City Of Miami Building Department

City of Miami permit action guide

Move From iBuild Application to ProjectDox Approval, Inspection and Final Certificate

City of Miami permitting uses two connected systems: start the application and manage the permit in iBuild, then upload and revise drawings in ProjectDox after the process number and upfront payment are complete.

This guide shows the correct jurisdiction check, portal sequence, file rules, 2026 residential fast-track options, inspection scheduling, permit status reports and final CO/CC closeout without generic estimates or unnecessary filler.

iBuild application and permit management
ProjectDox plans, comments and revisions
Inspector tracking, permit card and closeout
City of Miami permit moving through iBuild, ProjectDox and final inspection An animated Miami property map, permit file, digital plan-review screen and final inspection check explain the City of Miami permitting process. PROPERTY + ZONING CHECK CITY OF MIAMI? PROJECTDOX APPROVED iBUILD FINAL INSPECTIONPASSED MIAMI RIVERSIDE CENTER
2026 Same Day–No Delay serviceEligible residential projects may use Walk-Thru Express Monday through Friday, 7:30 AM–12:30 PM at Miami Riverside Center. Upload plans to ProjectDox before arriving and confirm eligibility first.
!
New under-$7,500 residential exemption requestCertain qualifying work may be exempt only after City approval. Flood-hazard properties and electrical, plumbing, structural, mechanical or gas work are excluded. Do not start based only on project value.
Start here

Choose the Exact City of Miami Task

First decision

City of Miami, Miami-Dade County or Another Municipality?

Use the City of Miami process when

  • The property is inside City of Miami municipal boundaries.
  • City property and zoning tools return the address.
  • iBuild recognizes the project address.
  • The permit concerns City of Miami building, zoning or public-works authority.
?

Verify before applying when

  • The mailing address says Miami but the parcel is in unincorporated Miami-Dade.
  • The site is in Miami Beach, Coral Gables, Doral, Hialeah or another municipality.
  • The address lies near a municipal boundary.
  • The project includes county DERM, county roadway or another outside review.
Do not use the mailing city alone. Open the City of Miami Maps & Data tools, search the address and confirm city services, zoning and property information before paying.
Official contact panel

City of Miami Building Department Contact Information

Building Department305-416-1100Permit, plan review and building assistance
Inspection assistance305-416-1100, Option 2Inspection questions and scheduling help
General building emailbuilding@miamigov.comInclude address and process/permit number
ePlan supporteplansupport@miamigov.comProjectDox and electronic-plan help
Project access issueeplanbuilding@miamigov.comInclude full name, address and process number
City service line311Alternate: 305-468-5900
Office locationMiami Riverside Center, 4th Floor444 SW 2nd Avenue, Miami, FL 33130
Make the request easy to route: Provide the full address, process or permit number, current iBuild/ProjectDox status, discipline involved and the exact action you need.
Permit decision table

Which City of Miami Permit Path Fits the Project?

Project
Start with
Prepare
Extra review to check
New building, addition or structural alteration
Full iBuild application
Complete plans, survey/site information, valuation, design professionals and contractors
Zoning, floodplain, Public Works, Fire, DERM, trees and historic review
Roof, windows or exterior doors
Building permit
Scope, product approvals, wind information, valuation and contractor
Walk-Thru Express eligibility; historic property restrictions
Kitchen or bathroom remodel
Residential alteration
Existing/proposed plans and electrical, plumbing or mechanical scope
Walk-Thru Express or Homeowner Express; structural changes
AC change-out, minor electrical or plumbing
Easy Permit check
Qualified contractor, license, scope and equipment information
Cannot be tied to an active master permit
Fence or driveway
Building / Public Works path
Survey, dimensions, location, materials and site access
Zoning, right-of-way, utilities, archaeology and structural review
Pool or excavation
Full permit and site review
Survey, structural plans, barrier, electrical and drainage information
Flood, archaeological Certificate to Dig and historic review
Commercial tenant improvement
Commercial permit
Use, occupant load, accessibility, life safety, MEP and valuation
Fire, DERM, Certificate of Use, zoning and CO/CC
Sign
Sign permit path
Dimensions, location, height, illumination and mounting
Miami sign code, zoning and historic property rules
Tree removal or construction near trees
Tree permit review
Tree survey, species, size, location and protection plan
New-construction tree bond and right-of-way tree rules
Expired or unfinished permit
Extension or completion request
Permit number, history, remaining work and inspection status
Active permits use extension; expired permits use completion process
Application workflow

Start the Permit in iBuild Before Uploading Plans

Confirm property
Start in iBuild
Pay upfront fee
Receive process number
Upload in ProjectDox
Resolve reviews
Pull permit

Create the iBuild account

Use a working email address. The account will be used for application management, status searches, contractor changes, fees and inspection services.

