confirm jurisdiction
Choose permit route
Submit in iBuild
Upload to ProjectDox
Clear all reviews
Pay and pull permit
Inspect and close

Confirm the City controls the address

Check the property, permit history, zoning and municipality before creating an application.

Save: Exact address, folio or property identifier, legal owner name and zoning information.

Choose the correct permit path

Decide whether the project qualifies for Easy Permit, Walk-Thru Express, Homeowner’s Express, Annual Facility Permit or full iBuild review.

Do not use an Easy Permit for work that requires plans, structural review or a larger master permit.

Start the application in iBuild

Enter the site address, full work description, construction value, owner, contractor and required professional information.

Upload plans and forms through ProjectDox

Use the invitation or project link created for the application. Upload drawings and supporting documents in the correct folders.

Use the City naming convention: Give every sheet and document a clear, stable name so revised versions can be matched correctly.

Complete every department review

A project can involve Building, Structural, Electrical, Plumbing, Mechanical, Zoning, Planning, Fire, Public Works, Floodplain, Environmental Resources and outside agencies.

Do not focus only on Building. One unresolved agency comment can stop permit issuance.

Respond to corrections as one coordinated set

Read all comments, revise the plans, cloud changes where required and include a numbered response explaining each correction.

Avoid duplicate uploads: Replace or version the correct file rather than adding several confusing “final” copies.

Pay, pull and print the permit

After approvals, verify the official fees, complete payment and pull the permit. Print the permit card and approved documents.

Work starts after permit issuance—not merely after application approval.

Complete inspections and final certification

Schedule every building and trade inspection. When construction is complete, obtain the required Certificate of Occupancy, Completion or temporary certificate.

Application readiness

Prepare These Items Before Opening iBuild

Property and applicant

  • Correct municipality
  • Exact site address
  • Folio or property ID
  • Owner’s legal name
  • Applicant contact
  • Owner authorization

Project and plans

  • Detailed scope
  • Construction value
  • Site plan
  • Floor plans
  • Code analysis
  • Structural details

Supporting documents

  • Energy calculations
  • Product approvals
  • Contractor credentials
  • Flood documents
  • Tree or environmental review
  • Notice of Commencement
Project document guide

What to Prepare for Common Miami Projects

Project
Useful documents
Resolve before submission
Roof replacement
Roof application, product approvals, assembly, fastening and deck information
Existing permit history, structural damage and exact roof system
Fence or driveway
Survey, site plan, dimensions, materials and right-of-way information
Setbacks, visibility triangle, easements and Public Works review
Windows or exterior doors
Opening schedule, Florida product approvals, design pressure and installation details
Exact product model and opening location
Kitchen or bathroom remodel
Existing/proposed plan, plumbing, electrical, ventilation and structural scope
Whether walls, occupancy, exits or structural systems change
Addition or new home
Survey, site plan, sealed plans, energy, flood, tree, drainage and trade documents
Zoning, lot coverage, setbacks, flood elevation and utility requirements
Commercial tenant improvement
Code summary, occupancy, accessibility, fire, structural and MEP plans
Permitted use, Certificate of Use, DERM, fire and existing CO status
Plan-review corrections

Respond to ProjectDox Comments Without Creating More Delays

Correction workflow

  1. Open every department comment.
  2. Separate design comments from missing-document requests.
  3. Revise the correct drawing or form.
  4. Cloud changed plan areas where required.
  5. Prepare a numbered response letter.
  6. Upload through the assigned task.

Response-letter format

Comment 1: Repeat the reviewer’s request.

Response: Explain the correction.

Location: Identify the revised sheet, detail or document.

Professional: Confirm the design professional signed and sealed revisions when required.

Do not upload unrelated sheets or a full duplicate project unless instructed. Conflicting file versions make it harder for reviewers to identify the current design.

