Check Jurisdiction, Submit Digital Plans and Close a Santa Clara County Permit
Santa Clara County issues building permits only for properties in its unincorporated service area. A Santa Clara, San José, Sunnyvale, Cupertino, Gilroy or other city mailing address does not prove that the County is the permit authority.
Start with Property Explorer. Once County jurisdiction is confirmed, use the InSite Public Permit Portal for applications, payments, status checks, document uploads and inspection requests.
What Do You Need From Santa Clara County?
Santa Clara County Permit Next-Step Finder
Select the situation that best matches the work.
Santa Clara County Permit Center Contact and Office Hours
County Permit or City Permit?
Use Santa Clara County when
- Property Explorer identifies an unincorporated parcel.
- The permit jurisdiction is shown as County of Santa Clara.
- The project is on qualifying unincorporated Stanford land.
- The parcel is in an unincorporated area near San Martin, Gilroy, Morgan Hill or another city.
- County Planning and Development confirms jurisdiction.
- The County portal recognizes the property record.
Use a city building department when
- The parcel is inside incorporated city limits.
- Property Explorer identifies a city jurisdiction.
- The property is inside the City of Santa Clara.
- The address is inside San José, Sunnyvale or another city.
- A city planning department controls zoning for the parcel.
- The County property profile shows only limited city information.
Open the jurisdiction and zoning checker
Search using the exact address or Assessor’s Parcel Number.
Read the jurisdiction result
Do not rely on the postal city printed on a tax bill, real-estate listing or mailing label.
Review zoning and constraints
Check the zoning district, General Plan designation, permit activity and mapped development constraints.
Call when a boundary is unclear
Provide the address and APN and ask staff to confirm the building, planning, fire, grading and septic authorities.
Which Santa Clara County Permit Fits the Project?
Project |
Likely County route |
Important additional review |
|---|---|---|
New house, ADU, addition or major structural work |
Building permit and plan review |
Planning, site plan, grading, fire, septic/sewer, energy, structural and hazard review |
Interior remodel |
Building permit when walls, use or systems change |
Structural, electrical, plumbing, mechanical, energy and occupancy conditions |
Residential reroof up to 5,000 square feet |
Online minor permit |
Roof material, deck repair, wildfire requirements and structural loading |
Air conditioner, furnace or water heater replacement |
Residential minor permit |
Electrical, gas, venting, equipment location and energy requirements |
Electrical service, subpanel or qualifying EV charger |
Residential electrical minor permit |
Utility coordination, load calculation and equipment specifications |
Residential photovoltaic system |
Solar or SolarAPP+ permit |
SolarAPP+ approval, structural attachment, electrical diagram and battery scope |
Swimming pool or spa |
Pool plan review and permit |
Barrier, electrical bonding, drainage, setbacks and septic-system separation |
Retaining wall |
Confirm height and surcharge |
Engineering, drainage, grading and geologic conditions can trigger review |
Fence |
Building permit may be exempt below code threshold |
Zoning height, visibility, easements and rural-district standards still apply |
Detached shed or accessory building |
Small structures may be permit-exempt |
Setbacks, lot coverage, grading, utilities, fire access and zoning remain applicable |
Demolition |
Demolition permit |
Utilities, hazardous materials, waste, stormwater and large-site SWPPP requirements |
Commercial tenant improvement or change of occupancy |
Nonresidential building permit |
Planning, accessibility, Fire Marshal, hazardous materials and trade plans |
Work That May Not Require a Building Permit
Common finish work
- Painting and papering
- Carpet and similar flooring
- Cabinet and countertop replacement
- Nonstructural finish work
Possible small-project exemptions
- Qualifying fences below the code height limit
- Small detached accessory buildings
- Low retaining walls without surcharge
- Qualifying low, detached decks
Still check these rules
- Zoning and setbacks
- Easements and rights-of-way
- Fire and wildfire standards
- Septic-system clearances
- Floodplain and grading rules
- HOA or private restrictions
Apply Through the Public Permit Portal
Confirm unincorporated jurisdiction
Use the address or APN in Property Explorer before preparing a County application.
Identify the complete permit package
Determine whether the project needs planning, building, grading, Fire Marshal or minor-permit applications.
Create a Public Permit Portal account
A public user account is required to complete applications, upload documents and make payments.
Complete the Development Services Intake Form
Describe the complete project and identify the owner, applicant, address, APN, valuation and requested permits.
