Seminole County Building Department: Permit Search & Inspections

Seminole County permit action guide

Get the Application Number, Upload the Plans, Pass Review and Close a Seminole County Permit

Seminole County uses two connected online systems. Building Permits Online handles the application number, fees, permit status and inspections. ePlan handles drawings, documents, reviewer comments and stamped plans.

This guide shows the correct order, county-versus-city jurisdiction, owner-builder office requirement, 11:30 PM inspection cutoff, flood and septic checks, impact-fee timing, final Engineering inspection and current 2026 permit-law changes.

Click2Gov application, fee and inspection path
ProjectDox ePlan folders and corrections
Flood, septic, fire and Engineering closeout
Seminole County permit moving from Click2Gov to ePlan and inspection Two digital permit systems, a site plan, flood water, trees and a final inspection check illustrate the Seminole County permitting process. PERMIT SYSTEM ROUTE CLICK2GOV Application number • fees • inspections ePLAN / PROJECTDOX Documents • drawings • review comments REVIEWED APPLICATION FINAL INSPECTION PASSED SEMINOLE COUNTY
!
New Florida permit law effective July 1, 2026 House Bill 803 changed permit-fee calculations and created limited exemptions for certain qualifying projects under $7,500. Do not assume that project value alone removes the permit requirement. Review the county’s official instructions before beginning work.
Start with the task

Open the Correct Seminole County Service

First local decision

Seminole County or a City Building Department?

SC

Unincorporated Seminole County

Use the Seminole County Building Division when the parcel is outside an incorporated city and county jurisdiction is shown in the property or GIS record.

Search the official Property Appraiser

CITY

Inside an incorporated municipality

Properties inside Altamonte Springs, Casselberry, Lake Mary, Longwood, Oviedo, Sanford or Winter Springs may use the applicable city building office.

Do not use the mailing city as the only jurisdiction test.

Why this matters: A Sanford mailing address can still be in unincorporated Seminole County, while another Sanford property can be inside the city. Confirm the parcel’s jurisdiction before requesting the application number.
Official contact panel

Seminole County Building Division Phone, Email, Address and Hours

Building permits 407-665-7050 Applications, plan review and inspections
Customer-service email BPCustomerService@seminolecountyfl.gov Include address, parcel and application number
Building-plan help 407-665-7586 Plan-submittal and review questions
Office hours 8:00 AM–5:00 PM Monday through Friday
Last customer sign-in 4:30 PM Phone system closes at 4:45 PM
Inspection hours 7:30 AM–4:00 PM Actual arrival time depends on the daily route
Office address 1101 E. First Street Sanford, FL 32771
Parking tip: The county advises visitors to use the parking lot off San Carlos Avenue near the Board of County Commissioners chambers for easier access.
Permit decision table

Match the Project to the Correct Seminole County Permit

Project
Likely permit route
Extra document or review to check
New house, addition or major residential alteration
Residential building permit
Site plan, construction plans, zoning, energy, product approvals, septic or utility letter and impact fees.
Residential reroof
Residential reroof
Reroof supplement, product approvals, contractor documents and solar-panel reinstallation where applicable.
Window or exterior-door replacement
Window / door permit
Florida product approvals, opening information and installation details.
Fence or wall
Fence / wall permit
Fence checklist, site plan, zoning setbacks, easements and pool-barrier rules.
Swimming pool or enclosure
Pool permit
Pool Safety Act form, site plan, electrical bonding, barrier and septic separation.
Generator installation
Electrical / gas / fuel permit
Site location, generator specifications, one-line diagram, load calculations and possible fuel-tank permit.
Solar photovoltaic system
Solar electrical permit
Structural attachments, electrical plans, product details and reroof coordination.
Shed, barn, deck, screen room, garage or carport
Accessory-structure permit
Zoning, setbacks, site plan, structural plans, flood and utility easements.
Dock or boathouse
Dock / boathouse permit
Shoreline, environmental, flood, site-plan and waterbody approvals.
Commercial alteration, tenant build-out or change of use
Commercial building permit
Approved site plan, fire, accessibility, occupancy, fixture counts, energy and concurrency.
The scope controls the checklist. Seminole County’s permit matrix is a guide, not an all-inclusive list. Describe every structural, electrical, plumbing, mechanical, gas, fire and site component before asking which application to use.
Two-system workflow

Apply for a Seminole County Permit in the Correct Order

Verify jurisdiction
Update contractor license
Request application number
Upload in ePlan
Complete review corrections
Pay fees
Download stamped plans

Verify the property and Planning path

Confirm the parcel is in unincorporated Seminole County. Ask Planning about zoning, setbacks, site-plan approval, floodplain, utilities and use.