Confirm the address and property constraints

Check city jurisdiction, Miami 21 zoning, flood zone, historic designation and archaeological layers before finalizing the scope.

Miami-specific risk: Soil disturbance in an archaeological conservation area may require a Certificate to Dig before building-permit approval.

Choose the correct permit or additional-plan route

Use the Permit Catalog and enter the complete building and trade scope. Work associated with an active master application should not be separated into an Easy Permit.

Enter owner, contractor, valuation and project details

Make the application description, plans, construction value, contractor information and proposed use consistent.

Good scope: “Interior kitchen renovation with new cabinets, relocated sink, electrical circuits and replacement exhaust hood.”

Pay the applicable upfront fee

Plans cannot enter ProjectDox review until the permit application exists and applicable upfront fees are paid.

Save the process number and upload-task email

The process number links iBuild and ProjectDox. Keep the email from eplans@miamigov.com containing the Applicant Upload Task.

Do not treat approval as permit issuance

After plan approval, complete contractor and fee requirements, then pull and print the permit card. The permit is not issued until required fees are paid and the permit card is printed.

Electronic plan review

ProjectDox File Rules That Prevent Prescreen Rejection

Drawing-file rules

  • Each drawing sheet is a separate file
  • Use the City standard naming convention
  • Keep the same file name for revised sheets
  • Upload plans to the Drawings folder
  • Upload supporting material to Documents
  • Check every file before submission

Blank upper-right stamp area

  • 8.5 × 11 sheet: 2 × 2 inches
  • 11 × 17 sheet: 3 × 3 inches
  • 24 × 36 sheet: 4.5 × 4.5 inches
  • 30 × 42 sheet: 4.5 × 4.5 inches
  • 36 × 48 sheet: 4.5 × 4.5 inches

Accept the Applicant Upload Task

Open the task, search by project number or name and accept the assigned upload task before adding files.

Upload all drawings and documents

Add drawing sheets individually and place other documents in the correct folder. The system allows multiple files per upload.

Complete the task after uploading

Reopen the Applicant Upload e-form, confirm that all required files are uploaded and named correctly, then complete the task.

Critical: Uploading files without completing the task does not start City review.

Respond to changemarks using versions

When corrections are required, replace each requested sheet using the exact original file name. ProjectDox recognizes it as a new version.

Published benchmark: The City says the first building-permit review cycle usually takes about 14 business days. This is not a guaranteed completion date; prescreen rejection, corrections and outside reviews add time.
2026 faster routes

Use the Correct Fast-Track Option

Walk-Thru Express

Monday–Friday, 7:30 AM–12:30 PM at Miami Riverside Center for eligible residential projects.

Examples include fences, driveways, windows and doors, roofing, kitchen/bath remodels, minor repairs and MEP work.

Homeowner Express Review

Uses prescreening followed by same-day discipline review when the homeowner’s eligible submission is complete and code-compliant.

Check homeowner eligibility

Easy Permit

For qualified contractors in good standing performing small work that does not require plan review.

Typical examples include AC change-outs, small electrical repairs, minor plumbing, portable toilets and bathroom-sink change-outs.

Walk-Thru exclusions can include: historic properties, open code violations, after-the-fact/legalization work and projects requiring structural review. Upload the documents first and confirm eligibility before traveling.
2026 permit exemption

Under $7,500 Does Not Automatically Mean No Permit

Potentially eligible

  • Qualifying residential work valued below $7,500
  • Written request with scope and value documentation
  • Work that is not divided into smaller projects
  • City approval before relying on the exemption

Not covered by the exemption

  • Property partly or entirely in a flood hazard area
  • Electrical work
  • Plumbing work
  • Structural work
  • Mechanical work
  • Gas work
Other approvals still apply. An approved building-permit exemption does not remove zoning, floodplain, planning, Public Works or historic-preservation requirements.

Open the City Exemption Process

Property and old plans

Find Permit History, Inspection Records and Microfilm

Search the current permit history first

Use iBuild Global Inquiry with the permit/process number or address. Check all related master and sub-permits.