Upload the coordinated digital package
Submit the intake form, plan set and supporting documents using the County’s file specifications and naming conventions.
Pay fees due at application
Plan-check and planning fees are generally collected at application. Other permit fees may be paid before issuance.
Monitor all reviewing departments
Check the portal regularly for planning, building, fire, grading, environmental or other review comments.
Confirm formal permit issuance
Approved plans or a paid application do not authorize work. Download the issued permit and approved documents before starting.
Prepare Files That the County Can Review
Digital requirement |
County standard |
Practical action |
|---|---|---|
File type |
PDF |
Do not upload photographs of printed drawing sheets as the plan set. |
Maximum file size |
100 MB |
Optimize images without making notes, dimensions or details unreadable. |
Color depth |
8-bit grayscale |
Use color only where essential and accepted for a specific supporting document. |
Naming |
County naming convention |
Name each file by document type instead of using “scan1” or “final plans.” |
Plan-sheet size |
18 × 24 to 24 × 36 inches |
Use one consistent sheet size throughout the drawing set. |
Building-plan scale |
Commonly ¼ inch = 1 foot |
Show a written and graphic scale on each applicable sheet. |
Security |
Unlocked file |
Remove passwords and restrictions that prevent comments or stamps. |
Revisions |
Complete coordinated replacement |
Cloud revisions and submit a response identifying every corrected sheet. |
Useful file names
- Development-Services-Intake.pdf
- Architectural-Plans.pdf
- Structural-Plans.pdf
- Structural-Calculations.pdf
- Energy-Documents.pdf
- Geotechnical-Report.pdf
- Response-to-Comments.pdf
Avoid these rejection risks
- Rotated or upside-down sheets
- Illegible scans
- Conflicting project descriptions
- Missing owner authorization
- Unlabeled calculation files
- Partial revision sets
- Password-protected PDFs
Santa Clara County Permit Document Checklist
Property and applicant
- Exact property address
- Assessor’s Parcel Number
- Owner’s legal name
- Applicant contact information
- Owner authorization when applicable
- Contractor or owner-builder information
Plans and scope
- Development Services Intake Form
- Detailed scope of work
- Construction valuation
- Site or plot plan
- Architectural drawings
- Structural drawings and calculations
Technical documents
- Energy compliance forms
- CALGreen documents
- Equipment specifications
- Electrical load information
- Plumbing and gas scope
- Mechanical calculations
Site and rural-property items
- Topographic information
- Grading and drainage plans
- Geotechnical or geologic report
- On-site wastewater approval
- Water-supply information
- Road and access approval
Hazard and fire items
- Fire Marshal review documents
- Wildland-urban-interface details
- Flood Elevation Certificate
- Defensible-space or access information
- Sprinkler and alarm plans
- Emergency-vehicle access details
Inspection and closeout items
- Special-inspection schedule
- Setback certification
- Deferred submittals
- Product approvals
- Testing and observation reports
- Final agency clearances
Clear Grading, Septic, Fire, Flood and Rural-Site Reviews
Planning and zoning
Confirm allowed use, setbacks, height, lot coverage, accessory structures, agricultural rules and any planning entitlement before final building design.
Grading and drainage
A separate grading permit is generally required when construction involves more than 150 cubic yards of cut or fill beyond five feet from the building foundation.
On-site wastewater
Rural parcels using septic systems may need capacity, location, replacement-area and setback approval before a building addition or new dwelling can proceed.
Fire Marshal review
New buildings, fire access, water supply, alarms, sprinklers, hazardous materials and state-licensed facilities can require separate Fire Marshal review.
Wildfire and home hardening
Mapped fire-hazard areas can affect roofing, siding, vents, decks, vegetation, access and other ignition-resistant construction details.
Floodplain and drainage
Flood-zone construction may require elevation information, flood-resistant materials, elevated equipment and Land Development Engineering review.
Geologic and hillside conditions
Fault, landslide, expansive-soil, erosion and steep-slope conditions may require professional reports and engineered foundations.
Road and right-of-way
New driveways, access improvements, drainage connections and work near public roads may require Roads and Airports Department approval.
Stanford and San Martin
Unincorporated Stanford land and the San Martin Planning Area can involve area-specific plans, land-use policies and advisory review.