Important: Concurrent Building and Planning review requires prior approval from Planning and Zoning.

Confirm the contractor is current

The online application-number request requires the contractor’s license to be current in the county database.

Request an application number in Building Permits Online

Open Click2Gov and select Request Application Number. Enter the property, contractor, permit type and requested information.

Open the project in ePlan

Use ePlan to upload application documents, supporting documents and drawings. This is also where review comments and approved stamped documents are delivered.

Complete the Upload and Submit task

Uploading files alone may not release them to reviewers. Complete the assigned workflow task that tells the county the package is ready.

Check: The project should move from your upload task into county intake or review.

Answer each review agency separately

Use Plan Tracking Status in Click2Gov and review comments in ePlan. Open the agency name to see that reviewer’s result.

Resubmittal: Upload the complete corrected set, revised documents and a point-by-point response letter.

Pay and download the county-stamped set

Pay the permit, reinspection and applicable impact fees through the county payment portal. Download the stamped plans from ePlan before beginning construction.

Maintenance window: Online permit and payment services may be unavailable from 11:30 PM to 5:00 AM.
ePlan folder guide

Put Each PDF in the Correct ePlan Folder

Application Documents

  • Permit application
  • Property Appraiser legal printout or deed
  • Permit Authorization Form
  • Owner-Builder Statement when applicable
  • Recorded Notice of Commencement

Documents

  • Product approvals
  • Energy calculations
  • Gas-plan worksheet
  • Septic or utility letters
  • Supporting affidavits
  • Response letter

Drawings

  • Site plan
  • Architectural plans
  • Structural plans
  • Electrical one-line diagram
  • Plumbing or mechanical plans
  • Details and calculations
File-name examples: Permit-Application.pdf, Property-Appraiser-Legal.pdf, A101-Floor-Plan.pdf, S201-Foundation-Details.pdf and Response-Letter-Revision-1.pdf.
Official ePlan tutorial

Complete the Required Upload and Submit Task

Why this step matters

The county’s official tutorial explains how to complete the Building Division Upload and Submit task after the files are added.

A project can remain in the applicant’s workflow when documents were uploaded but the required task was not completed.

Open all official ePlan tutorials

Owner-builder and contractor rules

Who Can Apply and What Must Be Verified?

Licensed contractor

  • License current in county database
  • License Administration Form
  • Workers’ compensation or exemption
  • General liability insurance
  • Seminole County listed as certificate holder
  • Every subcontractor current before issuance

Registration packages may be sent by email, fax, ePlan task or delivered in person.

Owner-builder

  • Owner personally appears at Building Division
  • Valid government-issued photo ID
  • Affidavit signed in the office
  • Direct onsite supervision
  • Licensed trades verified
  • Legal and financial responsibility accepted

An owner cannot complete the entire owner-builder setup only through the online portal.

Owner-builder limitations: The county affidavit addresses qualifying one- or two-family residences, farm outbuildings and limited owner-use commercial work. It also warns that construction cannot be performed for sale or lease under the exemption and that a sale or lease within one year can create a presumption of violation.

Read Owner-Builder Instructions

Notice of Commencement

Record the NOC Before the First Inspection When Required

General construction

The county permit guide lists a recorded Notice of Commencement when the job value is greater than $5,000.

A/C change-out

The county permit matrix uses a threshold of $15,000 or more for an air-conditioning change-out.

Submission timing

The recorded document must be provided before the first inspection. It can be uploaded during submittal or sent to Building customer service.

Practical check: Confirm the owner name, property description and contractor details match the permit. A recorded NOC that cannot be connected to the application can still delay inspection.
Planning before building

Resolve Site Plan, Zoning and Impact Fees Early

Site-plan approval

An approved site plan is required before issuance of a building permit when the project is subject to site-plan review.

