Clermont County Building Department | Permits, Inspections & Official Contact

Clermont County Permit Central guide

Get Zoning Approval, Submit Digital Plans and Close Your Clermont County Permit

Clermont County does not begin with a normal portal-only application. First complete and email the signed General Permit Application. Permit Central then sends a project-specific Citrix ShareFile link for your PDF construction documents.

This guide shows the real sequence: local township or village zoning, sewer or septic approval, flood and driveway screening, digital plan upload, county review, separate rough-energy inspections, fee calculation, virtual-inspection options and final Certificate of Occupancy.

Email application first, then use the private ShareFile upload link
County building review plus local zoning, Health and utility approvals
Current June 2026 rough-inspection change and closeout workflow
Clermont County permit moving from zoning and plan review to final occupancy A construction plan and permit move through zoning, Permit Central, separate rough inspections and final occupancy above animated river waves and a bridge. SITE + BUILDING PLAN SHAREFILE PERMIT CERTIFICATE OF OCCUPANCY CLERMONT COUNTY
!
New inspection rule effective June 1, 2026 Rough Energy/Insulation and Electric Service Release inspections can no longer occur with the initial Rough Building, Electrical and Mechanical inspections. Schedule them separately at least one day after the applicable rough inspections have passed.
Start with one action

What Do You Need From Clermont County Permit Central?

Clermont County Next-Step Finder

Select your project or problem to see the correct local route.

Official contact panel

Clermont County Building Department Address, Phone and Hours

Permit Central 513-732-7213 Applications, plan review and inspections
Department email PermitCentral@clermontcountyohio.gov Applications, revisions and records
Public Health 513-732-7499 Plumbing, septic and private water
Water Resources 513-732-7970 County water-meter coordination
County Auditor 513-732-7150 Parcel ID and property information
Permit Central address 2275 Bauer Road Batavia, OH 45103
Lobby hours 8:00 AM–4:00 PM Monday through Friday
Business hours 8:00 AM–4:30 PM Monday through Friday
Best time to speak with an inspector: The department says inspectors are typically available in the office from 8:00–9:00 AM and again around 3:00–4:00 PM after completing their routes.
County coverage is not simple

Confirm Which Building Department and Zoning Office Serve the Property

1

Building-code jurisdiction

Clermont County Building Inspection regulates the Ohio Building Code in all unincorporated and most incorporated areas of Clermont and Brown Counties.

It regulates the Residential Code of Ohio in all unincorporated and most incorporated areas of Clermont County.

2

Zoning jurisdiction

Your township or village normally handles land use, setbacks, height, lot coverage, signs and accessory-building placement.

Residential applicants must provide the zoning permit or approval letter when applying.

Do not assume every city or village has a separate building department. Call Permit Central with the exact property address and parcel number to confirm who performs building review and inspections.

Find the Parcel ID Find the Zoning Office

Permit decision table

Which Clermont County Permit Fits the Work?

Project
Starting route
Approval to check before filing
New one-, two- or three-family dwelling
Residential building application
Zoning, certified site plan, sewer or septic, driveway, flood, WMSC, water and energy path
Room addition or attached garage
Residential addition
Zoning, site plan, flood determination, septic or sewer and structural plans
Deck
Deck building permit
Zoning, site plan, septic approval and narrow exemption test
Shed or detached garage
Accessory-building permit
Zoning, site placement, property lines, size, use and foundation
Roof replacement
Roof-replacement permit
Scope, structural repairs and work valuation
Electrical installation
Electrical approval
Service size, circuits, temporary power and separate service-release inspection
HVAC, fireplace or pressure piping
Mechanical or pressure-piping approval
System count, fuel type, pressure test and utility release
Plumbing or private sewage
Public Health permit
Installer registration, plumbing plan review, septic or private-water approval
Pool or hot tub
Pool approval
Zoning, electrical bonding, barriers, equipment and site placement
Fence
Zoning first
A county building permit is required when the fence is over six feet tall
Commercial construction or change of use
Nonresidential plan review
Zoning, sealed plans, accessibility, Fire, plumbing, food, WMSC, water and sewer
Demolition
Demolition approval
Utilities, asbestos, WMSC, Health and site-restoration requirements
Small-project exemption check

