Use ProjectDox, Upload the Correct Permit Package and Finish Every Required Inspection
The official permit authority is the Village of Royal Palm Beach Building Division—not a City of Royal Palm Beach department.
The Village uses ProjectDox for electronic applications and plan review, Click2Gov for permit and fee information, and a separate automated IVR line for inspections. This guide explains which system to use, what documents to upload, how to name files, when Planning or Engineering review is needed and what proves the permit is finally closed.
Choose the Royal Palm Beach Task You Need
Royal Palm Beach Permit Route Finder
Select the project or problem to see the best first action and document package.
Village of Royal Palm Beach or Unincorporated Palm Beach County?
Use the Village Building Division when
- The parcel is inside Village boundaries
- The permit record appears in Village Click2Gov
- ProjectDox identifies Royal Palm Beach
- Village Planning handles the property
- The permit card lists Village inspection codes
- Village staff confirms jurisdiction
Use Palm Beach County when
- The parcel is in unincorporated county territory
- The address is outside Village limits
- The record appears in the county ePZB system
- The county Permit Center confirms jurisdiction
- County zoning controls the property
- The existing permit was issued by Palm Beach County
Royal Palm Beach Building, Planning, Engineering and Code Contacts
ProjectDox, Click2Gov and IVR Perform Different Jobs
System |
Use it for |
What to prepare |
Common mistake |
|---|---|---|---|
ProjectDox |
Apply, upload plans, receive tasks, answer comments and download approved files |
Account email, project type and correctly named PDFs |
Uploading improperly named or incomplete files |
Click2Gov |
Search permit information, applications, addresses, parcels, names and available fee details |
Application number, street information or parcel number |
Expecting Click2Gov to replace the ProjectDox application workspace |
Inspection IVR |
Schedule, cancel and retrieve inspection results by telephone |
Permit-card IVR number and three-digit inspection code |
Using the wrong inspection code or failing to save the confirmation number |
Virtual inspection |
Eligible in-progress and replacement inspections through a phone camera |
Scheduled inspection, charged phone, plans and reliable connection |
Assuming every inspection qualifies for virtual review |
Palm Beach County ePZB |
Unincorporated Palm Beach County properties only |
County jurisdiction confirmation |
Using county permitting for a property inside the Village |
Match the Project to the Royal Palm Beach Permit Package
Project |
Forms commonly listed by the Village |
Supporting documents to prepare |
Extra review to check |
|---|---|---|---|
New single-family home |
Blower Door Form, Contractor Data Sheet, Inspection Codes, NOC, owner-builder statement and single-family checklist |
Recent survey, landscaping survey, plans, engineered design, product approvals, trusses, soils, energy, final survey and elevation certificate |
Planning, landscaping, Engineering, flood, impact fees and utilities |
Addition, garage, carport or screen room |
NOC, pervious-area form, landscaping index, owner-builder statement, checklist, inspection codes and contractor data sheet |
Product approvals, truss design, soils, energy, insulation, final survey and elevation information |
Setbacks, lot coverage, easements and flood elevation |
Interior or exterior renovation |
Contractor Data Sheet, Inspection Codes, NOC and Planning/Zoning pre-check |
Floor plan, design or engineered plan, product approvals, energy and insulation documents when applicable |
Structural changes, wind products, electrical, plumbing and mechanical permits |
Window, door, shutter or garage door |
Inspection Codes, Contractor Data Sheet, NOC, owner-builder statement and applicable checklist |
Opening schedule, Florida product approvals or Miami-Dade NOAs and installation details |
Wind-pressure compatibility and structural opening changes |
Roof replacement |
Contractor Data Sheet, Inspection Codes, NOC, owner-builder statement, re-roof affidavit and roof specification sheet |
Roof system information, product approvals and fastening details |
In-progress roof inspections and virtual-inspection eligibility |
Pool, spa or enclosure |