What to Prepare for Common County Projects
Project |
Useful documents |
Question to answer first |
|---|---|---|
New house or ADU |
Site plan, zoning approval, complete architecture, structure, energy, CALGreen, fire, septic/sewer and grading documents |
Can the site legally and physically support the proposed dwelling? |
Residential addition |
Existing/proposed floor plan, structural calculations, energy forms, setback information and utility scope |
Does the addition affect setbacks, septic capacity, grading or fire access? |
Interior remodel |
Existing/proposed plans, structural details and separate electrical, plumbing, gas and mechanical information |
Are structural walls, bedrooms, occupancy, exits or systems changing? |
Reroof |
Roof area, material, weight, deck-repair scope and wildfire-compliance information |
Is the roof under 5,000 square feet and eligible for the minor-permit route? |
Pool |
Site plan, equipment, barrier, electrical bonding, drainage and septic-clearance information |
Can the pool meet setbacks and remain clear of septic components and easements? |
Solar and battery |
SolarAPP+ approval where eligible, one-line diagram, roof layout, structural details and equipment specifications |
Is the system eligible for SolarAPP+ or does it require standard review? |
Santa Clara County Building Permit Fees
Project valuation |
Current building-permit fee formula |
|---|---|
$1–$5,000 |
$821.89 flat |
$5,001–$25,000 |
$821.89 for the first $5,000 + $30.82 per additional $1,000 or fraction |
$25,001–$50,000 |
$1,438.31 for the first $25,000 + $57.53 per additional $1,000 or fraction |
$50,001–$100,000 |
$2,876.62 for the first $50,000 + $16.44 per additional $1,000 or fraction |
$100,001–$500,000 |
$3,698.51 for the first $100,000 + $11.30 per additional $1,000 or fraction |
$500,001–$1,000,000 |
$8,218.91 for the first $500,000 + $32.88 per additional $1,000 or fraction |
$1,000,001–$5,000,000 |
$24,656.72 for the first $1,000,000 + $143.83 per additional $10,000 or fraction |
Residential $25,000 example
Building permit: $1,438.31
Residential plan check at 70%: approximately $1,006.82
3% technology fee: approximately $43.15
0.73% training fee: approximately $10.50
0.205% comprehensive planning fee: $51.25
Illustrative subtotal: approximately $2,550.03 before trade, fire, grading, environmental, road or pass-through fees.
Plan-check percentages
- Single- and two-family residential: 70% of building-permit fee
- Nonresidential and multifamily: 84% of building-permit fee
- Reviews beyond three completed rounds may be billed at the plan-review hourly rate.
- Current plan-review hourly rate: $420
Common residential or service fee |
Current listed amount |
|---|---|
Residential reroof up to 5,000 square feet |
$513 |
Air-conditioner replacement |
$390 |
New air conditioner |
$431 |
Furnace replacement |
$390 |
Furnace and duct replacement |
$431 |
Water-heater replacement |
$390 |
Electrical service change or subpanel |
$308 |
EV charger under 60 amps, non-bidirectional |
$349 |
Residential roof-mounted photovoltaic system |
$950 |
Residential SolarAPP+ submittal |
$530 |
Residential energy-storage system, up to four batteries |
$1,036 |
Reinspection |
$431 |
Inspection outside normal business hours |
$1,844 |
Temporary Certificate of Occupancy |
$3,335 |
Investigation of construction performed without a permit |
$842 minimum |
The County fee page lists $1.49 for charges up to $67 and 2.22% for charges over $67. Review the portal’s payment screen before submitting.
Roads and Airports, Environmental Health, Fire Marshal, Land Development Engineering and outside-agency pass-through fees may be separate.
Understand the Owner-Builder Responsibilities
Before choosing owner-builder
- Confirm that you legally qualify.
- Read the current Owner-Builder Notice.
- Understand workers’ compensation obligations.
- Use licensed contractors for regulated work.
- Verify the project is for the owner’s lawful use.
- Do not use the exemption to hide an unlicensed contractor.
The owner becomes responsible for
- Application accuracy
- Plan and code compliance
- Job-site safety
- Contractor and worker compliance
- Inspection scheduling
- Corrections and final closeout
Request Before 3:00 PM for Next-Workday Service
Next-day cutoff
Submit before 3:00 PM on a regular County workday for an available next-workday inspection.
Advance scheduling
Inspection requests may be entered up to five days in advance.
Weekend and holiday requests
They are entered on the next regular workday and scheduled for the following workday or later.
Open the correct permit record
Confirm that the permit is issued, active and eligible for the requested inspection.
Select the exact inspection code
Do not request a final inspection when rough, utility, grading, fire or special-inspection requirements remain open.