Some Small Structures May Avoid Building Approval—but Not Zoning

Narrow deck exemption

The county’s updated deck guide identifies an exemption only when all conditions apply:

  • No more than 200 square feet
  • No point more than 30 inches above grade
  • Not attached to the dwelling
  • Does not serve the required exit door

Small detached shed exemption

The county’s current shed guide identifies an exemption for certain one-story detached storage sheds, playhouses and similar structures not exceeding 200 square feet.

Zoning placement rules still apply.

The general FAQ broadly lists decks and storage buildings as permit projects. Send the dimensions, height, attachment method and use to Permit Central and the zoning office before relying on an exemption.
Correct application sequence

How to Apply Without Sending Plans to the Wrong Place

Find the parcel number and exact jurisdiction

Use the Auditor property search and identify the township or village shown for the site.

Save: Parcel ID, legal owner, street address and zoning jurisdiction.

Obtain zoning approval

Contact the township or village and request the zoning permit or written approval for the exact project.

Residential filing: The zoning approval should include the parcel number and property address.

Resolve sewer, septic, water and driveway approvals

Public-sewer projects may require County Water Resources permits. Onsite sewage, private water and plumbing are handled through Public Health. A driveway curb-cut approval may also be required before building issuance.

Complete and sign the 2026 General Permit Application

Enter the project location, township or village, owner, applicant, permit categories, scope, floor areas and estimated cost for every regulated trade.

Do not skip page two: Residential applicants must identify the energy-compliance path.

Email the application before sending digital plans

Email the signed application to PermitCentral@clermontcountyohio.gov using an accurate and monitored primary-contact email.

Subject example: New Permit Application — 123 Main Street — Parcel 00-00-00.000.

Wait for the project-specific ShareFile link

After processing the application, Permit Central emails a secure Citrix ShareFile upload link for that project.

Never reuse the link: Each ShareFile link is tied to one application.

Upload PDF construction documents

The electronic-submittal guide accepts PDF files. Upload a complete coordinated set rather than photographs or incomplete pages.

Useful file names: Site-Plan.pdf, Architectural-Plans.pdf, Structural-Details.pdf and Energy-Compliance.pdf.

Pay the application and applicable permit fees

Permit Central accepts cash, check, money order and credit card. Make checks payable to Clermont County Treasurer. Additional credit-card charges apply.

Track review through Citizen Self Service

Search the permit number for a quick view of permit and review status. Respond to correction letters with a complete revised set and response letter.

Download the issued field plans after payment

When issuance is ready, the primary contact receives an invoice and then a link to download the stamped and signed field-set plans.

Keep those plans onsite throughout construction and every inspection.

Read ShareFile Instructions Email Permit Central

Application dependency board

Items That Can Stop Processing Before Plan Review Begins

Required for all applicable projects

  • Complete signed application
  • Construction documents
  • Applicable initial fees
  • Floodplain determination
  • Sewage-disposal approval
  • Zoning approval

Permit Central coordinates

  • Building review
  • Mechanical and electrical
  • Fire-protection review
  • WMSC approval
  • Flood-development review
  • Airport zoning

Other agency dependencies

  • Local Fire Department
  • County Engineer driveway drainage
  • Public Health plumbing
  • Public Health food licensing
  • Water and sewer permits
  • ODOT for state-highway access
Residential plan readiness

Put Enough Detail on the Plans to Pass Review

Site plan

  • Property dimensions
  • Distance to property lines
  • Existing and proposed structures
  • Walks and driveways
  • Easements
  • Clearing and grading limits