Review inspection history

Open the relevant permit and review inspection results, required inspections and final status.

Request digital microfilm records

The City provides older building records digitally. Use the official records request for plans or permits not visible in the current online record.

Verify final status before a sale

A permit number alone is not proof of closure. Check final inspections, contractor changes, revisions and required CO/CC certificates.

Inspection workflow

Schedule, Track and Pass City of Miami Inspections

Use the correct permit or sub-permit number

A plumbing inspection needs the plumbing sub-permit number; roofing needs the roofing permit number. A master permit may cover all inspections when structured that way.

Request online or call 311

In iBuild, select Inspections and then Schedule an Inspection. The City allows requests up to five days in advance and says inspections usually occur the next day.

Confirm the inspection date

Save the confirmation. Verify the address, inspection type, access notes and contact information.

Track the inspector on inspection day

After the inspection is approved and scheduled, use the route tool to see the inspector’s route, appointments ahead and approximate arrival.

Keep work and approved plans ready

Do not cover work that requires inspection. Provide safe access, the permit card and City-stamped plans.

Correct and reschedule when failed

The inspector provides correction information. Complete every item, then repeat the scheduling process.

Do not schedule the wrong discipline. Building, roofing, electrical, plumbing, mechanical and other inspections may use separate permit numbers and required sequences.
Fee planning

How City of Miami Building Permit Fees Are Built

Building permit line

The published schedule includes a building-permit charge based on 2.5% of construction cost, with a stated $57 minimum and $10,500 maximum for that line.

Upfront / dry-run fees

Upfront fees are collected when the process number is issued. The official schedule says 80% of that amount is credited toward the building-permit fee when issued.

Other charges

Trade permits, plan review, reworks after the second review, revisions, expedited review, certificates, enforcement and other project-specific charges can apply.

Use the invoice, not a generic calculator. Construction value is only one part of the final cost. The official iBuild/City invoice controls.

Open the Official Fee Schedule

Contractors and owner-builders

Keep the Correct Professional Attached to the Permit

Contractor registration

The company and qualifier must be registered with the City of Miami before they can be added to the permit.

Open contractor registration

Add or change contractor

Use iBuild’s Add/Change Contractor option, enter the process number, select the company, download the form, sign and notarize it, then upload it to ProjectDox.

Owner-builder

Owner-builder status can create direct responsibility for supervision, compliance, workers and inspections. Read the City instructions before applying under the exemption.

Read owner-builder requirements

Easy Permit email rule: The Easy Permit card is sent to the official email address on the qualified contractor’s City record. Contractor-information updates may require an in-person visit to the 4th-floor permit counter.
Miami-specific property checks

Check Flood, Historic, Archaeological and Tree Requirements Early

Flood

New construction and substantial improvements in a flood zone may require elevation and floodplain documents.

Historic property

Exterior work, demolition and alterations may require Historic Preservation approval before or alongside the building permit.

Archaeological area

Excavation for foundations, pools, pipelines or fences may require a Certificate to Dig before permit approval.

Trees

Tree removal, relocation and protection can require separate permits, surveys or bonds during construction.

Map before design: Use the City GIS layers for zoning, flood, historic and archaeological screening. A map is a starting point; the responsible department makes the final determination.
Permit expiration and recovery

Active Permit Extension vs. Expired Permit Completion

Active permit

The City allows one extension request before expiration. The published process says the extension is for 180 days from the request date to complete work and final inspections.

Request an extension

Expired permit

Use the Permit Completion process rather than an extension. Gather the permit number, outstanding inspection list, approved plans and current contractor information.

2026 single-family update: Newly issued single-family dwelling permits now generally expire one year after issuance or on the effective date of the next Florida Building Code edition, whichever is later, subject to the City’s current implementation and Building Official authority.
Final certificate

Finish With the Correct CO or CC

Certificate
Used for
Before requesting
Certificate of Occupancy (CO)
New construction or a change of use
Permit final, all final inspections approved, revisions and contractor requests complete
Certificate of Completion (CC)
Remodels, renovations and shell buildings
Permit final, all required inspections and closeout items completed
Temporary CO / CC
Limited temporary occupancy or completion when City requirements are met
Outstanding work must fit the City’s temporary-certificate conditions
Online timing: When the request is verified and correct, the City says the CO/CC may be available to print in iBuild within 3–5 days. In-person requests can be issued immediately when everything is verified.

