St. Johns County permit action guide

Clear the Property, Submit the Permit and Pass St. Johns County Inspections in the Correct Order

Most St. Johns County building projects do not begin with the building-permit application. They begin with a parcel number and, in many cases, an approved Clearance Sheet.

This guide explains the county’s real workflow: property and jurisdiction check, Clearance Sheet, zoning and flood review, coastal and wetland screening, building application, contractor registration, fees, inspections before the 7:00 AM cutoff and final Certificate of Occupancy or Completion.

Clearance Sheet, permit search and plan-review tools
Same-day inspection scheduling before 7:00 AM
Coastal, flood, wetland, tree and impact-fee checks
St. Johns County Clearance Sheet moving through zoning, flood, coastal review, permit and inspection An animated parcel map and Clearance Sheet move through local review gates before reaching permit issuance and final inspection. PARCEL + SITE PLAN ZONING + SETBACKS FLOOD + ELEVATION COASTAL + WETLANDS CLEARANCE SHEET PERMIT + INSPECTIONS FINAL APPROVED
📄
Local step most applicants miss In most cases, St. Johns County accepts a building-permit application only after an approved Clearance Sheet. The Clearance Sheet establishes parcel, address, zoning, setbacks, flood, elevation, driveway, coastal and site-development information.
🕖
Same-day inspection cutoff Inspections scheduled before 7:00 AM are performed the same day. Requests or cancellations after 7:00 AM may require direct contact with the inspector to avoid a service fee.
Start here

Choose the St. Johns County Task You Need

Official department information

St. Johns County Building Department Contact Details

Building permits 904-827-6800 bldcodes@sjcfl.us
Inspection system 904-827-6842 Schedule, cancel or check results
Contractor licensing 904-827-6820 conlicen@sjcfl.us
Building fax 904-827-6849 Confirm before faxing time-sensitive material
Contractor fax 904-827-6847 Insurance and licensing documents
Office address 4040 Lewis Speedway St. Augustine, FL 32084
Office hours Monday–Friday 7:30 AM–4:30 PM
Make the call useful: Have the full address, Parcel ID, Clearance Sheet number, permit number, contractor name and the exact portal message ready.
Check the permit authority

County Permit or Municipal Permit?

Use St. Johns County when

  • The property is in unincorporated St. Johns County
  • The county Property Appraiser returns the parcel
  • County zoning and Land Development Code apply
  • The county permit search recognizes the property

Verify first when

  • The property is inside the City of St. Augustine
  • The property is inside St. Augustine Beach
  • The mailing address differs from the municipality
  • The parcel lies near a city boundary
Do not decide jurisdiction from “St. Augustine” in the mailing address. Confirm the parcel and governing municipality before paying a Clearance Sheet or permit fee.
Local pre-permit requirement

What Is a St. Johns County Clearance Sheet?

It identifies the parcel

  • GIS address
  • Parcel number
  • Zoning district
  • Future-land-use information

It establishes site limits

  • Zoning setbacks
  • Minimum floor elevation
  • Driveway review
  • Lot-grading requirements

It screens environmental issues

  • Flood zone
  • Wetland and upland buffer
  • Protected trees
  • Coastal-control boundaries
Do not clear or fill the lot first. County guidance says no land clearing, placement of fill, structures, septic tanks, drainage changes or protected-tree removal should occur before Clearance Sheet approval.
Project
Clearance Sheet status
Why it matters
New single-family residence
Normally required
Sets address, setbacks, flood elevation, driveway and site-development conditions.
Residential addition
Normally required
Checks structure location, lot coverage, setbacks, drainage and environmental limits.
Accessory structure, shed, pool or garage
Normally required
Confirms location, easements, setbacks, buffers and existing structures.
Mobile home
Normally required
Coordinates site, address, zoning, utilities, septic and flood review.
Commercial addition or remodel
May be required
Checks proposed use, site conditions, zoning, flood and earlier development approvals.
New commercial development
After DRC approval
New commercial projects obtain Clearance Sheet approval after Development Review Committee approval.
Validity: The county’s published Clearance Sheet procedure says a residential Clearance Sheet is valid for six months unless a building permit has been issued.

St. Johns County Permit Route Finder

Select your project to see the most practical official next step.