Drainage and utilities

  • Existing and proposed grades
  • Downspout drainage route
  • Stormwater systems
  • Sewer line and invert
  • Private sewage information
  • Driveway curb-cut approval

Building drawings

  • Foundation plan
  • Existing and proposed floor plans
  • Room names and uses
  • Exterior elevations
  • Cross sections from footing to roof
  • Structural framing details

Life safety

  • Emergency-escape windows
  • Stairs and guards
  • Smoke alarms
  • Carbon-monoxide alarms
  • Garage separation
  • Hazardous-location glazing

Energy and moisture

  • Energy-compliance path
  • Window and door U-factors
  • Insulation R-values
  • Vapor barriers
  • Ventilation
  • Permanent energy certificate

Local design details

  • 30-inch frost depth
  • Foundation anchors
  • Drain tile
  • Truss drawings
  • Window flashing
  • Roof and attic ventilation
The general FAQ says residential projects normally require two plan sets and commercial projects four sealed sets. Applicants using electronic review may submit PDFs instead of four physical commercial sets.
Review-time expectations

Plan Review Time Depends on the Project and Correction Cycles

Residential target 10–15 business days Department-wide goal shown in the official FAQ
Commercial target 15–30 business days Department-wide goal shown in the official FAQ
Room-addition handout 5–7 days Project-specific estimate for a complete room-addition package
Official materials show different review estimates. Ask Permit Central for the current queue instead of scheduling construction around the shortest published figure.
Local zoning directory

Find the Township or Village Zoning Contact

Jurisdiction
Phone
Ask about
Batavia Township
Use, setbacks, accessory structures and certificate
Batavia Village
Village zoning approval
Bethel Village
Village land-use and placement rules
Chilo Village
Zoning and flood-development coordination
Felicity Village
Zoning approval
Franklin Township
Township zoning permit
Goshen Township
Setbacks, structures and land use
Jackson Township
Township zoning certificate
Miami Township
Zoning, signs and site development
Monroe Township
Zoning approval
Moscow Village
Village zoning and flood review
Neville Village
Village zoning and flood review
New Richmond Village
Village zoning, site and WMSC
Newtonsville Village
Village zoning approval
Ohio Township
Township zoning certificate
Owensville Village
Village zoning and WMSC
Pierce Township
Zoning permit and development standards
Stonelick Township
Township zoning approval
Tate Township
Township zoning certificate
Union Township
Zoning, commercial uses and site rules
Washington Township
Township zoning approval
Wayne Township
Township zoning certificate
Williamsburg Township
Township zoning and WMSC
Williamsburg Village
Village zoning, flood and WMSC
Inspection workflow

Schedule at Least One Day Ahead and Keep the Approved Plans Onsite

Booking One day ahead Inspections are scheduled for the next available business day
Inspector questions 8–9 AM Typical morning office availability
Afternoon questions About 3–4 PM After inspection routes
Reinspection trip $35 Failed, partial, additional or no-access trip

Before scheduling

  • Correct permit number
  • Inspection stage complete
  • Prior inspections passed
  • Work remains visible
  • Approved plans onsite
  • Changes formally approved

Before the inspector arrives

  • Clean and safe access
  • Building unlocked
  • Adult present if occupied
  • Address sign visible from road
  • Lot and owner name posted
  • Required test equipment ready
No access, a partial inspection or a failed inspection produces a reinspection charge. An occupied building will only be entered when the owner or another adult is present.
June 2026 inspection sequence

Do Not Combine the New Separate Rough-Energy Steps

Electrical, mechanical and other rough work complete
Rough inspections requested
All initial rough inspections pass
Install insulation and energy provisions
Schedule Rough Energy and service release separately
Drywall, finals and occupancy
Rough Energy must occur after the other rough inspections and before drywall. Electric Service Release also waits until applicable rough and insulation inspections are approved.
Inspection stages