Open iBuild and ePlan Help

Local approval map

Check Reviews Outside the Building Discipline

Project issue
Likely review
Question to answer first
Use, setback, lot coverage, height or parking
Zoning / Miami 21
Is the project allowed at this property?
Large development or site-plan change
Planning and land development
Is an ASPR, warrant, exception, waiver or rezoning required?
Driveway, sidewalk, street or right-of-way
Resilience and Public Works
Does the project require a separate Public Works permit?
Tree removal, relocation or trimming
Environmental Resources
Is a construction-related or standalone tree permit required?
Historic or archaeological property
Historic Preservation
Is a COA, SCOA or Certificate to Dig required?
New business or occupancy change
Zoning, Fire, DERM and Certificate of Use
What must be approved before the business opens?
Flood-zone construction
Floodplain / Building
Which elevation and flood-compliance documents apply?
Fire alarm, sprinkler or life safety
Fire Prevention Bureau
Is a standalone fire permit or expedited review available?
Inspection command board

Schedule the Correct Inspection and Track the Inspector

Schedule the inspection

The holder of each permit must request the inspection for that specific discipline.

Open inspection scheduling

Track the inspector

Use the City’s tracking service on the scheduled day to check expected inspector-arrival information.

Track the inspector

Review past results

Search inspection history to confirm approvals, failures and the next required stage.

View inspection history

Before requesting

  • Permit formally issued
  • Correct discipline selected
  • Work stage completed
  • Work remains visible
  • NOC handled when required
  • Required sub-permits active

Before arrival

  • Permit card onsite
  • Approved plans available
  • Gates and rooms accessible
  • Safe ladders provided
  • Animals restrained
  • Prior corrections completed
Do not cover work before approval. Framing, reinforcement, wiring, plumbing, gas, mechanical work and insulation may need to remain visible for the inspector.
Notice of Commencement

Record and Submit the NOC Before the First Inspection When Required

General threshold

Florida law generally requires the permitting authority to receive NOC information before the first inspection when the direct contract exceeds $5,000.

HVAC exception

The inspection requirement generally does not apply to repair or replacement of an existing heating or air-conditioning system below $15,000.

Record consistency

The owner, contractor and property information should match the City permit application.

Do not record too early without checking the construction start. A Notice can become ineffective when the improvement does not begin within the applicable statutory period.

Open Miami Permitting Forms

Property and permit research

Search More Than the Permit Number

Permit history

Search permits, applications, fees and inspection information through iBuild’s global inquiry.

Search permit history

Microfilm records

Request archived Building records when older plans or permit files are not available online.

Request Building records

Liens and violations

Check for recorded City liens and active violations before buying, refinancing or beginning a renovation.

Run a lien or violation search

Property-sale check: A permit number does not prove the work was completed. Confirm all required inspections passed and the permit received final closure.
Active and expired permits

Use an Extension for an Active Permit and Completion for an Expired Permit

Permit Extension

  • The permit must still be active.
  • The request must be made before expiration.
  • The City says a permit may be extended once.
  • The extension provides 180 days from the request date.
  • Use the time to complete work and all inspections.

Permit Completion

  • Use this route when the permit has expired.
  • Identify the remaining work and inspections.
  • Provide updated contractor information if needed.
  • Expect review of current code and safety conditions.
  • Do not restart work until authorization is issued.

Request Extension or Completion

Owner-builder assistance

Use the City’s Free Homeowner Help Before Taking Full Responsibility

Homeowner Assistance Program

The free program assists qualifying homesteaded City of Miami homeowners through the permitting process step by step.

Direct assistance

Homeowner line: 305-416-1139

Email: hoabuilding@miamigov.com

Owner-builder warning

The owner accepts contractor-level responsibilities for supervision, permits, worker coverage, inspections, liens and final closure.

