Redwood City Building Department | Permits, Inspections & Official Contact

Redwood City electronic permit guide

Upload the Correct Address-Named Files, Clear Plan Review and Protect Every Inspection

Redwood City accepts building permits and construction plans electronically through eTRAKiT. The application and every supporting file must be clearly named with the project address or the City may reject the intake package.

This guide explains the current 2026 code cycle, electronic application process, permit types, plan-review ranges, One-Stop service, inspections scheduled several days ahead, valuation-based fees, ADUs, SolarAPP+, construction-debris deposits, flood checks, Fire review and final closeout.

Correct eTRAKiT account, application and address-based filenames
Plan review, One-Stop, Fire, Planning, Engineering and flood dependencies
Current posted fees, inspection windows, C&D rules and permit expiration
Redwood City electronic building permit journey A digital construction plan moves upward beside a redwood tree through application, plan review, inspection and final approval. REDWOOD CITY eTRAKiT PLAN INTAKE PLAN REVIEW 1017 MIDDLEFIELD PERMIT APPLICATION FINAL INSPECTION APPROVED
!
Corrections to the existing page The official contact email is permits@redwoodcity.org—not building@redwoodcity.org. Applications use permits.redwoodcity.org/etrakit, not the outdated etrakit.redwoodcity.org address. Online inspection requests are currently scheduled approximately 3–8 days ahead, not automatically for the next business day.
i
New code effective January 1, 2026 Redwood City adopted the 2025 California Building Standards Code with local amendments. Complete 2026 applications should not use an outdated 2022-code cover sheet or calculations.
Start with one action

What Do You Need From Redwood City Building?

Redwood City Next-Step Finder

Select the project or permit problem that best matches your situation.

Official contact panel

Redwood City Building Department Phone, Email, Address and Hours

Permit Counter 650-780-7350 Applications, fees, plan review and general code questions
Permit email permits@redwoodcity.org Include the property address and permit number
Inspection line 650-780-7361 Phone cancellations during the transition period
Engineering 650-780-7380 Utilities, drainage, grading and right-of-way work
Fire Department 650-780-7400 Fire-safety review and construction inspections
Building address 1017 Middlefield Road Redwood City, CA 94063
Counter hours Mon–Thu, 10 AM–4 PM Virtual services are available during broader weekday hours
Walk-in warning: Counter service is first-come, first-served and depends on staffing and open appointment slots. Electronic submittal is strongly encouraged.
City or San Mateo County?

Confirm Jurisdiction Before Creating the Permit Record

RC

Use Redwood City Building when

  • The parcel is inside incorporated Redwood City.
  • The Community GIS identifies Redwood City jurisdiction.
  • The eTRAKiT address search returns the correct parcel.
  • Existing permits were issued by the City.
SM

Check San Mateo County when

  • The site is in Emerald Hills, North Fair Oaks or another unincorporated area.
  • The mailing address says Redwood City but the parcel is outside City limits.
  • eTRAKiT cannot locate the address.
  • An older permit identifies San Mateo County Building.
The Redwood City Fire Department also serves some unincorporated areas, but Fire service does not change building-permit jurisdiction. County projects are submitted through San Mateo County Building.

Open Community GIS Compare San Mateo County

Building versus Planning

Clear the Land-Use Rules Before Finalizing Construction Plans

Planning reviews

  • Allowed use and occupancy
  • Setbacks and lot coverage
  • Building height and floor area
  • Parking and driveway layout
  • Historic and precise-plan requirements
  • Redwood Shores planned-development or lagoon-bank rules

Building reviews

  • Structural design
  • Fire and life safety
  • Accessibility
  • Electrical, plumbing and mechanical systems
  • Energy and CALGreen compliance
  • Construction inspections and final approval
Permit decision table

Which Redwood City Permit Route Fits the Work?