Enter the request before 3:00 PM
Use the Public Permit Portal, the available mobile inspection application or call 408-299-5700.
Provide access information
Enter the gate code, unit, contact name, phone number, animal warning and safe-access instructions.
Keep approved documents at the site
The inspector must be able to review the approved plans, permit information and required technical documents.
Request FI01 Project Complete
To close the project, request the FI01 final inspection for every related permit that requires final closure.
Inspection stage |
What should be ready |
Common delay |
|---|---|---|
Setback, footing or foundation |
Location, excavation, forms, reinforcement and approved site information |
Concrete placed or work backfilled before inspection |
Underground trades |
Electrical, plumbing, gas or mechanical work exposed and test-ready |
Work covered with soil, slab or finish material |
Frame and rough trades |
Framing, shear, wiring, plumbing, gas and HVAC coordinated |
Incomplete rough work or unapproved field changes |
Exterior or wildfire details |
Flashing, weather barrier, vents, roofing and required ignition-resistant details visible |
Critical layers covered before verification |
Insulation and energy |
Rough approvals complete and insulation installed to the approved energy documents |
Drywall installed too early |
FI01 Project Complete |
All permitted work complete and related building, trade, fire, grading and agency conditions resolved |
A related permit or outside-agency clearance remains open |
Avoid a Failed or Missed Inspection
- Permit is issued and active
- Correct inspection code requested
- Permit information is visible
- Approved plan set is available
- Required work is complete
- Work remains exposed
- Required tests are ready
- Previous corrections are complete
- Special-inspection reports are available
- Inspector has safe access
- Gate and unit are unlocked
- Site contact can answer the phone
Protect the Permit Before It Expires
Initial permit period
County inspection guidance states that building permits are valid for 12 months from issuance.
Extension period
Each approved building-permit extension request provides an additional 180 days.
Request before expiration
Submit the current extension form while the permit remains active and explain why the project needs more time.
What the Permit Status Means
Find Existing Permits, Plans and Inspection History
Confirm the property jurisdiction
County records will be limited when the property is inside a city.
Search the Public Permit Portal
Use the exact property address, APN or permit number and open each related record.
Review all related permits
Building, electrical, plumbing, mechanical, grading and fire records may close separately.
Download available documents
Check the record for approved plans, revisions, correspondence, permits and inspection results.
Request missing public records
Submit a focused public-record request identifying the address, APN, permit number, date range and documents needed.
Verify final closeout
Confirm FI01 Project Complete and final status for every related record instead of relying on a payment receipt or plan approval.
Use the 2025 California Building Standards Code
Current state code cycle
The 2025 California Building Standards Code, Title 24, became effective January 1, 2026 and applies through the current 2026 permit period.
County amendments
Projects must also comply with applicable Santa Clara County amendments, zoning, fire, land-development, energy and environmental requirements.
Fix Common Santa Clara County Permit Problems
Problem |
Likely reason |
Best next action |
|---|---|---|
County portal cannot find the property |
The property may be inside a city or the address format is different |
Search Property Explorer by APN and verify jurisdiction. |
Application remains incomplete |
Intake form, authorization, plan set or supporting document is missing |
Compare the upload list with the digital-submittal requirements. |
PDF is rejected |
File is oversized, locked, incorrectly named or unreadable |
Export an unlocked, properly named PDF under 100 MB. |
Review is waiting on another department |
Planning, Fire, grading, septic, roads or hazard review remains open |
Identify the active reviewer and resolve that department’s comments. |
Plans return repeatedly |
Comments are answered separately or revisions conflict |
Submit one response letter and one coordinated revised plan set. |
Approved plans but no permit |
Final fees or issuance conditions remain |
Open the invoice and confirm formal permit issuance before work. |
Inspection cannot be requested |
Permit is not issued, a prerequisite is missing or the record is inactive |
Review permit status or call 408-299-5700. |
Inspection failed |
Work is incomplete, covered, inaccessible or inconsistent with plans |
Correct every item before paying for or requesting reinspection. |
Project appears finished but permit is open |
FI01 Project Complete or a related permit final is missing |
Request final inspections for every associated record. |
Permit is near expiration |
The 12-month permit period is ending |
Submit the extension request before expiration and confirm the current fee. |
What to Say When You Contact the Permit Center
“Please confirm whether the County or an incorporated city handles permits for [address and APN], and identify the zoning, fire, grading and septic authorities.”