Contractor Data Sheet, Inspection Codes, NOC, owner-builder statement, pool checklist and safety affidavit |
Survey, plans, safety barriers, bonding, pervious-area and landscaping information |
Setbacks, easements, drainage and pool safety |
Fence, shed, gazebo, pavers or driveway |
Accessory or fence checklist, NOC, owner-builder statement, inspection codes, contractor data and easement forms where applicable |
Survey, location plan, anchoring, design and pervious-area calculations |
Easements, landscaping, setbacks, drainage and right-of-way work |
Generator or electrical service |
NOC, owner-builder statement, generator checklist, inspection codes and contractor data sheet |
Design plan, product approvals and elevation certificate when required |
Equipment setbacks, flood elevation, gas permit and utility coordination |
Dock or seawall |
Contractor Data Sheet, easement agreement, hold-harmless agreement, inspection codes, NOC and seawall regulations |
Survey, site plan, engineered design and special inspection documents |
Waterway Utilization Permit, canal easement and Engineering review |
New commercial tenant |
New Tenant Inspection form and project-specific building or trade applications |
Floor plan, use, occupancy, life-safety and business information |
Planning use approval, fire, accessibility, business tax receipt and CO |
Apply Online Without Creating an Incomplete Project
Confirm jurisdiction, zoning and project type
Verify that the parcel is inside the Village. Check setbacks, flood information, easements, pervious area, landscaping and Engineering requirements before uploading plans.
Open the permit form finder
Choose the exact work type and download every listed Village form before creating the application.
Create or sign in to ProjectDox
Use an email address that will remain active for the entire permit. ProjectDox sends invitations, tasks and approved-file notices to this account.
Complete the online application carefully
Enter the legal owner, project address, scope, value, contractor and trade information exactly as shown on the supporting documents.
Upload PDFs using the Village naming standard
Upload plans, forms and supporting documents as PDF files with the required ProjectDox codes and file names.
Accept and complete every assigned task
Open ProjectDox notifications, accept the task, read review comments and upload the requested correction package.
Pay fees and download approved documents
Follow the Village invoice instructions, confirm permit issuance and download the approved plans and permit card.
Post the permit and complete inspections
Keep approved documents at the site, schedule the correct inspections and preserve confirmation numbers and final results.
Name Files the Way Royal Palm Beach Expects
Document |
Village code example |
ProjectDox filename example |
|---|---|---|
Contractor Data Sheet |
CONT 001 |
CONT001Contractor Data Sheet.pdf |
Engineered Design |
ENGD 001 |
ENGD001Engineered Design.pdf |
Energy Calculation |
ENER 001 |
ENER001Energy Calculation.pdf |
Product Approval |
NOA 001 |
NOA001Product Approval.pdf |
Notice of Commencement |
NOC 001 |
NOC001Notice of Commencement.pdf |
Planning/Zoning Pre-Check |
PZCK 001 |
PZCK001Planning and Zoning Pre Review Checklist.pdf |
Approved Site Plan |
SITE 001 |
SITE001Approved Site Plan.pdf |
Recent Survey |
SURV 101 |
SURV101Survey.pdf |
Final Survey |
SURV 501 |
SURV501Survey Final.pdf |
Elevation Certificate |
SURV 601 |
SURV601Survey Elevation Certificate.pdf |
Roof Specification Sheet |
RSPEC 001 |
RSPEC001Roof Spec Sheet.pdf |
Window and Door Checklist |
WIND 001 |
WIND001Window Door Checklist.pdf |
Prepare the Complete Permit Folder Before Uploading
People and authorization
- Legal owner information
- Contractor Data Sheet
- Contractor license information
- Owner-builder statement if applicable
- Authorized-agent documents
- Recorded NOC when required
Property and site
- Recent property survey
- Site or location plan
- Setbacks and easements
- Pervious-area calculation
- Landscape information
- Flood and elevation data
Construction documents
- Floor plan and perimeter
- Design or engineered plan
- Structural and truss design
- Florida product approvals or NOAs
- Energy and insulation forms
- Project-specific checklist
Building Approval Does Not Replace Zoning, Flood or Easement Review
Issue |
Why it matters |
Official next step |
