San Carlos permit action guide

Move From Planning Approval to a Final San Carlos Inspection Inside One Digital Permit Record

San Carlos changed its entire permit process in June 2025. New building, planning and Public Works applications now go through Tyler Customer Self-Service, and paper plan submittals are no longer accepted.

The practical detail many applicants miss is that the city still requires its signed one-page Building Permit Application as an uploaded attachment. This guide shows how to create the account, prepare the plans, handle soil and wildfire checks, pay fees, answer corrections, schedule inspections and prevent the permit from becoming void.

Tyler CSS application and permit-linking steps
2025 code-cycle, soil-zone and WUI checks
FY 2026–27 fees, inspections and closeout
San Carlos digital plan, oak tree, portal review and final inspection An animated residential plan moves through the San Carlos Customer Self-Service portal toward a final inspection, with hills, an oak tree and wildfire review represented. DIGITAL PLAN PACKAGE PLANNING • SOIL • WUI • CALGREEN TYLER CSS DASHBOARD APPROVED APPLICATION PDF FINAL INSPECTION CLOSED GOOD LIVING
NEW
New portal process began June 3, 2025 All new permit and planning applications must be submitted online through Tyler Enterprise Permitting & Licensing, also called Customer Self-Service or CSS.
PDF
The online form does not replace the Building Permit Application Complete and sign the city’s one-page Building Permit Application, then upload it in the portal’s attachment section. An application without this file can be delayed at intake.
LINK
Old permit not visible in your new account? Create the CSS profile first. Then email inspections@cityofsancarlos.org with the permit number and the exact email used for the profile so staff can link the record.
Start here

Choose the San Carlos Task You Need

Official contact panel

San Carlos Building Division Phone, Email, Address and Hours

Building Division 650-802-4261 Permits, codes, plans and inspections
Building email building@cityofsancarlos.org Include the property address
Inspection linking inspections@cityofsancarlos.org Permit number + CSS profile email
City Hall 600 Elm Street San Carlos, CA 94070
In-person counter Mon–Thu, 9 AM–12 PM By appointment
Remote help Mon–Thu 1 PM–5 PM Email or phone assistance
Friday remote help 8 AM–12 PM & 1–5 PM No normal walk-in counter
Good email subject: “Permit route question – 123 Example Street – kitchen remodel.” In the message, state the exact work, whether walls move and whether electrical, plumbing, HVAC, trees or exterior work are involved.
Jurisdiction check

Confirm the Property Is Inside Incorporated San Carlos

Use San Carlos Building when

  • The parcel is inside city limits
  • The CSS portal recognizes the address
  • San Carlos Planning regulates the property
  • Prior records use BLD, MEP, PLN or ENC numbers

Verify first when

  • The mailing address says San Carlos but the parcel may be unincorporated
  • The property is near Belmont, Redwood City or county land
  • The portal cannot locate the address
  • Old permits were issued by San Mateo County
Tyler CSS portal

Use the New San Carlos Permit System Correctly

New applicant

Create a CSS account

  1. Open Customer Self-Service.
  2. Select Login or Register.
  3. Scroll to Create an Account.
  4. Verify your email.
  5. Complete the profile before applying.
Inspection account

Link the issued permit

Create the account before asking staff to link a permit.

Email inspections@cityofsancarlos.org with:

  • Permit number
  • Property address
  • CSS account email
OLD
Previous records were transferred The city says paid, active and approved records retained their original numbers, including BLD, MEP, TRE, PLN and ENC records.
Application workflow

Apply for a San Carlos Building Permit in Eight Steps

Check Planning before final construction plans

Planning reviews project size, height, setbacks, use, occupancy, neighborhood impact, protected trees and design requirements.

Do next: Save the Planning approval or case number and place every condition on the plan set.

Confirm soil, WUI and survey requirements

Ask Building whether the parcel is in Soil Hazard Zone A or B, the Wildland-Urban Interface or an area requiring a survey or soils report.

Download the current project checklist

Use the new-home/residential-addition checklist, commercial tenant-improvement checklist or project handout that matches the work.

Complete the one-page Building Permit Application

Provide property, applicant, contractor, license, workers’ compensation, owner-builder and construction-lender information.

Prepare the digital plan package

Paper plans are not accepted for application review. Upload readable, properly scaled PDFs and separate supporting documents clearly.

Create the online application

Select the closest permit type, complete all required fields and upload the signed one-page application under Attachments.

Pay invoices and monitor departmental review

Use the dashboard for invoices, review progress, comments and resubmittals. Do not create another application to answer corrections.