The Development Review Committee reviews site plans involving at least 2,500 square feet of buildings and paving area.

Pre-application meeting

Commercial, multi-family and complicated site projects benefit from a Development Review Committee pre-application meeting before formal submittal.

Open site-plan approval guidance

Impact-fee statement

The county says a complete impact-fee statement application generally requires 5–7 business days to process.

Open the impact-fee application

Project condition
Ask before final plans
Responsible contact
New commercial, institutional or multi-family project
Is approved site plan or DRC review required before Building review?
Planning & Zoning: 407-665-7371
New residential dwelling or additional units
Which school, library, fire, mobility or utility impact fees apply?
Development Services: 407-665-7371
Change of use from residential to commercial
Is the use allowed, and what accessibility, fire, parking and site upgrades apply?
Planning, Building and Fire
Driveway, sidewalk, drainage or right-of-way work
Is an Engineering or right-of-way utilization permit required?
Engineering: 407-665-7373
Flood, septic and utility checks

Property Conditions That Can Change the Permit Package

Flood-prone property

A permit is required to verify that new construction in a Special Flood Hazard Area meets elevation and flood-protection requirements.

Flood information: 407-665-7335
floods@seminolecountyfl.gov

Drainage or site flooding

Public Works can discuss drainage, sewer and site-flooding problems and may provide a site review when appropriate.

Public Works flood help: 407-665-7373
pwflood@seminolecountyfl.gov

Private septic system

Projects not served by public sewer may require a Health Department septic contingency letter or septic permit before Building approval.

Show the septic location and required separation from pools, additions and accessory structures.

Public utilities

New buildings, additions and changes in use may need a utility-availability letter or confirmation of water and sewer capacity.

Dock or shoreline work

Docks, boathouses, seawalls and shoreline alteration can require additional Planning, flood, environmental or water-management review.

Check shoreline forms

Generator fuel storage

A separate fuel-tank permit may apply based on tank type and capacity. Fire permitting applies to flammable and combustible-liquid storage.

Current construction codes

Codes Listed by Seminole County

Florida Building Code

The county identifies the Florida Building Code, 8th Edition (2023), including Building, Residential, Plumbing, Mechanical, Fuel Gas, Existing Building, Energy and Accessibility.

Electrical code

The adopted-code page lists the 2020 National Electrical Code, also known as NFPA 70.

Fire code

The county page lists the Florida Fire Prevention Code, 7th Edition, including Florida-amended NFPA 1 and NFPA 101.

Open Adopted Code Links

Avoid repeat corrections

Items Seminole County Says Are Commonly Missing

Common problem
What to put in the plan package
No approved site plan
Provide the approved Seminole County site plan when the project requires one.
Missing soils information
Provide a signed and sealed geotechnical report for applicable new construction.
Incomplete code analysis
Identify occupancy, construction type, area, height and applicable code information.
Missing plumbing-fixture calculation
Show the required fixture counts for the proposed occupancy.
No design loads
State wind design and other structural design criteria on the drawings.
Rated assembly details missing
Identify approved wall, floor, ceiling and penetration assemblies.
Accessibility information incomplete
Show accessible route, parking, vertical access and restroom elevations.
Product approvals incomplete or expired
Use current approval numbers and complete the county Product Approval Form.
Rooms are not labeled
Label every room, storage space, equipment area and intended occupancy.
Energy documents omitted
Provide applicable energy calculations and required compliance forms.
Inspection command board

Schedule the Correct Inspection Before the 11:30 PM Cutoff

Open Schedule or Cancel Inspection

Use Building Permits Online and search using the application or permit number.

Select the permit discipline

Choose the Schedule link beside the building, electrical, plumbing, mechanical or other permit that needs inspection.

Choose the available inspection type

Select the exact inspection from the county’s list. Do not schedule a final when rough or trade prerequisites remain open.

Submit by 11:30 PM for the next business day

Inspection requests and rescheduling must be entered online the previous day by 11:30 PM.

Portal warning: The text box shown below the scheduled date is not operational and is not visible to county inspection staff.