|---|---|---|
Setbacks and structure location |
A code-compliant structure can still be too close to a property line or easement |
Contact Planning & Zoning at 561-790-5131; driveway specifications may involve Building |
Flood zone and elevation |
Equipment, floors, generators, additions and new buildings may require elevation information |
Use the Village flood map and confirm the current determination with Planning & Zoning |
Utility, drainage or canal easement |
Construction inside an easement may require consent, hold-harmless documentation and recording |
Obtain the Easement Agreement and Engineering or Building approval before construction |
Pavers and impervious area |
Pavers, patios, pools and additions can affect drainage and required pervious area |
Complete the Pervious Area Form and show all hard surfaces on the survey |
Right-of-way or swale |
Driveways, landscaping and utility work can enter public right-of-way |
Use the Village Engineering Permit and right-of-way/easement process |
Tree or vegetation removal |
Residential landscape minimums and approved commercial landscape plans may apply |
Ask Building or Planning whether a Vegetation Removal Permit is required |
Commercial exterior change or sign |
Architectural approval may be required for colors, materials, elevations, roofs and signs |
Confirm AARC or Planning approval before submitting the building permit |
Docks, Seawalls and Canal Work Need a Waterway Permit
Waterway Permit triggers
- Pier construction or alteration
- Pilings
- Bulkheads
- Seawalls
- Reefs or breakwaters
- Filling, excavation or dredging
Prepare before filing
- Property and canal survey
- Engineered design
- Easement agreement
- Hold-harmless agreement
- Seawall regulations
- Special inspection information
Choose the Responsible Permit Applicant Before Submission
Licensed contractor route
- Verify active Florida license
- Confirm correct license classification
- Use matching business and contact information
- Upload the Contractor Data Sheet
- Confirm subcontractor responsibilities
- Keep change-of-contractor documents if needed
Owner-builder route
- Complete the Village owner-builder statement
- Understand personal responsibility
- Coordinate all subcontractors
- Schedule every inspection
- Maintain approved documents on site
- Do not present an unlicensed contractor as an employee
Royal Palm Beach Permit Fees, Revisions and Reinspection Charges
Fee item |
Village-posted amount or formula |
Practical meaning |
|---|---|---|
Minimum building permit fee |
$75 |
The schedule uses tiered valuation percentages above the minimum |
Plan-review filing fee |
30% of estimated permit fee |
Applied to the permit fee when the permit is issued |
Administrative permit closure request |
$75 |
Does not automatically replace inspections or code compliance |
Minor post-permit revision |
$100 |
Use only after staff confirms the revision is classified as minor |
Major post-permit revision |
30% of permit fee or $500, whichever is greater |
A value increase can also affect permit charges |
Change of contractor |
$100 |
Complete the formal contractor-change process before new work continues |
Permit renewal |
50% of current permit fee; posted $37.50 minimum |
Subject to Building Official approval and current code review |
Reinspection |
$50 |
Avoid requesting an inspection before all corrections are complete |
Failure to post permit |
$50 plus a $50 reinspection fee |
Keep the permit and approved documents visible at the project |
New Tenant Inspection |
$75; valid 60 days |
The schedule lists a $100 fine for occupancy without the inspection |
Temporary CO or Completion |
$500 or 20% of permit fee up to $2,000, whichever is greater |
A temporary certificate requires approval and unresolved-item review |
Additional charges to check
- Florida education and radon fees
- Palm Beach County impact fees for applicable new construction or additions
- Easement recording fee
- Planning, Engineering or waterway fees
- Credit-card processing charge
- Separate business or tenant requirements
Private-provider fee treatment
The posted schedule describes a 25% reduction of applicable permit portions when an approved private provider performs plan review or inspection services.
The private-provider request must be submitted and approved with the initial permit application to receive the stated reduction.