Owner-builder status is not a way to lend a license to an unlicensed contractor. Read every disclosure and confirm the exemption applies.
Commercial and complex projects

Use Specialized Review Support Instead of Repeated Resubmissions

Concierge Program

Supports qualifying large commercial, complex, affordable-housing, City-led and other high-profile developments.

Phone: 305-416-1127

Email: concierge@miamigov.com

Joint Plan Review

Allows a qualifying project team to coordinate applicable reviewers and address major issues together.

Commercial expedited review

Check eligibility, fees, required readiness and available review disciplines before requesting expedited service.

Private provider

Understand the City of Miami Private Provider Process

Register the firm

Private providers must register with the City and remain under the authority of the Building Official.

Select the service scope

Use the City’s current Notice to Building Official and required affidavits for plan review and/or inspections.

Complete trade closeout

Submit required inspection reports and closeout affidavits for Building, Roofing, Electrical, Plumbing/Gas and Mechanical disciplines.

Open the Private Provider Program

Final certificates

Know Whether the Project Needs a CO, CC, TCO or TCC

Certificate
Common use
Before requesting
Certificate of Occupancy — CO
New construction or a change of use
Required finals, approvals, fire and applicable agency clearances
Certificate of Completion — CC
Remodel, renovation or shell-building completion
All permit and trade inspections completed
Temporary CO — TCO
Temporary occupancy while minor approved work remains
Habitable and safe space plus Building Official approval
Temporary CC — TCC
Temporary completion status for an eligible project
Required safety and agency conditions satisfied
Do not occupy or open a business based only on passed construction inspections. Obtain the required occupancy, completion, Certificate of Use and business approvals.
Current code framework

Codes Used by the City of Miami Building Department

Florida Building Code

The City identifies the Florida Building Code, 8th Edition (2023), including Building, Residential, Existing Building, Accessibility, Energy, Plumbing, Mechanical and Fuel Gas.

Electrical Code

The City lists the 2020 National Electrical Code, NFPA 70.

Fire Code

The City lists the Florida Fire Prevention Code, 8th Edition.

Permit fees

Use the Official Fee Schedule and Final iBuild Invoice

Permit-specific charges

Cost depends on permit type, project value, plan review, trade permits, revisions, inspections, certificates and other services.

Completion and extension

Permit extensions, expired-permit completion, revisions and after-the-fact work can create separate charges.

Verify before payment

Review the permit number, address and line items inside iBuild before paying.

No generic percentage calculator is used here. It could omit plan review, trade, technology, solid-waste, certificate, reinspection and penalty charges.

Open the Current Miami Fee Schedule

Status decoder

What the Miami Permit Status Means

DraftFinish the application and confirm it was submitted.
SubmittedThe City received the application and is checking intake.
Pending documentsUpload the exact missing form, drawing or supporting record.
In reviewApplicable departments are reviewing the project.
Corrections requiredOpen all comments and submit coordinated revisions.
ApprovedFees, pulling or formal issuance may still be required.
IssuedPrint the permit card and approved plans before starting work.
Failed inspectionCorrect every listed item before requesting reinspection.
ExpiredRequest Permit Completion before continuing work.
Final / closedSave proof and verify all trade permits and certificates.
Problem solving

Fix Common City of Miami Permit Problems

Problem
Likely cause
Best next action
Address does not appear
Wrong municipality, address format or property record
Confirm City limits and search the property information tools
No ProjectDox invitation
Application not advanced, incorrect email or intake issue
Check iBuild status and contact ePlan support
Review comments keep returning
Partial correction, conflicting files or missing response letter
Submit one coordinated revision addressing every discipline
Inspection cannot be scheduled
Permit not pulled, wrong discipline, missing NOC or inactive sub-permit
Check issuance, permit holder and inspection prerequisites
Old permit is expired
Work or inspections were not completed in time
Use Permit Completion rather than an active-permit Extension
Business cannot open
CO/CC, CU, Fire, DERM or zoning clearance remains open
Identify the exact final certificate and agency approval
Ready-to-use scripts

