City Of Lake Forest Building Department Guide | How to Get Permits

Lake Forest permit action guide

Move From Property Survey to Design Review, Building Permit, Inspection and Final Closeout

Lake Forest permits involve more than building-code review. An addition, deck, fence, demolition, exterior alteration or new home may also require a stamped survey, grading review, tree permit, Building Review Board approval or Historic Preservation Commission approval.

This guide shows which route comes first, what the City expects in a complete application, how to use BS&A Online and how to avoid an expired permit or an open record that delays a future property sale.

Correct permit office at 800 N. Field Drive
Official 5- and 15-business-day review targets
Design, historic, tree, ravine and inspection checkpoints
Lake Forest plans moving through design review, tree protection and final inspection An animated architectural plan, review board screen, tree and ravine protection layer, permit card and final inspection check explain the Lake Forest permit process. SURVEY + DESIGN PLAN PROJECT REVIEW ZONING + SCALE DESIGN / HISTORIC CODE REVIEW APPROVED PERMIT FINAL INSPECTION CLOSED 800 N. FIELD DRIVE
⚠️
May 2026 payment scam warning Lake Forest says it never requests permit or development payments by wire transfer. Legitimate permit and development invoices are sent only from bsa@cityoflakeforest.com. Verify unexpected payment requests by calling 847-810-3521.
Choose one task

What Do You Need to Do?

Lake Forest Permit Route Finder

Select the closest project to see the most useful first step.

Correct office information

Lake Forest Community Development Contacts

Permit assistance 847-810-3521 Building permits and portal help
Office location Municipal Services Center 800 N. Field Drive, Lake Forest, IL 60045
Front counter 8:00 AM–4:30 PM Monday through Friday
Inspection assistance 847-810-3503 Help with online inspection scheduling
Residential code 847-810-3513 Residential plan and code questions
Commercial code 847-810-3514 Commercial plan and code questions
Design / historic review 847-810-3520 Building Review Board and Historic Preservation
Possible unpermitted work 847-810-3502 Construction or code-compliance concern
Important address correction: Building permits are issued through Community Development at 800 N. Field Drive. The 220 E. Deerpath address shown in many City footers is City Hall—not the building-permit counter.
Permit decision table

Match the Project to the Correct Lake Forest Permit Package

Project
Start with
Prepare first
Extra Lake Forest check
Interior remodel
Addition / alteration permit
Scope, plans, valuation and trade information
Architect stamp if structural changes are proposed
Addition, garage or structural alteration
Addition / alteration packet
Stamped survey, scaled drawings, grading waiver or permit and building-scale information
Building Review Board or Historic Preservation review
New single-family home or duplex
New dwelling packet
Engineer-stamped grading plan, architect-stamped plans, Manual J/S and utility approvals
Design board, building scale, tree removal and North Shore Water Reclamation approval
Deck
Deck permit
Stamped survey, dimensions, property-line distances, framing, piers and beam details
HOA approval and grading waiver
Fence, wall or pillars
Fence / wall permit
Legal survey showing structures, easements and proposed location
Wall section, foundation and electrical permit if lighting is added
Patio, driveway or hardscape
Hardscape / driveway packet
Survey, dimensions, material, drainage and grading information
Ravine, steep-slope, drainage, tree and curb-crossing review
Windows, doors, siding or tuckpointing
Exterior-material permit
Existing and proposed materials, sizes, grille patterns and product details
Design or historic compatibility review
Pool, spa or hot tub
Pool / spa permit
Plot plan, engineering, equipment, piping, barrier and trade plans
Zoning, grading, tree and electrical review
Generator, HVAC, solar or exterior lighting
Project-specific packet
Equipment specifications, site location, load calculations and trade license
Noise, setbacks, screening and design compatibility
Demolition
Demolition application
Existing structure information, survey, utilities and replacement-project details
Building Review Board or Historic Preservation Commission approval
City rule of thumb for single-family homes: Obtain guidance for anything beyond flooring, painting or planting. Call 847-810-3521 before purchasing materials when the scope is uncertain.
Digital application workflow

Apply Through BS&A Online in Seven Clear Steps

Choose the exact City checklist

Do not begin with a blank generic application. Open the packet for the specific project: addition, deck, fence, pool, driveway, solar, HVAC or new building.

Do next: Use the checklist as the table of contents for the digital upload.

Confirm design, historic and zoning review

Exterior changes, demolition, additions and new buildings may need a board or commission decision before permit issuance.

Save money: Schedule a predevelopment discussion before completing final architectural plans.