Project
Starting route
Check before submitting
New single-family house or duplex
Full building permit
Planning, survey, utilities, Fire, drainage, C&D, energy and structural plans
Residential addition
Building plan review
Setbacks, lot coverage, fire-sprinkler threshold, structural and energy work
Kitchen or bathroom remodel
Building and trade review
Wall changes, fixtures, electrical, plumbing, ventilation and windows
Reroof
Roofing permit
Roof type, sheathing repair, solar coordination and C&D recycling
Shed or playhouse
120-square-foot exemption test
Zoning placement, utilities, use, wildfire provisions and floor area
Fence
Zoning plus seven-foot test
Pool barrier, visibility, height, retaining conditions and neighborhood rules
Retaining wall
Four-foot exemption test
Measure from footing bottom; surcharge, slope, drainage and property line
Electrical, plumbing or HVAC work
Trade permit
Contractor license, equipment specifications and related building scope
Commercial tenant improvement
Commercial plan review
Allowed use, licensed design professional, accessibility, Fire and occupant load
Accessory dwelling unit
ADU checklist plus building permit
Size, setbacks, utilities, fire flow, address, survey and homeowner survey
Residential solar
SolarAPP+ or standard solar permit
Eligibility, electrical service, battery scope, roof and structural information
Demolition
Demolition plus C&D plan
Utilities, salvage period, PCB or hazardous materials, Fire and site restoration
Correct electronic application sequence

Apply Through eTRAKiT Without Failing Intake

Confirm City jurisdiction and property information

Use Community GIS to check the address, parcel number, zoning, flood layers and City boundary.

Do not assume: A Redwood City postal address can still be outside incorporated City limits.

Choose the correct eTRAKiT account

Public users can self-register. Contractors with a valid Redwood City business license should obtain a contractor account by emailing permits@redwoodcity.org or calling 650-780-7350.

Complete the Building Permit Application

Enter the project address, APN, contractor or owner-builder declaration, workers’ compensation information, valuation, construction type, occupancy, zone and detailed scope.

Create the permit in eTRAKiT

Select the permit type matching the full project—not merely the fastest category available.

Name the application with the project address

The City’s example is “1017 Middlefield Permit Application.” Files without the address may not be accepted.

Upload plans and supporting documents

Construction plans, calculations, energy documents, surveys, specifications and supporting forms must also be clearly named with the project address.

Useful example: 1017-Middlefield-Architectural-Plans.pdf.

Wait for the assigned permit technician

Once the record and documents are successfully created, a technician is assigned and will provide next instructions.

Published response expectation: Initial follow-up may take up to five business days depending on workload.

Pay the plan-review portion

The current fee schedule states that 50% of the calculated Building Permit Fee is due during plan-check review. The remaining base balance is due for issuance.

Respond to every correction as a coordinated set

Update all affected sheets and calculations, clearly identify revisions and submit a response explaining where each comment was resolved.

Complete issuance conditions

Resolve Planning, Fire, Engineering, C&D, owner-builder, contractor, utility and outstanding fee requirements before construction.

Post the permit and protect the inspection record

The front of the permit card must be visible from the street in a weatherproof sleeve. Keep the complete approved plan set and job card onsite.

Open Official Submittal Steps Download Application

Electronic intake checklist

Prepare These Items Before Creating the Record

Application information

  • Project address and APN
  • Property owner
  • Applicant and project contact
  • Contractor license and business license
  • Complete scope
  • Total labor and material valuation

Construction documents

  • Site plan
  • Existing and proposed floor plans
  • Exterior elevations
  • Building sections
  • Structural drawings and calculations
  • Electrical, plumbing and mechanical plans

Supporting approvals

  • Title 24 energy documents
  • CALGreen information
  • Planning approval
  • Fire-safety information
  • Drainage and flood documents
  • C&D Waste Management Plan
Residential plan readiness

Show Enough Detail to Answer Building, Planning and Engineering Questions

Site plan

  • Street names
  • Lot dimensions
  • Front, side and rear setbacks
  • Easements
  • Existing and proposed structures
  • Parking and driveway