What to Say When You Contact the City

Jurisdiction:
“The property is at [address], folio [number]. Can you confirm that the City of Miami—not Miami-Dade County or another municipality—handles the permit?”
Permit route:
“I am planning [exact work]. Does this qualify for Easy Permit, Walk-Thru Express, Homeowner’s Express or full iBuild review?”
Plan-review correction:
“Application [number] has comments from [departments]. Can you confirm which task I must accept and where the revised files and response letter belong?”
Expired permit:
“Permit [number] is expired. Which remaining inspections or documents are required for Permit Completion, and must the plans be updated?”
Final project checklist

Do Not Consider the Miami Project Complete Until These Are Confirmed

  • City jurisdiction confirmed
  • Correct permit route selected
  • Property record verified
  • Contractor registered
  • Complete plans uploaded
  • ProjectDox tasks completed
  • Zoning and outside reviews cleared
  • All comments resolved
  • Permit paid and pulled
  • Permit card posted
  • NOC handled when required
  • All inspections approved
  • Trade permits finaled
  • CO, CC, TCO or TCC obtained
  • Certificate of Use obtained if required
  • Main permit closed
Office location

City of Miami Building Department Map

Address: Miami Riverside Center, 444 SW 2nd Avenue, 4th Floor, Miami, FL 33130. Phone: 305-416-1100. Hours: Monday–Friday, 7:30 AM–4:30 PM; public building functions close at 3:30 PM.
Official resource library

Open the Correct City of Miami Permit Resource

Frequently asked questions

City of Miami Building Permit FAQs

Where do I apply for a City of Miami building permit?

Use the City’s iBuild portal. Full plan-review projects also use ProjectDox for electronic drawings and supporting documents.

What is the City of Miami Building Department phone number?

Call 305-416-1100. The Building Department is at Miami Riverside Center, 444 SW 2nd Avenue, 4th Floor, Miami, Florida 33130.

What are the Miami Building Department office hours?

The department lists Monday through Friday from 7:30 AM to 4:30 PM. Building functions close to the public at 3:30 PM.

What is a Miami Easy Permit?

An Easy Permit is for eligible small projects that do not require plan review. Qualified contractors in good standing can apply and may receive the permit by email.

Which projects may qualify for same-day Walk-Thru Express review?

The City lists eligible small residential projects such as fences, driveways, windows and doors, roofing, kitchen or bathroom remodels and minor repairs. The service currently operates Monday through Friday from 7:30 AM to 12:30 PM.

How do I schedule and track a Miami building inspection?

Use the City’s online inspection service to request the inspection for the permit discipline you hold. On the scheduled day, use the inspector-tracking page for expected arrival information.

When is a Notice of Commencement required?

Florida law generally requires NOC information before the first inspection when the direct contract exceeds $5,000. Repair or replacement of an existing HVAC system below $15,000 is generally excluded from that inspection requirement.

How do I extend an active Miami permit?

Request an Extension before the permit expires. The City says an active permit may be extended once for 180 days from the request date.

What should I do when a Miami permit has already expired?

Use the Permit Completion process rather than an active-permit Extension. The City will identify the remaining work, documents, fees and inspections needed for closeout.

What is the difference between a Certificate of Occupancy and Certificate of Completion?

A Certificate of Occupancy generally applies to new construction or a change of use. A Certificate of Completion generally applies to remodels, renovations and shell-building work.

Source and accuracy note

Official Information Used for This Guide

Building-Department.org is an independent informational guide and is not the City of Miami.

This page was rebuilt using current City of Miami Building Department, iBuild, ProjectDox, Easy Permit, Walk-Thru Express, inspection, property search, permit extension, certificate, private-provider, code and fee resources.

Last reviewed: July 23, 2026.

Programs, hours, fees, review procedures, forms and inspection availability can change. Confirm time-sensitive details before filing, paying or beginning work.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.