Schedule, Confirm and Prepare for Royal Palm Beach Inspections
Automated inspection line
The IVR system can schedule inspections, cancel inspections and retrieve inspection results.
What the IVR asks for
Use the permit-card IVR number and the correct three-digit inspection code. Save the confirmation number after every transaction.
Estimated arrival time
The Village FAQ says a specific inspection time cannot be reserved. Call between 7:30 and 8:30 AM to request an estimated arrival time.
Inspection category |
Useful code examples |
Preparation |
|---|---|---|
Building |
110 Foundation, 114 Roof Sheathing, 117 Interior Framing, 145 Roof Framing, 151 Final Building |
Approved plans, permit card, structural work visible and safe access |
Fence, shed, screen and openings |
200 Final Screen, 202 Fence Final, 203 Shed Final, 208 Door Installation, 209 Window Change-Out |
Location, anchoring, product approvals and approved survey |
Electrical |
304 Rough Electrical, 305 Service, 313 Power Release, 398 Service Change, 399 Final Electrical |
Panels open as required, labels complete and work accessible |
Mechanical |
501 Air Conditioning, 503 Rough A/C, 504 Gas Piping, 598 Final Gas, 599 Final A/C |
Equipment data, condensate, electrical disconnect, access and clearances |
Plumbing |
601 Rough First Plumbing, 602 Top-Out, 605 Sewer, 614 Final Water Heater, 699 Final Plumbing |
Tests maintained, piping visible, fixtures complete and access available |
Pools |
700 Pool Steel, 702 Bonding, 703 Pool Deck, 709 Pool Enclosure, 706 Final Pool |
Barrier, alarms, bonding, equipment, drainage and safety affidavit |
Engineering and landscape |
400 Vegetation Removal, 405 Sod Final, 800 Sub-Grade, 805 Drainage, 807 Final Completion |
Approved civil or landscape plan, elevations and site stabilization |
Before requesting
- Permit is issued
- Correct inspection code selected
- Work is complete for that stage
- Required work remains visible
- Previous corrections are complete
- Site access is confirmed
Before the inspector arrives
- Permit is posted
- Approved plans are on site
- Address is visible
- Gates and rooms are accessible
- Safe ladders or access are ready
- Confirmation number is saved
Eligible Work May Be Inspected Through a Mobile Phone Camera
Examples listed by the Village
- In-progress roof inspection
- Water-heater change-out
- Air-conditioning change-out
- Electrical-service change-out
- Garage-door change-out
- Entry-door change-out
Virtual inspection steps
- Schedule the inspection by 2:00 PM the prior day.
- Call 561-790-5128 between 7:45 and 8:15 AM.
- Ask whether the inspection is eligible for virtual review.
- Receive the VUSPEX/RPB text during the assigned window.
- Accept the link and follow the prompts.
- Show the address, permit documents and requested work.
Keep the Permit Active With Approved Inspections
Village validity rule
The Building FAQ states that permits are valid for 180 days from issuance or from an approved inspection.
Do not schedule a placeholder inspection
The work must genuinely be ready for the requested stage. An avoidable failed inspection can create a reinspection charge.
Renew before restarting
Expired permits may require Building Official approval, renewal fees and review under the current Florida Building Code.
Do Not Occupy a New Business Space Before the Required Inspection
Prepare the occupancy package
- Proposed business use
- Existing Certificate of Occupancy
- Floor plan and occupant load
- Life-safety and accessible route
- Fire or suppression approvals
- Business Tax Receipt documents
Current fee-schedule warning
The Village-posted schedule lists a $75 New Tenant Inspection valid for 60 days.
It also lists a $100 fine for allowing occupancy without the required inspection.
Search Permit History Before Buying, Remodeling or Closing an Old Permit
Search Click2Gov
Use the application number, address, parcel number or name search.
Compare all related permits
Open building, electrical, plumbing, mechanical, pool, roof and accessory-structure records tied to the property.
Review inspections and final status
An issued permit does not prove the work passed final inspection. Look for final building and applicable trade results.