Architectural

  • Room names and dimensions
  • Existing and proposed walls
  • Doors and windows
  • Exterior elevations
  • Stairs, guards and handrails
  • Smoke and CO alarms

Structural

  • Footings and foundations
  • Floor and roof framing
  • Beams, headers and posts
  • Connections and anchors
  • Calculations
  • Special inspections

Energy and green building

  • 2025 code references
  • Title 24 forms
  • Insulation and glazing
  • HVAC efficiencies
  • Electrification requirements
  • CALGreen measures

Utilities and site work

  • Water and sewer service
  • Stormwater treatment
  • Grading and drainage
  • Flood-zone information
  • Encroachment work
  • Fire-flow information

Commercial and multifamily

  • Licensed architect or engineer
  • Occupancy and construction type
  • Occupant load and egress
  • Accessibility
  • Fire-resistance ratings
  • Fire sprinkler and alarm plans
Redwood City’s older residential checklist still mentions paper-set quantities, but the City now accepts only electronic permit and plan applications. Use the checklist for plan content—not as an instruction to deliver multiple paper sets.

Open Residential Plan Checklist

Plan review expectations

Use Published Review Ranges as Planning Estimates—not Promises

Project category
Published category estimate
Practical interpretation
Roofing and qualifying subpermits
Over the counter
Only properly scoped, complete work is eligible
New building
4–8 weeks
Planning, Engineering, Fire and corrections can extend the total process
Residential addition
3–4 weeks
Applies to a complete review cycle, not the full correction history
Residential structural review
3–4 weeks
Engineering quality and coordination affect timing
Residential alteration
3–4 weeks
Multiple trades or Planning review can add time
Commercial tenant improvement
4–8 weeks
Fire, accessibility and change-of-use review can be separate
Fire permit
4–8 weeks
Coordinate Fire comments with the Building plan set
Engineering construction permit
About 3 weeks
Incomplete utility, grading or right-of-way plans delay review
The City’s Building FAQ warns that current overall review times can range from 6–24 weeks depending on project scope. Use the longer current-queue warning for scheduling contracts and construction starts.
One-Stop plan review

Ask Whether a Narrow Project Qualifies for One-Stop Service

Before requesting One-Stop

  • Apply online for the building permit.
  • Wait until the application is accepted.
  • Obtain an assigned permit number.
  • Email permits@redwoodcity.org to request One-Stop service.

Published service window

  • Monday: 1:00–3:00 PM
  • Tuesday: 1:00–3:00 PM
  • Wednesday: 1:00–3:00 PM
  • Thursday: 1:00–3:00 PM
  • Friday: unavailable
One-Stop is not automatic and does not guarantee same-day issuance. Staff determines whether the scope and documents fit the service.

Open One-Stop Policy

January 2026 exemption guide

Some Work Avoids a Building Permit—but Not Zoning or Other Approvals

Work
Current building-permit exemption
Important limitation
Detached shed or playhouse
One story and no more than 120 square feet
Zoning, wildfire, use, utility and placement rules still apply
Fence
Not over seven feet, excluding pool barriers
Planning, visibility, retaining and neighborhood requirements can apply
Retaining wall
Not over four feet from footing bottom to wall top
No surcharge and no regulated liquid impoundment
Sidewalk or driveway
No more than 30 inches above grade, no lower story and not an accessible route
Engineering, drainage and right-of-way approval can still be required
Interior finish work
Painting, papering, tiling, carpeting, cabinets and countertops
Structural, electrical, plumbing, gas or mechanical changes require permits
Small prefabricated pool
Under 24 inches deep, no more than 5,000 gallons and entirely above ground
Larger pools require barrier, electrical and zoning review
Window awning
Qualifying residential awning projecting no more than 54 inches without additional support
Other occupancies or structural supports require review
Minor plumbing repair
Stopping a leak or clearing a blockage without replacing or rearranging concealed piping
Replacement of defective concealed pipes is new work requiring a permit
The exemption document explicitly states that an exemption does not authorize work that violates other City laws. Check zoning, Fire, flood, Engineering, HOA and utility requirements before relying on an exemption.