Know What Must Be Visible at Each Stage

Inspection
Work that should be ready
Do not do yet
Footing
Excavation complete, forms placed and natural bearing soil visible
Place concrete before approval unless the inspector authorizes the condition
Foundation
Structural steel visible and concrete forms in place
Conceal reinforcement
Crawl
Floor framing, beams and vapor barrier ready
Install the subfloor before inspection
Electrical rough
All electrical work that will be concealed completed
Cover boxes, wiring or circuits
Mechanical rough
All concealed mechanical work completed
Cover ducts, piping or connections
Building rough
Framing exposed; plumbing, heating and electrical roughs installed
Install insulation before rough approvals
Energy rough
Insulation, windows, doors, fire stopping and concealed energy provisions installed
Install drywall before approval
Pressure test
Pressure piping and supports visible with test gauge already under pressure
Wait for the inspector to pressurize the system
Trade finals
Boxes closed, fixtures installed, circuits identified and systems complete
Request Building final with incomplete trade work
Building final
All building work and every required final inspection completed
Occupy before the Certificate of Occupancy or Conditional C/O
Virtual inspection option

Ask Whether Your Inspection Still Qualifies for Video Review

Work listed in the county guide

  • Temporary power poles
  • HVAC replacement
  • Gas lines
  • Insulation
  • Decks
  • Solar systems

Other listed inspections

  • Above-ceiling work
  • Sunrooms and patio enclosures
  • Soil or footing
  • Nonstructural rough framing
  • Reinspections
  • Accessory structures

Equipment

  • Reliable internet
  • Smartphone or tablet
  • Video-call application
  • Flashlight
  • Tape measure
  • Approved plans onsite
The county still links its virtual-inspection guide, but the document was originally revised in 2020. Call 513-732-7213 to confirm current eligibility, available video platform and scheduling procedure.

Open Virtual Inspection Guide

Current published county schedule

Calculate the Base Clermont County Permit Components

Every application $50 Base processing fee
Residential surcharge 1% Applied to county permit fees
Nonresidential surcharge 3% Applied to county permit fees
Reinspection $35 Per failed, partial, additional or no-access trip

Residential Base Fee Estimator

Select the project and enter the affected or covered area when requested.

Selected fee
Published amount
Important detail
Residential new construction or addition
$0.12 per square foot
$120 minimum; rounded to next 100 square feet
Residential alteration
$0.06 per square foot
$70 minimum; rounded to next 100 square feet
Reroof or roof repair
$70
One inspection; base and surcharge also apply
Deck
$105
Three inspections; base and surcharge also apply
Shed or garage at least 200 square feet
$105
Three inspections
Residential above-ground pool
$70
Pool circuit and bonding; one trip
Residential in-ground pool
$105
Pool circuit and bonding; two trips
Residential WMSC site
$70
Applicable in county-enforced WMSC areas
Residential floodplain development
$50
Plus base fee when property is in a regulated flood area
Permit started without approval
Double permit fee, up to $1,000
Initial permit charges still apply
The county’s current fee page still identifies the schedule effective January 1, 2022 as the active published schedule. Confirm the live invoice before payment because water, sewer, plumbing, electrical and review-dependent charges may be added later.

Verify Current Fee Page Open Full Fee Schedule

Flood, stormwater and site dependencies

A Building Application Does Not Replace Site or Environmental Approval

Floodplain

Development in a special flood hazard area requires county floodplain approval where Clermont County administers the regulations.

  • Check the FEMA map
  • Complete the flood-development application
  • Show lowest-floor elevation
  • Use a design professional when required

Water Management and Sediment Control

WMSC review can apply to residential, nonresidential and multi-lot development.

  • Install sediment controls
  • Prepare construction entrance
  • Maintain controls throughout work
  • Complete basin verification when required

One acre or more disturbed

Contact Ohio EPA for applicable stormwater requirements before clearing or grading more than one acre.

Wetlands or navigable water

Contact the U.S. Army Corps of Engineers when the site may affect wetlands or regulated waterways.