Download the issued permit and stamped plans

The city issues approved permit cards and plans electronically. Print a properly scaled inspection set for the job site.

Application form decoder

Complete the One-Page Application Without Leaving a Legal Gap

Application area
What to enter
Common mistake
Primary contact
The person and email that should receive city notices and portal updates
Using an email nobody monitors during plan review
Owner and design team
Owner, tenant, designer, architect or engineer contact information
Leaving out the professional responsible for corrections
Contractor
License class, state license number, company details and city business-license number
Using an expired license or wrong classification
Workers’ compensation
Insurance, self-insurance or applicable no-employee declaration
Selecting an exemption that does not match the actual workforce
Owner-builder
The correct state-law owner-builder basis and owner signature
Using owner-builder status while an unlicensed person manages the work
Final certification
Applicant or authorized agent signature and printed name
Uploading an unsigned form
Permit decision table

Match the Project to the Correct San Carlos Route

Project
Start with
Check before filing
New house or residential addition
Planning approval + building permit
Design review, site plan, tree protection, soil zone, survey, WUI, Title 24 and CALGreen
Kitchen or bathroom remodel
Building/MEP permit
Wall changes, structural work, fixture relocation, electrical load, ventilation and energy forms
Deck or balcony
Building permit
Setbacks, height, structural plans, soil, waterproofing and protected trees
Commercial tenant improvement
Planning/use check + building permit
Occupancy, accessibility, Fire, hazardous use, business registration and construction type
ADU or JADU
Ministerial ADU review
Site-specific plan information, pre-approved-plan restrictions, utilities, trees and JADU deed restriction
Residential rooftop solar
SolarAPP+ eligibility
Licensed contractor, system eligibility, battery, service changes and SolarAPP+ approval
Fire sprinkler or fire alarm
Digital Fire plan review
Building permit relationship, system design and Fire Department inspection requirements
Protected-tree removal or major pruning
Tree permit
Tree species, canopy/root impact, arborist report and Tree Protection Plan
Street, sidewalk or storm-drain connection
Public Works ENC permit
Right-of-way, traffic control, trenching, drainage and inspection requirements
Pool, spa or hot tub
Building + trade permits
Barrier, setbacks, grading, bonding, plumbing, equipment and protected-tree impacts
Document readiness

Build a Reviewable Residential or Commercial Plan Package

Residential plans

  • Planning approval
  • Scaled site plan
  • Existing and proposed floor plans
  • Building elevations
  • Wall, floor and roof sections
  • Door and window information
  • Electrical and fixture layouts
  • Planning conditions in plan set

Engineering and energy

  • Title 24 forms
  • CALGreen checklist
  • Structural plans
  • Structural calculations
  • Soils report when required
  • Survey plan when required
  • Civil plans for reference
  • Special-inspection form

Commercial projects

  • Existing and proposed use
  • Occupancy and construction type
  • Accessibility details
  • Exit and occupant-load plan
  • Fire/life-safety documents
  • Mechanical, electrical and plumbing plans
  • Energy documents
  • Construction-waste documents
Current residential checklist: The April 2026 revision states that residential plans must comply with the 2025 California Code Cycle and that Planning approval is required before Building submittal for new homes and additions.
San Carlos site conditions

Check Soil, Wildfire, Trees and Survey Requirements Before Design Is Finished

2025 code cycle

Prepare new applications under the currently adopted California code cycle and local technical amendments.

Soil Hazard A or B

Zone B is identified by the city as the more restrictive zone. Ask whether a stamped soils report is required.

Wildland interface

Properties south of San Carlos Avenue and west of Alameda de las Pulgas may be within the WUI.

Protected trees

A permit is required to remove a protected tree or prune 25% or more of its canopy or root system.

City design value
Published value
How it affects plans
Climate zone
Zone 3
Energy design and Title 24 assumptions
Seismic design category
E
Structural design and detailing
Basic wind speed
91 mph
Structural and component design
Soil bearing value
1,500 psf
Lower assumed values require a soils report
Building exposure
B, C or D
Exposure D is the most severe listed category
WUI
Do not guess wildfire applicability from a street address alone Ask Building to verify the parcel. WUI requirements can affect roofing, vents, exterior walls, glazing, decks and vegetation management.
Permit-exempt work