Open 2026 Exemption Guide

Inspection command center

Schedule Several Days Ahead and Check the Day-of Time After 9 AM

Inspection hours 9 AM–4 PM Monday through Friday
Current booking range 3–8 days ahead For online inspection requests
Day-of estimate After 9 AM Check Today’s Building Inspections
Arrival range Within 2 hours Of the posted estimated time

Have this ready before booking

  • Permit number
  • Project address
  • Exact inspection type
  • Contact name and phone
  • Complete work stage
  • Access instructions

Have this ready onsite

  • Permit posted from the street
  • Approved plans
  • Permit or job card
  • Qualified contractor employee or owner-builder
  • Safe access and required ladder
  • Test equipment and reports
Contractors must stand their inspections with a qualified employee onsite. An owner-builder must personally provide the approved plans, permit and job card. Missing documents or work that is not ready can result in additional inspection fees.

Open Inspection Scheduling Request in eTRAKiT

Inspection sequence

Do Not Cover Work Before the Required Approval

Inspection
Work that should be ready
Do not do yet
Footing
Excavation, forms and reinforcement complete and visible
Place concrete
Foundation
Forms, reinforcing, anchors, waterproofing or drainage at the required stage
Backfill or conceal required components
Underground trades
Electrical, plumbing or mechanical systems installed and tested
Pour slab or cover trenches
Rough trades
All concealed electrical, plumbing, gas and mechanical work complete
Install insulation or wall finishes
Framing
Structural framing, connectors and applicable rough approvals complete
Conceal framing
Insulation and energy
Insulation, air sealing and energy components fully installed
Install drywall
Trade finals
Fixtures, equipment, panels, controls and safety devices complete
Request an incomplete final
Building final
All construction, revisions, trade finals, Fire, Engineering and documents complete
Occupy before authorization
Permit expiration protection

A Passed Inspection Restarts the 365-Day Permit Clock

Initial validity

An issued Redwood City building permit is valid for 365 days from issuance.

Extension through inspection

Every passed field inspection extends the permit for another 365 days from that inspection date.

Expired permit

A permit issued within the current code cycle may qualify for one 365-day extension when there are no complaints or project issues.

The published one-time extension fee is the current minimum permit fee. Contact the assigned technician before expiration rather than assuming an old approval remains active.
Current posted schedule effective July 1, 2025

Estimate a Single-Family Building Permit From the Official Valuation Table

Plan-review payment 50% of base fee Due during plan-check review
Technology fee 13% Of the Building Permit Fee
General Plan fee 0.39% Of building valuation
Reinspection $201.78/hour Current posted hourly amount

Single-Family Base Fee Estimator

Enter the total construction valuation, including labor and materials. The tool applies the City’s current posted single-family table.

Single-family valuation
Published formula
$1–$500
$182.14
$501–$2,000
$182.14 for the first $500 plus $29.91 for each additional $100 or fraction
$2,001–$25,000
$630.76 for the first $2,000 plus $46.27 for each additional $1,000 or fraction
$25,001–$50,000
$1,694.93 for the first $25,000 plus $53.38 for each additional $1,000 or fraction
$50,001–$100,000
$3,029.54 for the first $50,000 plus $30.30 for each additional $1,000 or fraction
$100,001–$500,000
$4,544.75 for the first $100,000 plus $28.59 for each additional $1,000 or fraction
$500,001–$1,000,000
$15,981.80 for the first $500,000 plus $8.28 for each additional $1,000 or fraction
$1,000,001–$2,000,000
$20,120.59 for the first $1,000,000 plus $4.14 for each additional $1,000 or fraction
Above $2,000,000
Use the nonresidential and multifamily valuation table
This is not a complete project invoice. Electrical, plumbing, mechanical, Planning, Fire, Engineering, C&D, impact, strong-motion, state building-standard, utility and outside-consultant charges may be added.