State highway access

Projects connecting to a state highway may need Ohio Department of Transportation coordination.

Demolition and asbestos

Complete the required air-quality and asbestos notifications before demolition or regulated renovation.

Permit expiration

Keep Inspection Activity on the Record or Request an Extension Early

Approval period

The March 2026 county form says approval or permit expiration occurs one year after approval.

Stopped construction

After work begins, approved plans become invalid when work is delayed or stopped for more than six months without inspection activity.

Extension options

  • One one-year extension when work has not started
  • Up to two six-month extensions after work starts
  • Residential fee shown as $50.50
  • Commercial fee shown as $51.50
Request the extension before expiration. Work performed after the permit expires may require a new application, another plan review and new fees.

Open 2026 Extension Form

Occupancy and closeout

Do Not Occupy Until the County Issues the Certificate

Before a final Certificate of Occupancy

  • Building final passed
  • Electrical final passed
  • Mechanical final passed
  • Plumbing final approved by Health
  • WMSC final completed
  • All permit fees paid

Conditional occupancy

An owner may request a Conditional Certificate of Occupancy when the building is safe and sanitary, life-safety systems remain operational, construction areas are separated and all outstanding fees are paid.

Approval is not automatic.

The fee schedule lists penalties for occupying without final inspections and a valid Certificate of Occupancy: $50 residential and $500 nonresidential.

Open Conditional Occupancy Request

Permit and property records

Search Citizen Self Service Before Sending a Records Request

Open Citizen Self Service

Search by permit, plan, inspection, property or other available record information.

Review permit and inspection history

The shared portal includes Building Inspection and Public Health permit and inspection data from January 2019 to the present.

Confirm the Certificate of Occupancy or Completion

An issued permit number does not prove that required finals passed or occupancy was approved.

Email a focused records request

Send the exact property address, parcel ID, approximate year, permit number and requested record to PermitCentral@clermontcountyohio.gov.

Email subject: Records Request — 123 Main Street.

Understand the construction-plan limit

Clermont County states that construction plans are destroyed when a project is completed. Contact the builder, design professional, contractor or previous owner for old plan sets.

Status troubleshooting

Fix Common Clermont County Permit Problems

Problem
Likely reason
Best next action
No ShareFile link received
Application not processed, incomplete form or incorrect email
Email the signed form again with address and parcel number, then call Permit Central.
Application cannot be processed
Missing zoning, sewage, flood or Health approval
Use the all-project checklist and supply every prerequisite.
Plans repeatedly receive corrections
Incomplete dimensions, unclear site data or uncoordinated revisions
Submit a complete revised set with the same sheet numbers and a response letter.
Building rough will not pass
Electrical, mechanical, plumbing or another rough inspection remains open
Pass all related rough inspections before or with the Building rough.
Electric service was not released
Rough or insulation inspection remains incomplete
Follow the June 2026 separate-inspection sequence.
Inspector charges a no-access fee
Locked building, unsafe access, no adult home or work area inaccessible
Correct the access problem before rescheduling.
Building final passes but occupancy is not issued
Trade, plumbing, WMSC, Fire, sewer or fee item remains open
Request a complete closeout list for every permit category on the application.
Old plans cannot be found
County destroyed the construction plans after project completion
Request permit and inspection records, then contact the original builder or owner for plans.
Ready-to-use scripts

What to Say When You Contact Permit Central

Jurisdiction question
“I plan to [describe exact work] at [full address], parcel [number], in [township or village]. Does Clermont County perform the building review and inspections, and which local zoning approval do I need?”
ShareFile question
“I emailed the signed application for [address] on [date] but have not received the project-specific ShareFile link. Please confirm whether the application is complete and processed.”
Inspection request
“I need the [inspection type] inspection for permit [number]. The approved plans are onsite, the work is visible and safe access will be available.”
Closeout question
“Permit [number] appears complete, but no Certificate of Occupancy is available. Which Building, electrical, mechanical, plumbing, WMSC, Fire or fee item remains open?”
Final project checklist