Correct application sequence

Apply for a St. Johns County Permit Without Skipping a Required Review

Confirm jurisdiction
Find Parcel ID
Obtain Clearance Sheet
Prepare permit package
Complete plan review
Issue and record NOC
Inspect and close

Confirm the property and Parcel ID

Search the Property Appraiser records and save the exact Parcel ID. The county says this number is needed to begin the permit process.

Do not copy an old permit address blindly: Confirm the current parcel and legal property information.

Determine whether a Clearance Sheet is required

Most new homes, additions, accessory structures, mobile homes and many commercial projects need the pre-permit site review.

Start early: The Clearance Sheet may involve zoning, flood, driveway, coastal, wetland, tree and utility reviewers.

Prepare the detailed site plan

Show the parcel, dimensions, roads, structures, setbacks, driveways, easements, water, wetlands, trees and applicable coastal information.

Make it measurable: Show actual distances from structures to property lines—not only a rough sketch.

Open the correct building application and checklist

Use the county’s official forms page for building, demolition, electrical, plumbing, HVAC, gas, irrigation, solar, mobile-home and coastal applications.

Submit a coordinated permit package

Include the application, Clearance Sheet, site plan, construction plans, product approvals, energy documents, contractor information and project-specific affidavits.

Use clear file names: Clearance-Sheet.pdf, Site-Plan.pdf, Architectural.pdf, Structural.pdf and Product-Approvals.pdf.

Track the permit and plan-review log

Use Permit Status for holds and inspections. Use the Plan Log to read discipline-specific review comments.

Reply once, completely: Address every comment and identify the revised page or document.

Pay fees and confirm formal issuance

Review permit, plan-review, trade and impact fees. Do not begin because an application was submitted or approved; confirm that the permit is issued.

Record the Notice of Commencement when required

For permitted projects exceeding $5,000, county guidance requires a recorded Notice of Commencement before the first Building Services inspection.

Post it: The current county NOC form states that the recorded notice must be posted at the job site before the first inspection.

Complete inspections before covering work

Schedule the correct inspection, keep approved documents onsite and correct every failed item before requesting reinspection.

Obtain Certificate of Occupancy or Completion

It is unlawful to occupy a building before the required Certificate of Occupancy or Completion has been issued.

Permit decision table

Match the Project to the Correct County Permit Path

Project
Start with
Additional review to check
New single-family home
Clearance Sheet + building permit
Flood, zoning, driveway, septic/well or utility, trees, wetlands, coastal and impact fees
Residential addition or detached garage
Clearance Sheet + building permit
Setbacks, lot coverage, drainage, flood elevation, product approvals and trade permits
Shed or accessory structure
Clearance Sheet review
Structure size, location, setbacks, easements, anchoring and flood requirements
Pool, spa or enclosure
Clearance Sheet + pool permit
Barrier, electrical, easements, wetlands, flood zone and drainage
Roof, windows, doors or siding
Building permit
Product approval, wind design, structural repairs and flood substantial-improvement review
Electrical, plumbing, HVAC or irrigation
Trade permit
Licensed and county-registered contractor; online private account
Solar photovoltaic system
Solar and electrical documents
Structural attachment, product data, electrical diagram and utility coordination
Commercial buildout or renovation
Commercial sufficiency review
Use, occupancy, accessibility, Fire, zoning, health, utilities and CO
New commercial site
Development Review Committee
Construction plans, paving, drainage, utilities and later Clearance Sheet approval
Dock, bulkhead or coastal armoring
Coastal and environmental review
CCCL, state permits, wetlands, flood design and county authorization
Application preparation

What to Prepare Before Submission

Property and site

  • Parcel ID
  • Correct site address
  • Lot, block and subdivision
  • Boundary dimensions
  • Roads and driveways
  • Easements and waterways

Plans and project scope

  • Detailed scope of work
  • Construction valuation
  • Existing structures
  • Proposed structures
  • Zoning setbacks
  • Energy and product documents

Environmental and approvals

  • Flood-zone information
  • Finished-floor elevation
  • Wetland jurisdictional line
  • Upland buffer
  • Protected-tree locations
  • Coastal-control line
Detailed site-plan checklist