Open Current Fee Page Open Full Master Fee Schedule

Selected current flat fees

Common Permit Amounts From the Posted Schedule

Project or service
Current posted amount
Important note
Residential kitchen or bathroom remodel
$1,244.65
Additional valuation, Planning or trade charges may apply
Residential reroof
$616.87
C&D diversion requirements apply to roofing
Shed
$302 + $66 per unit
A qualifying shed no larger than 120 square feet may be exempt
One- or two-car garage including electrical
$1,874.24
Planning and valuation-related fees may be separate
Garage for three or more cars
$2,506.26
Confirm floor area, use and Planning review
Residential solar, 15 kW or less
$450
SolarAPP+ charges and related electrical work may be separate
Residential solar, 16 kW or more
$450 + $15 per kW
Use the City’s invoice for the exact calculation
Inspection outside normal hours
$243.98 per hour
Two-hour minimum
Revision to submitted plan
$228.45
Additional plan-check time can also be billed
Reactivation of expired permit
$184.83
Eligibility and current-code implications must be reviewed
Construction and demolition debris

Submit the Waste Plan Before Issuance and the Final Report Within 60 Days

Covered work

  • All new construction
  • All demolition
  • All roofing
  • Additions or alterations valued at $50,000 or more

Diversion targets

  • At least 65% of construction, roofing and demolition debris
  • 100% of inert demolition material
  • Separate records for demolition and construction phases

Deposit and administration

  • Refundable deposit of at least $500 or $50 per estimated ton, whichever is greater
  • Current Master Fee Schedule administration charge: $277.25
  • Keep weight tags and salvage receipts
Official-source discrepancy: The January 2026 C&D packet still prints a $251.54 administration fee, while the City’s current Master Fee Schedule lists $277.25. Pay the amount on the current City invoice.
The January 2026 packet requires the final report and supporting receipts within 60 calendar days after final inspection or Certificate of Occupancy. An older City FAQ still says 90 days. Follow the shorter 60-day deadline.

Open January 2026 C&D Packet

ADU and solar routes

Use the Specialized Checklist Before Creating the Building Record

Accessory dwelling unit

  • Complete the ADU Completeness Checklist.
  • Submit plans, Building Permit Application and checklist in eTRAKiT.
  • A new detached ADU requires a fire-flow test.
  • The City lists a typical four-week fire-flow-test lead time.
  • Detached side and rear setbacks are generally at least four feet.
  • No impact fees are charged on ADUs under 750 square feet.
  • Complete the ADU homeowner survey before finalizing the permit.

SolarAPP+ automatic permit

  • Start in SolarAPP+ and obtain the approved compliance document.
  • Use the City’s SolarAPP+ guide to create the eTRAKiT permit.
  • Upload the SolarAPP+ approval and project documents.
  • Use the standard review route when the project is not eligible.
  • Battery, service-upgrade or unusual structural work may require added review.
ADU 0–400 sq. ft. $3,823.64 Also applies to qualifying garage conversion base fee
ADU 401–600 sq. ft. $4,455.66 Additional valuation and miscellaneous fees apply
ADU 601–800 sq. ft. $5,087.67 Use current City invoice as final amount
Redwood City’s pre-reviewed ADU program can reduce building-code review to approximately 30 days, but site, utility, Fire, Planning and project-specific conditions still require review.
Fire, flood and site dependencies

A Building Permit Does Not Replace Fire or Engineering Approval

Fire plan review

Plans for incorporated Redwood City are routed through the City Building Permit Technician. Fire review can apply to sprinklers, alarms, commercial work, multifamily projects and major residential changes.

Fire-sprinkler 50% rule

An addition and remodel can trigger residential sprinkler requirements depending on the project scope. Review the City’s policy before finalizing construction cost or area.

FEMA flood zone

Development or significant redevelopment within a Special Flood Hazard Area can require Chapter 41 compliance, elevation information and additional Engineering review.