Prepare the survey and plans

Show proposed work, setbacks, structures, utilities and easements. Structural changes generally require Illinois-registered design-professional plans.

Plan scale: City checklists commonly request floor plans at 1/4-inch scale and sections at 1/2-inch scale.

Register or sign in to BS&A

Open the Lake Forest municipal portal, register an account and choose Apply for a Permit.

Upload one complete package

Include the signed owner application, plans, survey, contractor information, HOA approval and any board Action Summary or Certificate of Appropriateness.

Small paper plans: City staff can help scan 8.5-by-11-inch or 11-by-17-inch documents.

Pay the plan-review charge

Plan-review charges are collected at application. The remaining permit charges are paid before issuance.

Payment check: Credit-card transactions carry a 2.95% fee.

Respond to corrections and confirm issuance

Upload coordinated revisions, answer every comment and confirm the permit is issued before construction begins.

Job-site requirement: Post the permit placard where it is visible from the street and keep approved plans on site.
Application readiness

What a Complete Lake Forest Permit Package May Include

Owner and property

  • Project address
  • Owner of record
  • Property-owner signature
  • Owner’s Designee Form if used
  • HOA approval when required
  • Fair market construction value

Survey and design

  • Current stamped plat of survey
  • Setbacks and easements
  • Proposed work location
  • Detailed scaled plans
  • Architect or engineer stamp
  • Building-scale workbook if triggered

Contractors and approvals

  • Electrician’s license
  • HVAC contractor license
  • Illinois roofing license
  • Plumber’s license and letter
  • Board Action Summary or COA
  • Tree-removal application
Construction value means more than the contractor price. Lake Forest defines it as the fair market value of labor, materials, all trades and engineering or professional services. Land cost is excluded.
Local document details

Project-Specific Information Reviewers Look For

Project
Important drawing or document details
Common missing item
Addition or alteration
Materials, structural changes, survey, Manual J/S when new HVAC is included
Board decision, grading waiver or trade-license information missing
New home
Engineer-stamped grading plan at 1 inch = 20 feet, architect plans and building-scale worksheet
Water-reclamation approval, tree application or contractor credentials missing
Deck
Overall dimensions, property-line distances, material, pier/post spacing and beam sizing
Stamped survey or grading waiver missing
Fence or wall
Property lines, easements, height, material, foundation and pillar section
Electrical permit and fixture cut sheets omitted when lighting is proposed
Roof
Roofing squares, existing and proposed material, tear-off and hot-work information
Illinois roofing license not current
Windows or doors
Existing/proposed materials, quantity, size changes, cladding and grille pattern
Historic or design compatibility not resolved
Architectural review

Building Review Board or Historic Preservation Commission?

Building Review Board

Use this route for applicable properties outside the City’s historic districts.

  • Complete or partial demolition
  • New buildings
  • Additions and exterior alterations
  • Building-scale variances
  • Exterior lighting
  • Signs, landscaping and new-development site plans

Meeting pattern: First Wednesday at 6:30 PM, subject to the current calendar.
Contact: 847-810-3520

Open Building Review Board guidance

Historic Preservation Commission

Use this route for projects inside a local historic district or affecting an individual landmark.

  • Complete or partial demolition
  • New construction
  • Additions and exterior alterations
  • Building-scale variances
  • Architectural compatibility
  • Certificate of Appropriateness requirements

Meeting pattern: Fourth Wednesday at 6:30 PM, subject to the current calendar.
Contact: 847-810-3520

Open Historic Preservation guidance

Best first step: Call 847-810-3511 to arrange a predevelopment meeting when the project may need a City board or commission. Bring the survey, photographs and a concept drawing.
Site protection

Tree, Drainage, Grading, Ravine and Steep-Slope Checks

Tree removal

Complete the questionnaire on the City application to determine whether a permit is required.

Submit the application with a plat of survey showing each tree proposed for removal.

Published target: Generally five business days.

Grading and drainage

Additions, decks, patios, driveways, hardscape and new construction may need a grading waiver or full grading permit.

Show how the work affects runoff, neighboring property and existing drainage paths.

Ravines and steep slopes

Lake Forest Community Development coordinates with Engineering on grading, drainage and steep-slope conditions.

Contact staff before excavating, changing drainage or placing structures near a ravine or bluff.