What the Clearance Sheet Site Plan Should Show

Site-plan item
What to show
Common mistake
Scale
A readable drawing scale and full parcel boundaries
Submitting an unscaled sketch or aerial screenshot
Property details
Lot, block, subdivision, dimensions, streets and roads
Leaving out the recorded subdivision information
Structures
Every existing and proposed structure, use, dimensions and setbacks
Showing only the new structure
Driveways and easements
Driveway, access, easements, patios, AC pads and impervious areas
Locating improvements inside an easement
Wetlands
State jurisdictional wetland line and required upland buffer
Using an approximate wetland edge without qualified confirmation
Trees and habitat
Specimen or historic trees and applicable conservation or habitat areas
Clearing vegetation before review
Coastal property
Coastal Construction Control Line when any part of the lot is seaward of it
Assuming beachfront location is handled only through the building plans
Well and septic
Existing and proposed well and septic systems
Applying for installation before Clearance Sheet approval
Drainage and elevation
Finished-floor elevation, waterways and lot-grading information
Ignoring how fill or grading affects adjacent land
Inspection scheduling

Schedule St. Johns County Inspections Correctly

Schedule by phone

904-827-6842

Use the touch-tone system and have the permit number and correct inspection request number ready.

Schedule online

A Building E-Services private account is required to schedule or cancel inspections online.

Open private-account login

Same-day cutoff

Inspections scheduled before 7:00 AM are performed the same day.

Check the permit first for holds or missing requirements.

Before requesting

  • Permit is issued and active
  • Correct inspection code selected
  • Required work is complete
  • Work remains visible
  • NOC is recorded when required
  • Permit has no unresolved hold

Before the inspector arrives

  • Safe access is provided
  • Address is visible
  • Approved plans are onsite
  • Permit documents are onsite
  • Correction list is onsite
  • Animals and gates are secured
Do not cover work before approval. The permit holder must provide access and leave components visible when inspection is required. Covering framing, wiring, plumbing, gas, insulation or structural work can require removal.
Failed and canceled inspections

What to Do After a Disapproved Inspection

Read the complete correction list

Do not rely on a short verbal summary. Check the permit record and contact the assigned inspector when clarification is needed.

Correct every listed item

Confirm the correction matches the approved plans, code requirement and inspector’s written direction.

Keep the correction list onsite

The county specifically tells applicants to have the correction list available when the reinspection occurs.

Reschedule only when ready

Repeatedly requesting an inspection before corrections are complete can create service or reinspection fees.

Cancellation: When an inspection is canceled after 7:00 AM on the scheduled day, contact the inspector directly to avoid a service fee.
Coastal, flood and environmental review

Complete These Property Checks Before Final Design

Special Flood Hazard Area

Development in Zones A, AE, AH, AO and VE must comply with county floodplain and Florida Building Code requirements.

New construction and substantial improvements may need elevation and flood-resistant design documents.

50% substantial-improvement rule

An improvement costing at least 50% of the structure’s pre-improvement market value is treated as a substantial improvement.

Substantially damaged structures may require full flood compliance.

Coastal Construction Control Line

The site plan must identify the CCCL when all or part of the parcel lies seaward of the line.

State environmental authorization may also be required.

Wetland line and buffer

Show the jurisdictional wetland line and the applicable 25-foot or 50-foot upland buffer.

A qualified wetland scientist may be needed.

Protected trees and habitat

Identify specimen or historic trees, conservation easements, gopher-tortoise burrows and listed-species habitat when applicable.

Sea-turtle lighting

Properties in a coastal area may be subject to sea-turtle lighting rules.

The county site-plan checklist lists 904-209-0323 for turtle-lighting information.

Floodplain development requires a permit. St. Johns County says any development wholly or partly inside a Special Flood Hazard Area requires construction approval.
Contractor registration

Verify the Contractor Before the Permit Is Submitted

State-certified registration package

  • Florida state license
  • Active Sunbiz record
  • Liability insurance certificate
  • Workers’ compensation certificate or exemption
  • State license contact form
  • Matching company names on every document

County matching rule

The state license, corporate registration, insurance and workers’ compensation documents must match.

Send updates to conlicen@sjcfl.us or fax 904-827-6847.

Before hiring: Search the county contractor database and verify that the contractor is registered and permitted to work under the correct license.

Search Registered Contractors

Owner-builder decision

St. Johns County Owner-Builder Rules

Personal appearance

The owner must personally appear and sign the owner-builder affidavit in the Building Services Division.

Allowed project types

The current affidavit covers a one- or two-family residence, farm outbuilding or a commercial building costing no more than $75,000.

Own use or occupancy

The property cannot be built or improved for sale or lease under the exemption.

One-year presumption

If the improved property is sold or leased within one year after completion, the law presumes it was improved for sale or lease.