Redwood Shores

Waterfront or lagoon-bank work can require Planning approval, a Planned Development Amendment, grading or landscaping review and a Building permit.

Public right-of-way

Sidewalk, driveway, curb, utility, sewer, street or excavation work can require a separate Engineering or Public Works permit.

Reach and energy codes

New residential, multifamily and commercial projects can be subject to Redwood City’s local all-electric and EV infrastructure requirements.

Owner-builder protection

Owner-Builder Status Transfers Construction Responsibility to the Property Owner

Application declarations

  • Identify the owner-builder exemption used.
  • Sign the owner-builder declaration.
  • Complete workers’ compensation information.
  • Disclose any construction lender.
  • Provide authorized-agent documentation when applicable.

Responsibilities accepted

  • Managing licensed subcontractors
  • Jobsite safety
  • Code compliance
  • Permit posting
  • Standing every inspection
  • Corrections and final approval
Commercial and multifamily construction must be performed by appropriately licensed contractors as required by California law. Do not use owner-builder status to allow an unlicensed person to operate as the general contractor.

Open Owner-Builder Forms Verify CSLB License

Construction activity rules

Follow Redwood City Work Hours and Keep Dumpsters Off the Street

Contractor construction hours

  • Monday–Friday: 7:00 AM–8:00 PM
  • Contractor weekend and City-holiday work is prohibited without written approval.
  • Submit a weekend or after-hours request at least 30 calendar days before the work.
  • Emergency work is handled separately.

Residential owner work

  • Residential property owners may work weekends and holidays from 9:00 AM–5:00 PM.
  • Permit, safety and noise rules still apply.
  • A contractor cannot use the owner’s weekend allowance.
Dumpsters, PODs and similar stationary containers may not be placed in the street. Published citations are $100 for the first day, $200 for the second day and $500 for the third and each later day.
Permit and property records

Search eTRAKiT First, Then Request Missing Plans or Documents

Search by permit number or address

Use the public eTRAKiT search to locate Building records and available status information.

Compare the address with Community GIS

Confirm the parcel, City jurisdiction, zoning and available mapped permit information.

Review every related permit

A project may have separate Building, electrical, plumbing, mechanical, Fire, Planning and Engineering records.

Verify the final inspection

An issued permit does not prove that the work passed final inspection or received occupancy approval.

Request unavailable records through the PRA portal

Provide the exact address, parcel, permit number, approximate year and record type needed.

City response process: A determination is typically made within 10 calendar days, with a possible statutory extension.

Open Public Records Portal

Permit status decoder

What to Check When the Application Stops Moving

Application not accepted Confirm that the application and every file contain the project address in the filename.
Waiting for technician Initial follow-up may take up to five business days depending on workload.
Planning hold Resolve use, setback, parking, height, historic, precise-plan or Redwood Shores conditions.
Engineering hold Resolve grading, drainage, flood, utilities, stormwater or right-of-way requirements.
Fire review pending Complete fire-flow, sprinkler, alarm, access or Fire plan-review requirements.
Corrections required Submit one complete coordinated response rather than disconnected revised sheets.
Approved but not issued Check contractor, owner-builder, C&D deposit and unpaid fee requirements.
Final inspection blocked Confirm revisions, trade finals, C&D, special inspections, Fire and Engineering closeout.
Troubleshooting