Keep approved documents on site

Have the permit, county-stamped plans, required affidavits and safe access ready. Do not conceal work before inspection.

Read the result before continuing

Use Inspection Status to confirm approval or read every correction before rescheduling.

Building inspections

Inspection hours:
7:30 AM–4:00 PM

Use the online system for scheduling and results.

Fire inspection

407-665-7422

Leave a message with permit, address and contact information or use the county’s online fire-inspection route.

After-hours inspection

Submit the county request form at least two business days in advance. Approval depends on staff availability and advance payment.

Final Engineering inspection

Complete the Site Inspection Before Requesting the Building Final

When to submit

Submit the Final Engineering Inspection form after all site work is complete and before requesting the final building inspection.

Open the Final Engineering form

What Engineering checks

  • ADA sidewalk conditions
  • Sidewalk, curb, sod and tree damage
  • Right-of-way restoration
  • Drainage and erosion
  • Sod and conveyance swales
  • Completed site improvements
County timing: When no issue is found, the county says the building final should become schedulable within approximately 48 hours after the Final Engineering inspection request is submitted.
Status decoder

What the Online Permit Status Means

Application number requested The initial record exists, but plans may not yet have been uploaded or released in ePlan.
Applicant upload task Upload the files and complete the assigned Upload and Submit task.
In agency review Open Plan Tracking Status and select each agency description to see its result.
Corrections required Upload a complete revision set, corrected documents and a point-by-point response.
Fees due Review every building, trade, impact, reinspection and administrative charge before payment.
Approved Confirm that the permit is issued and stamped plans are downloadable before starting work.
Issued / active Work may proceed within the approved scope and required inspection order.
Final / closed Save the inspection history, Certificate of Completion or Occupancy and final permit record.
Fees and 2026 changes

Use the Current Invoice Instead of an Old Valuation Formula

Fee calculator

The county calculator provides an estimate only. Staff-calculated fees control the permit.

Open the fee calculator

HB 803 fee change

Effective July 1, 2026, inspection fees must be based on the actual cost of providing inspections rather than the total construction cost.

The county says some common reroof, electrical-service and A/C change-out fees increased.

Online payment

Visa, MasterCard and Discover are accepted online. A convenience fee applies and is non-refundable.

Online payment is unavailable from 11:30 PM to 5:00 AM.

Limited under-$7,500 exemption: The new state law applies only to qualifying work that meets the statutory requirements. Use the county’s official update before treating a repair as permit-exempt.

Read Seminole County’s HB 803 update
Permit search and records

Find Permit History, Plans and Open Records

Search the property in Building Permits Online

Use the application or permit number when available. Review the application, plan tracking, fees, permit status and inspections separately.

Use the Building Public Request Portal

The county’s public portal can search permit records by permit type and date range.

Confirm the property ID

Compare the address, owner, parcel ID and legal description using the official Property Appraiser record.

Request unavailable permit files

Email BPPublicRecords@seminolecountyfl.gov with the property address, parcel ID and a clear description of the requested records.

Verify final status before a sale

A permit number does not prove that the project passed final inspection. Check every related building and trade permit.

Unpermitted and expired work

How to Start Fixing an Open, Expired or Unpermitted Project

Collect the history

  • Address and parcel ID
  • Permit or application number
  • Original scope
  • Plans and inspection results
  • Contractor information
  • Current photographs

Ask the Building Division

  • Is renewal or extension available?
  • Which inspections remain open?
  • Must concealed work be exposed?
  • Are revised plans required?
  • Are trade permits missing?
  • What proves final closure?