Direct supervision

The owner-builder must provide direct, onsite supervision and cannot hand responsibility to an unlicensed contractor.

Employer responsibilities

An owner employing workers may have tax, workers’ compensation and injury-liability responsibilities.

Do not pull an owner-builder permit for someone acting as your contractor. The owner becomes the legally and financially responsible party of record.

Read the Owner-Builder Affidavit

Current fee planning

Building, Reinspection and Impact Fees

Building permit basics

  • Permit issuance fee: $14
  • Permit extension fee: $37
  • Plan review: generally one-half of building-permit fee
  • Permit transfer: $53

Inspection and enforcement

  • Inspection/reinspection fee: $53
  • Safety inspection: $37
  • After-hours inspection requires approval
  • Building work started without a permit: double applicable fee plus $200

Use the official estimator

The county provides separate calculators for building/mobile-home and trade permit fees.

Open the county cost estimator

Fees can stack: Building, plan review, electrical, plumbing, mechanical, gas, irrigation, fire, Clearance Sheet, impact and outside-agency fees may be separate.
2026 impact-fee examples

Current Residential Impact Fees by Unit Size

Residential unit size
Current total impact fee
Included categories
Under 800 square feet
$11,074
Roads, buildings, law enforcement, fire/rescue, parks and schools
801–1,250 square feet
$14,597
Roads, buildings, law enforcement, fire/rescue, parks and schools
1,251–1,800 square feet
$16,583
Roads, buildings, law enforcement, fire/rescue, parks and schools
1,801–2,500 square feet
$20,652
Roads, buildings, law enforcement, fire/rescue, parks and schools
2,501–3,750 square feet
$25,647
Roads, buildings, law enforcement, fire/rescue, parks and schools
3,751–5,000 square feet
$28,855
Roads, buildings, law enforcement, fire/rescue, parks and schools
5,001 square feet or more
$30,332
Roads, buildings, law enforcement, fire/rescue, parks and schools
Current phase: The county identifies these as its 2026 Phase 1 impact fees, effective March 4, 2026. Credits, prior use and project classification can change the amount due.

Open Current Impact-Fee Schedules

Permit status help

What Common Permit Statuses Mean

Clearance Sheet pending One or more zoning, flood, driveway, coastal or site reviewers have not completed review.
Plan review pending The building application is under technical review. Check the Plan Log for comments.
Plans rejected Correct every reviewer comment and submit a complete revision package.
Hold or release required A document, payment, contractor registration or outside-agency release remains unresolved.
Permit issued Work may begin within the approved scope and conditions.
Inspection disapproved Complete corrections and keep the correction list onsite before rescheduling.
Final inspection approved Construction inspection is complete, but verify all trade permits and certificate requirements.
CO or Completion issued The required final approval has been issued for occupancy or completion.
Permit and property records

Search Permits, Plans, Inspections and Certificates

Search the public permit database

Search by permit number first. You can also use the project address, Parcel ID, contractor, license number or Clearance Sheet number.

Check the Plan Log

Use the Plan Log to locate review comments by permit, parcel, address, project or contractor.

Review inspection history and CO status

Open the full permit record and check inspections, holds, releases and Certificate of Occupancy status.

Request plans or the permit package

Use the Permit Center public-records request when detailed plans, job copies or older attachments are not available online.

Provide: Project name, address, Parcel ID, permit number and the exact document requested.

Email Records Management when needed

publicrecordsbldg@sjcfl.us · 904-827-6822

Portal problem: The county’s permit-search page currently warns that Google Chrome may not work correctly. Try another browser when the search page does not load or respond.
Open permit recovery

What to Do When an Old Permit Was Never Closed

Collect the record

  • Permit number
  • Clearance Sheet number
  • Property address
  • Parcel ID
  • Approved plans
  • Inspection history

Ask the department

  • Which inspections remain?
  • Is the permit expired?
  • Can it be reactivated?
  • Are revised plans required?
  • Must the contractor be changed?
  • What proves final closure?
Code and contractor complaints

Report Unpermitted or Unlicensed Construction

Unlicensed activity

Contact Contractor Licensing at 904-827-6820 or conlicen@sjcfl.us.

The county also accepts Building Department PRIDE cases, including anonymous reports.

Floodplain development

To report suspected illegal floodplain development, the county lists Code Enforcement at 904-209-0675, option 6.