Fix Common Redwood City Permit Problems

Problem
Likely reason
Best next action
Application files were rejected
The address is missing from the filename or documents are incomplete
Rename every file with the exact project address and resubmit a complete package.
eTRAKiT does not find the address
Search format or unincorporated jurisdiction
Confirm the parcel in Community GIS and compare San Mateo County jurisdiction.
Review takes longer than the category estimate
Current queue, outside review or multiple correction cycles
Use the assigned technician and eTRAKiT status to identify the exact pending review.
Inspector cannot approve the work
Plans, job card or qualified onsite representative is missing
Prepare all documents and arrange the required onsite person before rescheduling.
Work was covered too early
Concrete, drywall, insulation or finishes were installed before inspection
Ask the inspector what must be exposed and inspected.
Permit is approved but cannot issue
C&D, contractor, Fire, Planning, Engineering or fee condition remains
Request a complete issuance checklist from the assigned technician.
C&D deposit has not been returned
Final report, receipts or diversion calculations are missing
Submit the complete final report within 60 days and confirm every waste stream.
Permit shows issued but property records are unclear
Final inspection or Certificate of Occupancy is missing
Check all inspections and request the final certificate or records through the City.
Ready-to-use communication

What to Say When You Contact the City

Permit-route question
“I plan to [describe exact work] at [full address and APN]. Which Building, Planning, Fire, Engineering and trade records are required?”
Intake question
“I created eTRAKiT record [number] and uploaded address-named files. Please identify the exact item preventing application acceptance.”
Inspection question
“I need the [inspection type] for permit [number]. The approved plans and job card are onsite, the work is visible and [qualified onsite contact] will be present.”
Closeout question
“Permit [number] appears complete. Which trade final, Fire, Planning, Engineering, C&D, report or occupancy item remains open?”
Final closeout checklist

Do Not Consider the Permit Finished Until These Are Confirmed

  • City jurisdiction confirmed
  • Planning and zoning approval complete
  • Correct eTRAKiT permit created
  • All files named with project address
  • Current 2025-code plans approved
  • Fire and Engineering approvals complete
  • C&D plan and deposit accepted
  • Contractor or owner-builder documents complete
  • Permit formally issued
  • Permit visible from the street
  • Approved plans and job card onsite
  • All revisions approved before inspection
  • Every trade and Building final passed
  • Occupancy and C&D closeout records saved
Building counter location

Redwood City Building Division Map

Address: 1017 Middlefield Road, Redwood City, CA 94063.
In-person Building counter: Monday–Thursday, 10:00 AM–4:00 PM, excluding legal holidays.
Call 650-780-7350 before visiting for project-specific help or to confirm staffing.
Official resources

Open the Correct Redwood City Permit Resource

Frequently asked questions

Redwood City Building Department Questions

How do I apply for a Redwood City building permit?

Create an account at permits.redwoodcity.org/etrakit, complete the Building Permit Application and upload the application, plans and supporting documents. Include the exact project address in every filename. An assigned permit technician will provide the next instructions.

What is the Redwood City Building Department phone number and email?

Call 650-780-7350 or email permits@redwoodcity.org. The counter is at 1017 Middlefield Road and is open for in-person Building service Monday through Thursday from 10:00 AM to 4:00 PM, excluding holidays.

Which building code applies to Redwood City permits in 2026?

Applications submitted under the current 2026 code cycle must comply with the 2025 California Building Standards Code and Redwood City’s local amendments, effective January 1, 2026.

Does a small shed, fence or retaining wall require a permit?

A qualifying one-story shed no larger than 120 square feet may be exempt. A fence not over seven feet may be exempt unless it is a pool barrier. A retaining wall not over four feet from footing bottom to wall top may be exempt when it does not support a surcharge. Zoning and other City rules still apply.

How do I schedule a Redwood City building inspection?

Request the inspection through eTRAKiT with the permit number, address, inspection type and contact information. Online inspections are currently scheduled approximately 3–8 days ahead. Check Today’s Building Inspections after 9:00 AM for the estimated time.

How long does Redwood City plan review take?

The category page lists approximately 3–4 weeks for many residential additions and alterations and 4–8 weeks for new buildings and tenant improvements. The current Building FAQ warns that total review can range from 6–24 weeks depending on scope and workload.

When does a Redwood City building permit expire?

An issued permit is valid for 365 days. Each passed field inspection extends it for another 365 days from the inspection date. Certain permits within the current code cycle may qualify for one 365-day extension.

How are Redwood City building permit fees calculated?