Do not clear the site before review. Tree-preservation fencing, erosion controls and approved drainage measures may be required before construction starts and must remain until the City authorizes removal.
Current code framework

Building Codes Used by Lake Forest

Subject
Adopted code listed by the City
Contact
One- and two-family residential
2021 International Residential Code
Residential Plans: 847-810-3513
Commercial construction
2021 International Building Code
Commercial Plans: 847-810-3514
Mechanical and fuel gas
2021 IMC and 2021 IFGC
Community Development
Electrical
2020 National Electrical Code
Community Development
Plumbing
Illinois State Plumbing Code
Community Development
Fire and life safety
2021 NFPA 1 and NFPA 101; listed 2019 alarm and sprinkler standards
Fire Prevention / Community Development

Local amendments in Chapter 150 of the Lake Forest Code also apply.

Published review targets

How Long Does Permit Review Take?

Smaller projects

The City says smaller projects may be reviewed over the counter or in approximately five business days, depending on scope and required reviews.

Larger projects

The City publishes an approximate 15-business-day review target for larger projects.

These are review targets—not approval guarantees. Missing surveys, board decisions, grading information, architect seals, licenses or correction responses can restart or extend the process.
Fee and payment guidance

How to Get the Correct Lake Forest Permit Cost

Fee sequence

  1. Enter the complete fair-market construction value.
  2. Pay the plan-review charge at application.
  3. Complete building and trade reviews.
  4. Review the itemized BS&A invoice.
  5. Pay the remaining permit, connection, impact or bond amounts before issuance.

Payment methods

The City lists cash, check and credit-card payment.

Credit-card fee: 2.95%.

Never pay by wire transfer. Verify that a legitimate electronic invoice came from bsa@cityoflakeforest.com.

Avoid the old fee document. The public Document Center still labels a Community Development schedule as “2018.” Use the current BS&A invoice or request the latest City Council-approved schedule from Community Development before budgeting.
Cash bonds: Some projects require bonds to protect streets, sidewalks, parkways, grading or other public interests. A successful final inspection can trigger the bond-refund process when the approved work is complete and no public damage remains.
Online inspection workflow

Schedule and Prepare for Lake Forest Inspections

Sign in to BS&A
Select Schedule Inspection
Choose the permit
Select inspection and date
Verify contact information
Add access notes
Submit and save confirmation

Before scheduling

  • Permit is issued and active
  • Correct inspection type identified
  • Required work is complete
  • Work remains visible
  • Safe access is available
  • Contractor contact is current

Before the inspector arrives

  • Permit placard visible from street
  • Approved plans on site
  • Gate and work area unlocked
  • Prior inspections passed
  • Site and street kept clean
  • Tree and erosion fencing remains
City guidance: Inspections can usually be completed within one to two business days after a request, but use the dates actually available in BS&A. Call 847-810-3503 when the online scheduler is not working.
Never conceal work early. Schedule framing, electrical, plumbing, HVAC, insulation and other rough inspections before drywall, concrete, finishes or landscaping hide the work.
Permit validity and final approval

Prevent an Expired or Open Permit From Following the Property

Start within 90 days

Lake Forest says permitted projects must begin within 90 days after permit issuance.

12- or 18-month validity

The City says permits are valid for 12 or 18 months depending on project scope.

Limited extension

An extension may be available for an added fee when reasonable progress is being made. Request it before expiration.

Open-permit risk: The City warns that permits not completed and inspected before expiration may be recorded against the property and delay a future sale.

Final closeout checklist

  • All required inspections requested
  • Failed items corrected
  • Trade finals completed
  • Final building inspection passed
  • Certificate of Occupancy obtained when required
  • Permit record shows complete
  • Bond-refund conditions satisfied
  • Final documents saved by owner
Construction-neighbor rules

Lake Forest Construction Hours

Monday through Friday

7:00 AM–8:00 PM

Saturday and Sunday

8:00 AM–6:00 PM

Keep contractor vehicles off neighboring lawns and driveways, prevent street obstruction and maintain erosion and tree-protection fencing until the City authorizes removal.
Property-sale requirement

Home Sewer Inspection Before Transferring Water Billing

Who needs it?

The program applies to single-family residences and duplexes before water billing is transferred from seller to buyer.

  • Apply to Community Development
  • Inspection fee: $150
  • Complete up to 120 days before transfer
  • City schedules within approximately 10 working days
  • Inspection takes about one hour

What the City checks

The inspector looks for improper stormwater connections to the sanitary sewer.

  • Downspouts
  • Sump pumps
  • Yard drains
  • Other possible stormwater connections
  • Dye testing when needed

Reinspection after violations: $50.