Use the Exact Threshold—Then Check Planning and Right-of-Way Rules

Work
Published building threshold
Still verify
Side or rear fence
Six feet or less
Front-yard, corner visibility, right-of-way and Planning limits
Front-yard fence, wall, hedge or screen
Generally no more than four feet
Corner sight-distance triangle can limit height to three feet
Detached shed or greenhouse
Single story and no more than 120 square feet
Setback, height, utilities, tree and WUI requirements
Wood retaining wall
Three feet or shorter
Surcharge, slope, drainage, property line and right-of-way
Concrete or masonry retaining wall
Less than four feet from footing bottom to wall top
Surcharge, slope, soil and nearby structure conditions
Painting and wallpaper
Generally permit-exempt
Associated structural, electrical, plumbing or hazardous-material work
Like-for-like toilet replacement
City FAQ states permit is generally not required
Relocation, piping changes or broader bathroom remodel
Most other mechanical, structural, plumbing and electrical work requires a permit. Roofs, water heaters, furnaces, pools, windows, electrical appliances and relocated plumbing commonly need approval.
Official published estimates

San Carlos Plan-Review Turnaround Times

Permit type
Published estimate
What can extend it
EV charging installation
1–2 days
Service upgrades, trenching or incomplete electrical details
Kitchen and bathroom remodel
3–5 days
Structural changes or missing trade information
Solar installation
3–5 days
Non-SolarAPP+ project, battery or service changes
Deck
1–2 weeks
Soil, setback, structural or tree issues
Interior remodel
1–3 weeks
Complex scope or multi-department review
Tenant improvement
2–4 weeks
Use, accessibility, Fire or hazardous-material review
Single-story addition
2–4 weeks
Planning, soil, tree, survey or Public Works issues
Second-story addition
3–5 weeks
Residential design and structural review
New single-family residence
4–6 weeks
Incomplete plans or unresolved outside review
New multifamily project
6–8 weeks
Project size, corrections and department coordination
Plan-review recheck
10 days–2 weeks
Incomplete responses or additional design changes
These are planning estimates, not guaranteed approval dates. Review time starts with a complete package and does not include the applicant’s correction time.
Residential AB 2234 timeline

Major Residential Projects Have Separate State-Law Review Milestones

Completeness review

The city’s AB 2234 page identifies a 15-day completeness determination for covered post-entitlement residential permits.

25 units or fewer

The city page identifies a 30-day review period for covered projects of 25 units or fewer.

26 units or more

The city page identifies a 60-day review period for covered projects of 26 units or more.

Covered projects only: These milestones apply to qualifying majority-residential post-entitlement permits under AB 2234, not every remodel or trade permit.
Effective July 1, 2026

San Carlos FY 2026–27 Building Fees and Valuation Benchmarks

FY27
Use the current schedule San Carlos’s adopted FY 2026–27 Cost of Services schedule became effective July 1, 2026. The portal invoice is the controlling amount for the individual project.
Main electrical service $278 Listed per permit
Residential PV solar $348 Listed PV permit fee
Water-heater replacement $117 Listed plumbing permit fee
Replacement FAU/HVAC $232 Listed mechanical fee
Planning permit review $232 Listed per building permit
Green-building review $232 Listed per review
Energy calculation review $116 Listed per review
Additional reinspection $232/hour Listed for second and later reinspections
Construction valuation benchmark
FY 2026–27 listed value
How it is used
New residential and additions
$232 per square foot
Helps establish permit valuation; it is not the final permit fee
Interior remodel
$117 per square foot
Valuation input for applicable remodeled area
Garages and accessory structures
$48 per square foot
Valuation basis for applicable structure area
Decks
$39 per square foot
Valuation basis before permit and review charges
Commercial shell
$57 per square foot
Used with the city’s valuation-based permit table
Tenant improvements
$57 per square foot
Base valuation; complex uses can have additional trade and Fire fees
Valuation example—not a final permit quote

A 400-square-foot residential addition using the city’s $232-per-square-foot benchmark produces an estimated construction valuation of $92,800. Building, plan-check, Planning, energy, green-building, Fire, trade, impact, technology and transaction fees can be added separately.

400 sq ft × $232 = $92,800 estimated valuation

Open FY 2026–27 Fee Schedules

Inspection workflow

Request, Confirm and Prepare for a San Carlos Building Inspection

Confirm the permit is issued

Inspection options appear for active issued permits. Make sure all required fees and issuance conditions are complete.

Link the permit to your CSS account

If it is missing, email inspections@cityofsancarlos.org with the permit number and CSS account email.

Request the exact inspection in CSS

Open the permit, select the appropriate inspection and submit the request. Staff confirmation places it under My Inspections → Scheduled.

Check the 90-minute window after 8:30 a.m.

Open Today’s Inspections from the portal. Login is not required to view the day’s inspection window.