Most Building Permit Fees use a valuation table. For single-family work, the current published tiers begin at $182.14. Fifty percent of the calculated Building Permit Fee is due during plan review, with the remaining base balance due at issuance. Technology, General Plan and project-specific charges are additional.

What do I submit for a Redwood City ADU?

Submit the ADU Completeness Checklist, Building Permit Application and complete construction plans through eTRAKiT. A new detached ADU requires a fire-flow test, and homeowners must complete the City ADU survey before finalizing the permit.

How do I verify that an old Redwood City permit was completed?

Search eTRAKiT by permit number or address, review all associated trade permits and confirm the final inspection or Certificate of Occupancy. Request unavailable records through the City’s Public Records Act portal.

Source and accuracy note

Official Information Used for This Guide

Building-Department.org is an independent informational guide and is not the City of Redwood City.

This page was checked against Redwood City Building and Code Enforcement, eTRAKiT, electronic Permit Submittal instructions, current contact information, inspection scheduling, Building FAQs, One-Stop policy, plan-review estimates, January 2026 permit-exemption guide, Building Permit Application, Master Fee Schedule, January 2026 Construction and Demolition packet, Planning, ADU, SolarAPP+, Fire, Engineering, flood and public-record resources.

Last reviewed: July 22, 2026.

Portal functions, fees, code requirements, inspection availability, staff and department procedures can change. Confirm time-sensitive information with the City before submitting, paying, ordering materials or beginning construction.

Free Building Permit & Inspection Assistant

Check Permit Type, Estimate Fees, Prepare Inspections and Find Official Building Department Links

Use this free tool before applying for a building permit, booking an inspection, checking zoning rules, or searching permit records. It helps homeowners, contractors, landlords, buyers, and business owners understand the next step before visiting the official building department portal.

Start Permit Helper
8 toolsPermit finder, fee estimate, inspection checklist, zoning pre-check, and official searches.
All citiesWorks sitewide on city, county, village, and regional building department pages.
No loginNo address, permit number, email, or private data is required to use the tool.
Mobile-firstBuilt for visitors checking permits and inspections from a phone.

What building department task do you need help with?

Choose your goal. The tool will suggest the right next step, what to prepare, and which official page to check.

Homeowner tip

Before starting work, check whether your project needs building, zoning, electrical, plumbing, mechanical, right-of-way, or HOA approval.

Contractor tip

Many portals require contractor registration, license details, insurance, plans, owner authorization, and inspection scheduling access.

Building Permit Type Finder

Select the project type to understand which permits or reviews are commonly required. Always confirm with the official local building department.

Permit Fee Estimate Calculator

Estimate a rough permit fee using project value and common percentage-based review assumptions. Local minimum fees, technology fees, impact fees, reinspection fees, and trade fees can change the final amount.

Inspection Readiness Checklist

Use this before scheduling framing, electrical, plumbing, mechanical, roofing, final, or certificate-related inspections.

Zoning and Setback Pre-check

Use this before applying for a permit when your project may affect land use, setbacks, lot coverage, height, parking, signs, fences, accessory structures, or business use.

Plan Review Timeline Estimator

Estimate how complex your review may be. Local staffing, incomplete plans, corrections, holidays, fire review, zoning review, and outside agency review can change timing.

Permit Records Search Helper

Use this if you are trying to find old permits, inspection history, certificate of occupancy details, open permits, or code-related records.

Official Building Department Resource Finder

Enter city/county and state to create safe searches for official permit portals, inspection scheduling, building codes, zoning maps, forms, fees, and contact pages.

Building Department vs Planning/Zoning

  • Building Department: permits, plan review, inspections, code compliance, certificates.
  • Planning/Zoning: land use, setbacks, height, lot coverage, signs, parking, variances.

Best sitewide placement

Place this tool after the first main guide section or before FAQs. It turns a normal article into a practical permit-preparation page.

Important note

This tool gives educational guidance only. Final permit requirements, fees, inspections, forms, and deadlines must be confirmed with the official local building department.