Open the Home Sewer Inspection Program

Status help

What Common Permit Statuses Mean

Draft The application has not been fully submitted. Complete the remaining fields and upload requirements.
Submitted The City received the application and is checking completeness.
Plan review Code, zoning, engineering, Fire or design review is underway.
Corrections required Read every comment, revise the correct sheets and upload one coordinated set.
Board approval pending A Building Review Board, Historic Preservation, Plan Commission or ZBA step remains.
Approved Final fees, licenses, bonds or issuance steps may still remain.
Issued Construction may begin within the approved scope. Post the placard and keep plans on site.
Expired or open Contact the City before continuing work. An extension, revised permit or remaining inspection may be required.
Useful call scripts

What to Say When You Contact Lake Forest

Permit requirement:
“I am planning [exact work] at [address]. Can you confirm the correct permit packet, required survey or grading information, design-board review and inspections?”
Design review:
“The property is [inside/outside/not sure] a historic district. The project changes [demolition, addition, exterior material, scale or lighting]. Which commission or board must review it first?”
Plan-review correction:
“Permit [number] has comments from [reviewer]. I uploaded a numbered response and coordinated revised set. Can you confirm the resubmission is complete?”
Open-permit closeout:
“Permit [number] at [address] remains open. Which inspection, document, bond condition or certificate is still required to close the record?”
Final project control

Lake Forest Permit Completion Checklist

  • Correct permit packet selected
  • Current survey prepared
  • Zoning and setbacks checked
  • Design or historic approval completed
  • Tree and grading review completed
  • Contractor licenses current
  • Permit formally issued
  • Permit placard posted
  • Approved plans kept on site
  • Inspections scheduled at correct stages
  • Final inspection passed
  • Permit, certificate and bond closed
Permit office location

Lake Forest Community Development Map

Permit office: Community Development, Municipal Services Center, 800 N. Field Drive, Lake Forest, IL 60045.
Official resources

Open the Correct Lake Forest Permit Resource

Frequently asked questions

Lake Forest Building Permit FAQs

Where is the Lake Forest building-permit office?

Building permits are handled by Community Development at the Municipal Services Center, 800 N. Field Drive, Lake Forest, IL 60045—not at the City Hall address shown in the general website footer.

Where do I apply for a Lake Forest permit?

Use the City of Lake Forest BS&A Online portal. Register or sign in, choose Apply for a Permit and upload the signed project application and required construction documents.

How long does Lake Forest permit review take?

The City publishes an approximate five-business-day target for smaller projects and approximately 15 business days for larger projects. Incomplete documents or additional board, historic, engineering or Fire reviews can extend the process.

Does my project need Building Review Board approval?

It may if the property is outside a historic district and the project includes demolition, new construction, an addition, exterior alteration, building-scale variance, exterior lighting, signage, landscaping or a new-development site plan.

When is Historic Preservation Commission review required?

Commission review may apply when the property is inside a local historic district or is an individual landmark and the work includes demolition, new construction, additions, exterior alterations or a building-scale variance.

How do I schedule a Lake Forest inspection?

Sign in to BS&A, choose Schedule an Inspection, select the permit, choose the inspection type and available date, verify the contact information, add access notes and submit the request.

What must be at the job site for inspection?

Post the permit placard where it is visible from the street and keep the approved plans available electronically or in hard copy. The work must remain visible and safely accessible.

How long is a Lake Forest building permit valid?

The City says permits are valid for 12 or 18 months depending on scope, and work must begin within 90 days after issuance. Contact Community Development before expiration when an extension may be needed.

Can a homeowner apply without a general contractor?

The City application requires the property owner’s signature or an authorized designee form. Applicable plumbing, electrical, HVAC and roofing credentials are still required. Confirm the owner’s role with permit staff before submitting.

Is a home sewer inspection required before selling?

It is required before transferring water billing for a single-family residence or duplex. The published inspection fee is $150, and the inspection may be completed up to 120 days before the transfer.

Independent guide and freshness

Source and Update Notes

Building-Department.org is an independent informational guide and is not the City of Lake Forest. Permit applications, fees, inspections, design decisions and enforcement must be handled through the City or its authorized portal.

This page was rebuilt using current City Community Development pages, BS&A services, 2026 board and commission information, permit checklists, code information, inspection guidance, home sewer inspection rules and the May 2026 payment-scam alert.

Last reviewed: July 22, 2026.

Staff, forms, fees, meeting dates, code editions and procedures can change. Confirm time-sensitive details before filing, paying or beginning work.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.