“I am planning [exact work]. Which building, planning, grading, fire and trade applications are required, and which digital documents should I upload?”
“Application [number] has not moved. Can you identify the active reviewing department, outstanding comment and exact resubmittal needed?”
“Please confirm which FI01 Project Complete inspections and related permit finals remain open for [permit number/address].”
Do Not Consider the Project Finished Until These Are Complete
- County jurisdiction confirmed
- Zoning and development constraints checked
- Planning approval completed if required
- Grading and drainage resolved
- Septic or sewer approval completed
- Fire Marshal conditions resolved
- Flood and wildfire requirements resolved
- Correct portal application submitted
- Digital plans accepted
- Every review comment corrected
- Fees paid and permit issued
- Issued permit available at the site
- Approved plans available for inspection
- Special inspections completed
- Building rough inspections passed
- Electrical inspections passed
- Plumbing and gas inspections passed
- Mechanical inspections passed
- Outside-agency clearances completed
- FI01 Project Complete approved on all related permits
Santa Clara County Permit Center Map
Phone: 408-299-5700.
Email: e-permits@pln.sccgov.org.
Open the Correct County Tool or Page
Santa Clara County Building Department FAQs
Does Santa Clara County issue permits inside every city in the county?
No. The County Department of Planning and Development handles building permits for unincorporated Santa Clara County. Properties inside incorporated cities use the appropriate city building department.
How do I confirm whether my property is in the County’s service area?
Use the County’s jurisdiction and zoning checker or Property Explorer. Search by exact address or Assessor’s Parcel Number and read the permitting-jurisdiction result before applying.
Where do I apply for a Santa Clara County building permit?
Use the InSite Public Permit Portal at the official County Accela address. A public user account is required to complete applications, upload documents and make payments.
What are the Santa Clara County Permit Center hours?
Monday through Thursday hours are 8:00 AM to noon and 1:00 PM to 5:00 PM. Fridays are limited to Building services for active permits during the same morning and afternoon hours.
Which projects can use the minor-permit application?
The County offers online Minor Residential Mechanical, Electrical, Plumbing and Reroof applications. The specific scope must meet the minor-permit eligibility rules shown in the portal.
What is the next-day inspection cutoff?
Submit an available inspection request before 3:00 PM on a regular County workday for next-workday scheduling. Requests can be entered up to five days in advance.
How much is a Santa Clara County residential reroof permit?
The FY 2026–2027 Building Fee Schedule lists $513 for a residential reroof up to 5,000 square feet. Larger or more complex roofing work may be calculated by valuation or require additional review.
How much is the Santa Clara County reinspection fee?
The current FY 2026–2027 schedule lists a $431 reinspection fee. It may apply when work is incomplete, prior corrections remain unresolved or access is unavailable.
How long is a Santa Clara County building permit valid?
County inspection guidance states that a building permit is valid for 12 months from issuance. An approved extension provides an additional 180 days and should be requested before expiration.
How do I completely close a Santa Clara County permit?
Complete every required building, trade, fire, grading and agency inspection, then request the FI01 Project Complete inspection for each related permit that requires final closure.
Source and Accuracy Notes
Building-Department.org is an independent informational guide and is not the County of Santa Clara. Jurisdiction, permit issuance, zoning decisions, fee invoices, inspections and code interpretations must be confirmed through the responsible government agency.
This page was rebuilt using the County Department of Planning and Development’s Permit Center, Building Section, Public Permit Portal, Property Explorer, digital-submittal, inspection, fee, Fire Marshal, land-development and public-record resources.
Last reviewed: July 22, 2026.
Fees, forms, portal functions, office services, code amendments, hazard maps and inspection procedures can change. Recheck the official source before filing, paying or starting work.

Khushboo Bobade is a public records researcher and editorial writer specializing in government service documentation and construction permit systems.
Her research focuses on explaining building permits, inspection procedures, zoning regulations, and public permit records maintained by local government building departments across the United States.
Professional profile: View LinkedIn Profile
Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links
Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.
What building department task do you need help with?
Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.
Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.
Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.
Building Permit Type Finder
Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.
Permit Fee Estimate Calculator
Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.
Inspection Readiness Checklist
Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.
Zoning and Setback Pre-check
Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.
Plan Review Timeline Estimator
Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.
Permit Records Search Helper
Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.
Official Building Department Resource Finder
Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.
Building Department vs Planning/Zoning
- Building Department: permits, plan review, inspections, code compliance, certificates.
- Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.
Best sitewide placement
Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.
Important note
This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.