Check the actual property
Compare additions, pools, sheds, fences, converted rooms, windows, roofs and mechanical equipment with permit history.
Contact Building for missing documents
Provide the address, parcel number, permit number, approximate year and exact document needed.
Save final proof
Keep final inspections, Certificates of Occupancy, Certificates of Completion and approved plans with the permanent property records.
What Common ProjectDox and Permit Statuses Mean
Respond to Plan Review Comments With a Complete Revision Package
Action |
Strong response |
Delay-causing response |
|---|---|---|
Read the task |
Identify every Building, Planning, Engineering and trade comment |
Uploading plans without opening or accepting the task |
Write responses |
Answer the comment and identify the revised sheet or form |
Writing only “fixed” or “see plan” |
Coordinate documents |
Update site, architectural, structural and trade information consistently |
Leaving conflicting dimensions or equipment information |
Name files |
Reuse the Village naming code and correct document category |
Changing the file into an unrecognized generic name |
Field revision |
Obtain approval before constructing the changed scope |
Building first and asking the inspector to approve the change |
Report New Violations or Resolve Existing Unpermitted Work
Situation |
First action |
What usually closes it |
|---|---|---|
Suspected unpermitted construction |
Search permit history and submit a specific complaint |
Permit legalization, inspections, correction or removal |
Open Code Enforcement case |
Read the notice, deadline and cited condition |
Correct the condition and complete required verification |
Permit expired during construction |
Stop affected work and contact Building |
Approved renewal, current-code review and remaining inspections |
Work covered before inspection |
Do not continue covering adjacent work |
Expose the required work and pass the missed inspection |
Occupied commercial space without inspection |
Contact Building and Planning immediately |
New Tenant Inspection, permits, approvals and occupancy documentation |
Fix Common Royal Palm Beach Permit Problems
Problem |
Likely cause |
Best next step |
|---|---|---|
ProjectDox login fails |
Browser cache, unsupported browser or incorrect account email |
Use current Chrome, Edge or Safari, clear cache and reset the password. |
Application is not moving |
Task not accepted, missing file or incorrect filename |
Open the workflow task and compare uploads with the Village naming standards. |
Permit record not found |
Wrong jurisdiction, address format or search field |
Confirm Village limits and search by application number or parcel. |
Planning rejected the location |
Setback, easement, lot coverage, landscaping or pervious-area conflict |
Revise the survey or design before resubmitting the building plans. |
Inspection was not scheduled |
Wrong IVR number, wrong code or missed cutoff |
Schedule before 2:00 PM, verify the three-digit code and save confirmation. |
Virtual inspection did not proceed |
Inspection is ineligible, connection is weak or work cannot be shown clearly |
Request an in-person inspection and keep the work visible. |
Permit approved but not issued |
Fees, NOC, contractor documents or outside review remains |
Ask for the exact issuance checklist rather than opening another application. |
Old permit remains open |
Final inspection or trade sign-off was missed |
Collect the permit history and ask which current closeout inspections are required. |
What to Say When You Call the Village
“I am planning [exact work] at [address and parcel number]. Which ProjectDox permit type, Planning pre-check and project-specific forms are required?”
“ProjectDox application [number] shows [status]. I completed task [task name] and uploaded [files]. Which item is still preventing the next review step?”
“I need inspection code [three-digit code] for permit [number]. The work is ready and visible. Can you confirm the scheduling cutoff and whether it qualifies for virtual inspection?”
“Permit [number] at [address] is not closed. Which building, electrical, plumbing, mechanical, pool or Engineering final is still outstanding?”
Royal Palm Beach Permit Completion Checklist
- Village jurisdiction confirmed
- Planning and zoning pre-check completed
- Flood and elevation requirements checked
- Easement and Engineering permits checked
- Correct form-finder package downloaded
- ProjectDox account created
- Every PDF named correctly
- All review tasks completed
- Fees and impact-fee requirements cleared
- NOC uploaded when required
- Permit formally issued
- Permit and plans posted on site
- Inspection confirmation numbers saved
- All corrections completed
- Building and trade finals passed
- CO or Certificate of Completion saved
Royal Palm Beach Building Division Map
Building hours: Monday–Friday, 8:00 AM–4:30 PM.