Do Not Consider the Project Finished Until These Are Confirmed

  • Parcel and building jurisdiction confirmed
  • Township or village zoning approved
  • Sewer, septic and water approvals complete
  • Flood and WMSC review complete
  • Signed 2026 application submitted
  • Project-specific ShareFile link received
  • Complete PDF plans uploaded
  • Plan corrections resolved
  • All required fees paid
  • Stamped field plans onsite
  • Initial rough inspections passed
  • Separate Energy Rough completed
  • All final inspections passed
  • Certificate of Occupancy or Completion issued
Office location

Clermont County Permit Central Map

Address: 2275 Bauer Road, Batavia, OH 45103.
Lobby: 8:00 AM–4:00 PM, Monday through Friday.
Bring: Property address, parcel ID, permit number, zoning approval and the exact question or document that needs review.
Official resources

Open the Correct Clermont County Permit Resource

Frequently asked questions

Clermont County Building Department Questions

How do I apply for a Clermont County building permit?

Complete and sign the 2026 General Permit Application, then email it to PermitCentral@clermontcountyohio.gov. After processing the application, Permit Central emails the primary contact a project-specific Citrix ShareFile link for PDF construction documents.

What is the Clermont County Building Department phone number?

Call Permit Central and the Building Inspection Department at 513-732-7213. The office is at 2275 Bauer Road, Batavia, Ohio 45103.

Does Clermont County handle permits inside cities and villages?

The county regulates commercial building codes in all unincorporated and most incorporated areas of Clermont and Brown Counties. It handles residential codes in all unincorporated and most incorporated areas of Clermont County. Confirm the exact property before applying.

Do I need zoning approval before applying?

Yes, when applicable. Residential applicants must provide a zoning permit or approval letter from the township or village. The approval should identify the parcel number and project address.

How long does Clermont County plan review take?

The department’s general target is 10–15 business days for residential review and 15–30 business days for commercial review. A separate room-addition guide lists 5–7 days, so ask about the current project-specific queue.

How do I schedule a Clermont County building inspection?

Call 513-732-7213 when the required stage is complete. Inspections must be scheduled at least one day in advance and are placed on the next available business day.

What changed for rough inspections on June 1, 2026?

Rough Energy or Insulation and Electric Service Release inspections can no longer occur with the initial Rough Building, Electrical and Mechanical inspections. They must be scheduled separately at least one day after the applicable rough inspections pass.

How much is a Clermont County residential building permit?

The published schedule starts with a $50 base fee. Residential new construction and additions are $0.12 per square foot with a $120 minimum, while residential alterations are $0.06 per square foot with a $70 minimum. A 1% state surcharge and other project fees are added.

Can I get copies of the original construction plans for an old house?

Usually not from the county. Permit Central states that construction plans are destroyed after a project is completed. Permit and inspection records may still be requested, but old plans should be sought from the builder, contractor, designer or previous owner.

Can I occupy a building after the final work is complete?

Not until the Building Department issues a Certificate of Occupancy or approved Conditional Certificate of Occupancy. All required finals and outstanding fees must be resolved.

Source and accuracy note

Official Information Used for This Guide

Building-Department.org is an independent informational guide and is not Clermont County Permit Central.

This page was checked against Clermont County Permit Central, the 2026 General Permit Application, electronic ShareFile instructions, permit checklist, project handouts, inspection requirements, June 2026 inspection notice, virtual-inspection guide, fee schedule, extension form, zoning directory, flood and WMSC regulations, Public Health and public-record guidance.

Last reviewed: July 21, 2026.

Forms, inspection procedures, zoning contacts, code editions, fees and outside-agency requirements can change. Confirm time-sensitive requirements before submitting documents, paying fees or beginning construction.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.