Keep stamped plans and the permit card on site

The contractor must maintain a paper copy of the stamped, approved, properly scaled plans. Color is recommended but not required.

Read the result before continuing

Do not cover work after a failed or incomplete inspection. Correct every item before requesting reinspection.

Inspection method

The city may use an on-site inspection, virtual inspection, photographs or special-inspection documentation depending on the project.

Reschedule or cancel

Email inspections@cityofsancarlos.org. Include the permit number, address and requested change.

Permit inactivity

The current inspection handout says permits are void 180 days after the last major inspection unless an extension is approved.

Extension request: Email building@cityofsancarlos.org before the 180-day deadline. Explain the cause of delay and provide an anticipated completion date.

Open Official Inspection Instructions

Construction hours

Noise Hours Include Deliveries, Setup and Cleanup

Monday–Friday

8:00 AM–5:00 PM

Includes site preparation, cleanup and deliveries.

Saturday

9:00 AM–5:00 PM

Includes site preparation, cleanup and deliveries.

Sunday and listed holidays

No construction allowed

The city lists ten no-construction holidays.

No early material delivery. The published hours expressly include deliveries and site setup, not only power-tool noise.
ADU, solar and commercial work

Special San Carlos Permit Routes

ADU or JADU

  • Applications are ministerial and do not require a normal discretionary hearing.
  • Pre-approved-plan designs still need site-specific information.
  • No impact fees are collected for an ADU or JADU under 750 square feet.
  • JADUs require a recorded deed restriction.
  • ADUs and JADUs cannot be rented for fewer than 30 consecutive days.

Open ADU guidance

SolarAPP+

  • Eligible new residential rooftop systems can receive automated approval.
  • Submit the project through SolarAPP+ first.
  • Complete the city permit process as instructed.
  • Ineligible or commercial systems use manual review.
  • Manual solar review is published at approximately three to five business days.

Compare solar routes

Commercial tenant improvement

  • Confirm the proposed business use first.
  • Prepare the commercial checklist.
  • Coordinate accessibility and Fire.
  • Obtain an active San Carlos business registration.
  • Check hazardous-material, wastewater and PCB requirements where applicable.

Open commercial checklist

Status decoder

What Your CSS Permit Status Means

Draft The application is saved but has not been fully submitted.
Submitted The city received the record and is checking the intake package.
Incomplete A required field, signed application or supporting document is missing.
Fees due Pay the listed portal invoice before expecting the next review step.
In review Building, Planning, Fire or Public Works is reviewing the record.
Corrections required Download all comments and submit a coordinated revision under the same record.
Approved Review is complete, but payment or permit issuance may remain.
Issued Construction may begin within the approved scope and conditions.
Inspection failed Correct every listed item before requesting the same inspection again.
Final / closed Save the record and verify that all trade, Fire, Planning and Public Works permits are also complete.
Permit history and plans

Search the Portal Before Filing a Public-Records Request

Search the CSS public portal

Use the property address or permit number. Previous TrakIt records were transferred into the new system.

Check every related record

A project may have separate BLD, MEP, PLN, TRE, ENC and Fire records.

Read inspection results

An issued permit is not proof of completed work. Look for final inspection and closure information.

Submit a focused public-record request

Specify the address, approximate year, permit type and exact documents needed. The city states that public-record requests are reviewed and responded to within ten days.

Arrange plan viewing when copies are restricted

Building plans may be viewed by appointment Monday through Thursday from 9:00–11:30 a.m. State law restricts duplication of official professional plans.

Older homes

The city says records may be limited, outdated or incomplete, especially for older houses.

1980 to present

The Building Division states that it generally has more complete residential files for this period.

In-person review

The city states there is no charge to review public records in person at City Hall.

Troubleshooting

Fix Common San Carlos Permit Problems

Problem
Likely reason
Next action
Application remains incomplete
Signed Building Permit Application or checklist item is missing
Open Attachments and compare the upload with the project checklist
Old permit is not in the account
Profile email does not match the prior city record
Email the permit number and CSS profile email to inspections@cityofsancarlos.org
Inspection option is missing
Permit is not linked, issued or active
Check permit status and request record linking
Review comments repeat
Only selected sheets were corrected or responses are unclear
Upload a coordinated plan set and numbered response letter
Permit approved but not issued
Invoice, contractor document or department condition remains open
Review every invoice and departmental status in CSS
Inspection window is not visible
The morning route has not been posted
Check Today’s Inspections after 8:30 a.m.; no login is required
Permit may expire
No major inspection has occurred within 180 days
Email Building before the deadline with the delay reason and completion date
Old unpermitted work affects a sale
Prior construction lacks a permit or final inspection
Request permit history and written legalization or closeout requirements
Ready-to-use scripts