Open CO / CC Instructions

Useful scripts

What to Say When You Contact the City

Jurisdiction question
“I am planning work at [full address and folio]. Can you confirm that the property is inside the City of Miami and identify the building, zoning, flood, historic or Public Works approvals required?”
ProjectDox problem
“My process number is [number] for [address]. The ProjectDox status shows [status/task]. Can you confirm whether the issue is file naming, an incomplete upload task, missing discipline documents or project access?”
Inspection request
“I need the [inspection type] for permit/sub-permit [number] at [address]. The required prior inspection passed, the work remains visible and the site contact is [name and phone].”
Why not final?
“Permit [number] at [address] is not final. Can you identify the outstanding inspection, revision, contractor request, fee or related sub-permit preventing closure?”
Final checklist

Do Not Consider the Miami Project Complete Until These Are Confirmed

  • City jurisdiction confirmed
  • Zoning and property layers checked
  • Flood, historic and archaeology reviewed
  • Correct permit route selected
  • iBuild application submitted
  • Upfront fee paid
  • ProjectDox task completed
  • All discipline comments resolved
  • Contractor correctly attached
  • Permit pulled and card printed
  • Approved plans kept on site
  • Inspections requested in sequence
  • All sub-permits finaled
  • Why Not Final cleared
  • CO or CC printed when required
  • Final records saved
Office location

City of Miami Building Department Map

Address: Miami Riverside Center, 444 SW 2nd Avenue, 4th Floor, Miami, FL 33130. Schedule City services or confirm walk-through eligibility before traveling.
Official resources

Open the Correct City of Miami Permit Resource

Frequently asked questions

City of Miami Building Permit FAQs

What is the difference between iBuild and ProjectDox?

iBuild is used to start and manage the permit application, search status, manage contractors, pay fees and request inspections. ProjectDox is used to upload drawings and documents, receive review tasks, view changemarks and submit revised plan versions.

Where do I apply for a City of Miami building permit?

Start the building-permit application in the official iBuild portal. After the process number is created and required upfront fees are paid, use the ProjectDox Applicant Upload Task to submit plans and supporting documents.

How do I check a City of Miami permit status?

Use iBuild Global Inquiry or Search Process Number for the overall permit record. Check General, Plan History, Review Status and Event tabs. Use ProjectDox for discipline-level review status, changemarks and routing reports.

How do I schedule a City of Miami inspection?

Use iBuild, select Inspections and then Schedule an Inspection. Enter the correct permit or sub-permit number. The City allows requests up to five days in advance and says inspections usually occur the next day.

Can I track the Miami building inspector?

Yes. After the inspection has been approved and scheduled, the City’s route tool can show the inspector’s route, the number of appointments ahead and an approximate arrival time.

What is an Easy Permit?

Easy Permit Request allows qualified contractors in good standing to obtain permits for small work that does not require plan review. The work cannot be associated with an active master building-permit application.

Which projects may qualify for Same Day–No Delay review?

Eligible residential examples include fences, driveways, windows and doors, roofing, kitchen or bathroom remodels, minor repairs and certain MEP work. Historic properties, open code violations, after-the-fact work and projects requiring structural review may not qualify.

Does work under $7,500 automatically avoid a permit?

No. The 2026 exemption requires a written request and City approval. It does not apply to flood-hazard properties or electrical, plumbing, structural, mechanical or gas work, and it does not remove other departmental approvals.

What is the difference between a CO and a CC?

A Certificate of Occupancy is generally used for new construction or a change of use. A Certificate of Completion is generally used for remodels, renovations and shell buildings. The iBuild permit record indicates which certificate is required.

What should I do when a City of Miami permit expires?

An active permit may qualify for one 180-day extension requested before expiration. An expired permit uses the Permit Completion process. Check the permit history and outstanding inspections before choosing the request.

Independent guide and freshness

Source and Accuracy Note

Building-Department.org is an independent informational guide and is not the City of Miami. Applications, exemptions, plan reviews, payments, inspections, certificates, zoning decisions and enforcement must be completed through the City or the correct outside agency.

This guide was rebuilt from current City of Miami Building Department, iBuild, ProjectDox, inspection, fee, records, GIS, CO/CC, fast-track and 2026 legislative-update resources.

Last reviewed: July 23, 2026.

Portal behavior, forms, fees, staff, code rules and eligibility can change. Confirm time-sensitive details before paying, submitting plans, attending walk-through review or starting work.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.