Use the correct form

  • Expired Permit Application Information
  • Permit Extension Request
  • Revision / Additional Information Form
  • Owner / Builder Statement
  • Public Records Request
  • Violation Lookup
Do not cover more work. Framing, wiring, plumbing, gas, roofing and structural connections may need to be exposed before the county can approve an after-the-fact permit.
Ready-to-use scripts

What to Say When You Contact Seminole County

Permit requirement:
“I am planning [exact work] at [address and parcel ID]. The property appears to be in unincorporated Seminole County. Which permit type, plans, Planning approvals, trade permits and inspections are required?”
ePlan task problem:
“My application number is [number]. I uploaded files in ePlan, but the project has not moved to review. Can you confirm whether the Upload and Submit task is still assigned to me?”
Review correction:
“I uploaded a complete revised plan set and response letter for application [number]. Which review agencies still show outstanding comments?”
Open permit:
“Permit [number] at [address] does not appear final. Which building, trade, Fire or Engineering inspection remains incomplete?”
Project closeout

Do Not Consider the Project Finished Until These Are Complete

  • County jurisdiction confirmed
  • Planning and zoning cleared
  • Correct application number obtained
  • Contractor registration current
  • ePlan task completed
  • Review corrections resolved
  • Impact fees paid
  • NOC recorded when required
  • Permit formally issued
  • Stamped plans on site
  • Building inspections passed
  • Trade permits finaled
  • Fire inspection completed
  • Final Engineering inspection completed
  • CO or Certificate of Completion obtained
  • Final records saved for owner
Office location

Seminole County Building Division Map

Address: Seminole County Building Division, 1101 East First Street, Sanford, FL 32771. Hours: Monday–Friday, 8:00 AM–5:00 PM. Last customer sign-in: 4:30 PM.
Official links

Seminole County Building Permit Resources

Frequently asked questions

Seminole County Building Permit FAQs

Where do I apply for a Seminole County building permit?

Start in Seminole County Building Permits Online to request an application number. After the record is created, use the county ePlan system to upload application documents, supporting documents and construction drawings.

Does Seminole County use Accela for building permits?

No. The county’s official workflow currently uses Click2Gov Building Permits Online for application numbers, fees, permit status and inspections, together with the ProjectDox ePlan system for plans, documents and review comments.

What are the Seminole County Building Division hours?

The Building Division is open Monday through Friday from 8:00 AM to 5:00 PM. The last customer sign-in is at 4:30 PM, and the Building Division phone system closes at 4:45 PM.

How do I schedule a Seminole County building inspection?

Use Building Permits Online, select Schedule or Cancel Inspection, enter the application or permit number, choose the correct permit discipline and inspection type, and submit the request by 11:30 PM on the prior day for the next business day.

Must an owner-builder visit the Seminole County office?

Yes. Seminole County requires an owner-builder to personally appear at the Building Division with valid government-issued photo identification and sign the Owner-Builder Statement in the office.

When is a Notice of Commencement required?

The county permit matrix lists a recorded NOC for general jobs valued above $5,000 and for an air-conditioning change-out valued at $15,000 or more. It must be provided before the first inspection.

What time are Seminole County inspections performed?

The Building Division lists normal inspection hours between 7:30 AM and 4:00 PM. The exact route and arrival time depend on the inspector’s daily schedule.

Why are my uploaded ePlan files not being reviewed?

Uploading documents does not always complete the workflow. Check whether the Building Division Upload and Submit task is still assigned to you. Complete that task so the package is released to county intake and reviewers.

Is a Final Engineering inspection required before the building final?

Yes, for applicable building projects. Submit the Final Engineering Inspection form after site work is complete and before requesting the building final. Engineering checks right-of-way restoration, drainage, erosion, sod, sidewalks and related site conditions.

Does Florida’s new under-$7,500 rule mean no permit is required?

Not automatically. House Bill 803 created limited exemptions for certain qualifying projects under $7,500, but all statutory conditions must be satisfied. Review Seminole County’s official state-law update before beginning work.

Source and freshness note

Official Information Used for This Guide

Building-Department.org is an independent informational website and is not Seminole County Government. Applications, payments, reviews, inspections, exemptions, certificates and enforcement decisions must be completed through Seminole County or the correct municipal agency.

This page was checked against the Seminole County Building Division, Building Permits Online, ePlan, Forms and Applications, Building Division contacts, current adopted codes, permit-type matrix, owner-builder affidavit, generator submittal guide, inspection instructions, Final Engineering form, flood resources, impact-fee guidance and the county’s July 2026 state-law update.

Last reviewed: July 23, 2026.

Permit forms, statutory exemptions, fees, online systems and departmental procedures can change. Confirm time-sensitive requirements before paying, ordering professional plans or beginning construction.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.