Ask City Staff a Question They Can Answer Quickly

Permit route question
“I am planning [exact work] at [address]. Does this need Planning approval first, and which Building permit type should I select in Customer Self-Service?”
Soil and WUI question
“Is [address/APN] in Soil Hazard Zone A or B or the Wildland-Urban Interface, and which soils, survey or wildfire documents are required?”
Portal-linking question
“My CSS profile email is [email]. Please link permit [number] at [address] so I can request and view inspections.”
Permit-closeout question
“Permit [number] still appears open. Which building, trade, Planning, Fire or Public Works final is missing?”
Final project control

San Carlos Permit Completion Checklist

  • City jurisdiction confirmed
  • Planning approval completed
  • Soil Hazard Zone verified
  • WUI applicability checked
  • Protected trees identified
  • Current project checklist used
  • One-page application signed
  • Digital plans properly scaled
  • Title 24 and CALGreen included
  • Contractor license verified
  • Portal invoices paid
  • Corrections answered in one record
  • Permit formally issued
  • Stamped plans printed for site
  • Construction hours followed
  • Inspections requested before concealment
  • 180-day activity deadline protected
  • Building and related records finaled
City Hall map

San Carlos Building Division at 600 Elm Street

Visit by appointment: Building’s in-person counter hours are Monday through Thursday from 9:00 a.m. to noon. Email building@cityofsancarlos.org before traveling when you need plan viewing or detailed project help.
Official resources

Open the Exact San Carlos Permit Resource

Frequently asked questions

San Carlos Building Permit and Inspection FAQs

Where do I apply for a San Carlos building permit?

Use the City of San Carlos Tyler Customer Self-Service portal. All new applications are submitted online. You must also complete, sign and upload the city’s one-page Building Permit Application.

Does San Carlos accept paper building plans?

No. The Building Division states that new permit applications and plans are processed digitally. After issuance, the contractor must print and maintain a properly scaled copy of the stamped approved plans at the job site.

What is the San Carlos Building Division phone number?

Call 650-802-4261 or email building@cityofsancarlos.org. Include the property address when asking whether a project requires a permit.

How do I schedule a San Carlos building inspection?

Create a Customer Self-Service account and request the inspection from the issued permit. If the permit is not visible, email inspections@cityofsancarlos.org with the permit number and the email used for your CSS profile.

How do I find my inspection arrival time?

Open Today’s Inspections from the top of the permit portal after 8:30 a.m. on the inspection morning. The city posts a 90-minute arrival window, and login is not required to view it.

When does a San Carlos permit become void?

The current inspection handout says a permit becomes void 180 days after the last major inspection. Before the deadline, email Building with the delay reason and anticipated completion date to request an extension.

What are the construction hours in San Carlos?

Construction is allowed Monday through Friday from 8:00 a.m. to 5:00 p.m. and Saturday from 9:00 a.m. to 5:00 p.m. Construction is prohibited on Sundays and listed holidays. The hours include setup, cleanup and deliveries.

Does a small shed require a building permit?

A detached single-story shed or greenhouse may be exempt when it does not exceed 120 square feet. Planning rules for setbacks, height and location still apply, and electrical or plumbing work may require separate permits.

How do I know whether my project is in the WUI or a soil hazard zone?

Email the Building Division with the property address or APN. San Carlos identifies Soil Hazard Zones A and B and states that properties south of San Carlos Avenue and west of Alameda de las Pulgas may be within the Wildland-Urban Interface.

Can I get copies of old San Carlos building plans?

Search the permit portal and submit a public-record request when needed. State law can prevent the city from duplicating professional plans without required permission. Plans may be viewed by appointment at City Hall Monday through Thursday from 9:00 to 11:30 a.m.

Independent guide and freshness

Source and Accuracy Note

Building-Department.org is an independent guide and is not the City of San Carlos. Applications, payments, inspections, code decisions, tree permits and approvals must be completed through official city systems.

This guide was checked against the San Carlos Building Division, Building Permits page, June 2025 New Permitting Procedures, Tyler Customer Self-Service portal, current Building Permit Application, April 2026 residential checklist, Inspection Information handout, FY 2026–27 fee schedule, AB 2234 page, ADU guidance, protected-tree resources and Public Records page.

Last reviewed: July 21, 2026.

Forms, fees, portal labels, staff assignments and code interpretations can change. Confirm live requirements before paying, ordering plan sets or beginning construction.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.