Bring: Address, parcel number, application or permit number, survey, correction notice and a clear list of questions.
Open the Correct Royal Palm Beach Permit Resource
Royal Palm Beach Building Department Questions
Is it the City or Village of Royal Palm Beach Building Department?
The official local government is the Village of Royal Palm Beach. The Village Building Division handles qualifying permits, plan review, inspections and certificates for properties inside Village boundaries.
What is the Royal Palm Beach Building Division phone number?
Call 561-790-5128 for building-permit, plan-review, inspection and Certificate of Occupancy questions. The Building Division is located at Village Hall, 1050 Royal Palm Beach Boulevard.
Where do I apply for a Royal Palm Beach building permit?
Use the Village ProjectDox e-permitting portal. Create an account, complete the application and upload the required forms, plans and supporting documents as correctly named PDF files.
How long does Royal Palm Beach permit review take?
The Village Building FAQ states that permit issuance usually takes about seven to ten business days and commercial projects commonly take 15 to 30 business days. Missing documents, corrections and outside approvals can extend the review.
How do I schedule a Royal Palm Beach inspection?
Call the automated IVR inspection line at 561-790-5144. Enter the IVR number shown on the permit card and the correct three-digit inspection code, then save the confirmation number.
What is the Royal Palm Beach inspection cutoff?
The current virtual-inspection page says all in-person and virtual inspections must be scheduled by 2:00 PM on the previous day. An older IVR brochure lists midnight. Schedule by 2:00 PM and confirm with the Building Division when timing is critical.
How long is a Royal Palm Beach permit valid?
The Village Building FAQ states that a permit is valid for 180 days from issuance or from an approved inspection. Contact Building before the permit expires when work will not progress within that period.
Can I complete an inspection virtually?
Some inspections may qualify, including in-progress roofing, water-heater replacement, air-conditioning replacement, electrical-service replacement and garage or entry-door replacement. The inspector can require an in-person inspection.
How do I search Royal Palm Beach permit history?
Use the Village Click2Gov Building Permit search. Search by application number, address, parcel number or name, then review all related permits and inspection results.
Do I need a permit for a fence, shed, pool or air conditioner replacement?
The Village FAQ identifies fences, sheds, pools, driveways, patios, screens, additions, air-conditioning replacements, water-heater replacements and new construction as common projects requiring permits. Confirm the exact package with Building before work starts.
Source and Accuracy Notes
Building-Department.org is an independent guide and is not the Village of Royal Palm Beach or Palm Beach County.
This page was rebuilt using official Village Building, ProjectDox, permit-form, inspection, virtual-inspection, Planning, Engineering, fee, flood-map, waterway and Code Enforcement resources.
Last reviewed: July 21, 2026.
Forms, fees, inspection cutoffs, staff assignments, portal instructions and building-code requirements can change. Confirm time-sensitive information with the Village before filing, paying, visiting or starting work.

Khushboo Bobade is a public records researcher and editorial writer specializing in government service documentation and construction permit systems.
Her research focuses on explaining building permits, inspection procedures, zoning regulations, and public permit records maintained by local government building departments across the United States.
Professional profile: View LinkedIn Profile
Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links
Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.
What building department task do you need help with?
Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.
Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.
Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.
Building Permit Type Finder
Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.
Permit Fee Estimate Calculator
Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.
Inspection Readiness Checklist
Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.
Zoning and Setback Pre-check
Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.
Plan Review Timeline Estimator
Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.
Permit Records Search Helper
Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.
Official Building Department Resource Finder
Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.
Building Department vs Planning/Zoning
- Building Department: permits, plan review, inspections, code compliance, certificates.
- Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.
Best sitewide placement
Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.
Important note
This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.