Immediate danger: Call 911 for an active collapse, fire, gas leak, exposed live wiring or another urgent threat.
Ready-to-use call scripts

What to Say When You Contact the County

Clearance Sheet question
“I am proposing [exact project] at [address and Parcel ID]. Can you confirm whether a Clearance Sheet is required and which zoning, flood, driveway, coastal or environmental reviewers will be involved?”
Building permit question
“My Clearance Sheet number is [number]. Which building application, sufficiency checklist, plans, affidavits and trade permits are required for [project]?”
Inspection question
“I need inspection request number [code] for permit [number]. The work is complete, visible and accessible. Can you confirm there are no holds that will prevent the inspection?”
Open permit question
“Permit [number] at [address] does not appear closed. Which inspection, fee, release or final document remains outstanding?”
Final project control

St. Johns County Permit Closeout Checklist

  • Correct jurisdiction confirmed
  • Parcel ID verified
  • Clearance Sheet approved
  • Site plan matches project
  • Zoning and setbacks confirmed
  • Flood and elevation requirements completed
  • Wetland and coastal issues resolved
  • Contractor registration verified
  • Permit formally issued
  • NOC recorded and posted when required
  • Approved plans kept onsite
  • Inspection requests made before cutoff
  • Disapproved items corrected
  • All trade finals passed
  • Impact and permit fees paid
  • CO or Completion issued
Office location

St. Johns County Building Department Map

Address: 4040 Lewis Speedway, St. Augustine, FL 32084.
Building permits: 904-827-6800.
Hours: Monday–Friday, 7:30 AM–4:30 PM.
Official resource library

St. Johns County Permit Tools, Forms and Records

Frequently asked questions

St. Johns County Building Department FAQs

What is the official St. Johns County building-permit portal?

St. Johns County uses its Building E-Services and WATS online tools for permit search, plan-review logs, Clearance Sheets, contractor search, fee estimates, uploads and private-account services. The old page’s Accela instructions are not the county’s current official workflow.

Do I need a Clearance Sheet before a building permit?

In most cases, yes. The county says building-permit applications are generally accepted only after a Clearance Sheet has been issued. New homes, additions, accessory structures, mobile homes and many commercial projects commonly require one.

What information is included on a Clearance Sheet?

A Clearance Sheet can include the GIS address, Parcel ID, flood information, zoning setbacks, minimum floor elevation, driveway review, comprehensive-plan information, impact fees and site-development requirements.

How early must I schedule an inspection for same-day service?

St. Johns County says inspections scheduled before 7:00 AM will be performed the same day. Use the telephone system at 904-827-6842 or a Building E-Services private account.

What happens if I cancel an inspection after 7:00 AM?

Contact the assigned inspector directly. The county warns that a cancellation submitted after 7:00 AM on the scheduled day may create a service fee when the inspector is not contacted.

When is a Notice of Commencement required?

County guidance requires a recorded Notice of Commencement before the first Building Services inspection for permitted projects exceeding $5,000. The recorded notice should also be posted at the job site.

Can a property owner pull an owner-builder permit?

An eligible owner may use the statutory owner-builder exemption, but must personally appear and sign the affidavit at Building Services, provide direct onsite supervision and accept legal and financial responsibility for the work.

How do I check whether a contractor is registered?

Use the county’s Contractor Search tool and search by contractor number, name or business name. Contractor Licensing can also be contacted at 904-827-6820 or conlicen@sjcfl.us.

How do I find an old permit, plan or Certificate of Occupancy?

Search the public permit database first. For plans, job copies or records not available online, use the Permit Center Public Records Request process or email publicrecordsbldg@sjcfl.us.

Can a building be occupied after the final work is complete but before the CO?

No. St. Johns County states that it is unlawful to occupy a building before the required Certificate of Occupancy or Certificate of Completion has been issued.

Source and accuracy note

Official St. Johns County Information Used

Building-Department.org is an independent informational guide and is not St. Johns County Government.

This page was checked against St. Johns County Building Department, Building Permits, Building Inspections, Online Permitting & Status, Clearance Sheet guidance, the residential site-plan checklist, Building Application & Forms, Contractor Licensing, Floodplain Management, Development Review, the FY2026 fee schedule and the current impact-fee schedule.

Last reviewed: July 23, 2026.

Fees, forms, inspection codes, review procedures, flood requirements and portal behavior can change. Confirm time-sensitive details with the county before filing, paying, clearing land or starting construction.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.